Seismic Retrofit of the I155 Bridge at Caruthersville, Missouri - PowerPoint PPT Presentation

1 / 38
About This Presentation
Title:

Seismic Retrofit of the I155 Bridge at Caruthersville, Missouri

Description:

Tie Beam. Multiple Concrete Columns. Individual Pile Caps # 5 Hoops at ... Tie Beam. Truss Superstructure. Important elements of the earthquake resisting system ... – PowerPoint PPT presentation

Number of Views:496
Avg rating:3.0/5.0
Slides: 39
Provided by: capr1
Category:

less

Transcript and Presenter's Notes

Title: Seismic Retrofit of the I155 Bridge at Caruthersville, Missouri


1
Seismic Retrofit of the I-155 Bridge at
Caruthersville, Missouri
  • Mark R. Capron, P.E.
  • Jacobs

2
Presentation Overview
  • Project team
  • Description of the Bridge
  • 1993 - 1994 Study
  • Current Study
  • Summary

3
Project Team
  • MoDOT
  • Tennessee DOT
  • FHWA
  • Jacobs
  • Mid-America Earthquake (MAE) Center
  • Fuller Mossbarger Scott and May (FMSM)

4
MAE Center Overview
  • One of three Centers established by the National
    Science Foundation (NSF)
  • Funded by NSF, 8 core universities, and joint
    collaborative projects with industry

Mid-America Earthquake Center
5
Description of the Bridge
  • Bridge Structure
  • Missouri 1,030 ft concrete approach spans
  • Steel girder spans 2,150 ft, 2 girder,
    multi-girder
  • Two span truss 920 ft and 520 ft
  • Tennessee 2,480 ft concrete approach spans
  • Designed and built in 1970s

6
Concrete Approach Spans
Multiple Prestressed Concrete Girders
Composite Concrete Deck
Steel Bearings
Cap Beam
Multiple Concrete Columns
  • 5 Hoops at 12
  • Lap Splices

Tie Beam
Individual Pile Caps
H-Piles
Piers 2-14, 26-59
  • 18 Embedment in cap
  • No shear connectors
  • Driven 40 50 feet
  • No top reinforcement

7
Steel Approach Spans
Non-Composite Lightweight Concrete Deck
Steel Two-Girder System
Steel Bearings
Multiple Concrete Columns
  • 6 Hoops at 12
  • Lap Splices

Pile Cap
H-Piles
Piers 15-18
Piers 22-25
  • 36 Embedment in cap
  • No shear connectors
  • Driven 57 - 72 feet

Seal Course
8
Truss Spans
Non-Composite Lightweight Concrete Deck
Steel Bearings
Multiple Concrete Columns
Tie Beam
  • 6 Hoops at 12
  • Lap Splices

Concrete Caisson
Seal Course
Piers 19-21
9
Truss Superstructure
Hinge
Wind Transfer Device
Upper Lateral System
Deck Bearing System
Deck
Main Bearings
Lower Lateral System
Important elements of the earthquake resisting
system
10
Subsurface Conditions
  • River Alluvium
  • Loose sand or soft to firm clay
  • Upper 30 to 70 feet
  • Shear wave velocities 500 to 600 fps
  • Mississippi Embayment
  • Sand, gravel, and hard clay
  • Extends to bed rock at 2700 feet

11
Project Location
12
Located 6 Miles From New Madrid Fault
13
1993 1994 Seismic Study
  • Study phases
  • Evaluate existing structure (completed)
  • Retrofit feasibility study (completed)
  • Evaluation of the retrofitted structure
  • Final report and cost estimate
  • Criteria documents
  • FHWA seismic retrofitting guidelines
    FHWA/RD-83-007
  • FHWA seismic retrofitting manual FHWA-RD-94-052
  • Performance objectives
  • Life safety
  • No collapse

14
1993 1994 Seismic Study (continued)
  • Widespread liquefaction to depths of 40 feet
  • Dynamic settlement 3 to 17 inches
  • Lateral spreading 1 to 13 feet
  • Critical structural components have 25 to 60 of
    required capacity
  • Conceptual retrofit costs
  • 2.2 million restrainers only
  • 38.4 million full retrofit
  • MoDOT elected to hold project in 1994

Full retrofit of the bridge is a major project
15
Current Seismic Study
  • MoDOT selected Jacobs for completion of the
    Seismic Study
  • Advance the previous study
  • Develop alternative seismic retrofit strategies
    and conceptual cost estimates

16
Advancing the Previous Study
  • Ground motions
  • Incorporate peer review comments
  • Refine site specific ground motions
  • Refine site characterization
  • Liquefaction, evaluation and mitigation / ground
    failure
  • Incorporate peer review comments
  • Obtain additional soil data

17
Advancing the Previous Study
  • Structural retrofit
  • Large capacity isolation bearings and dampers
  • Push-over analysis of bents
  • State-of-the-art soil structure interaction
  • Conceptual cost estimates and constructability

Photo from Earthquake Protection Systems Inc.
18
Organization of the Current Study
Task A Geotechnical Hazard Assessment Studies
FMSM
Task B Evaluation of the Retrofitted Structure
Task C Non-Linear Analysis with Retrofit and SSI
Task D Quantities and Cost Estimates
19
Task A Geotechnical and Hazard Assessment Studies
  • Supplement 1993-1994 borings and construction
    records
  • Land borings SPT and CPT
  • Laboratory testing
  • Refraction/Reflection survey
  • Spectral Analysis of Surface Waves (SASW)

Photo from FMSM
20
Site Characterization
  • Six soil profiles selected along alignment

Vs (ft/sec)
21
Site Characterization
  • Small-aperture seismic array
  • Direct observation of spatial coherency from
    earthquake ground motions at small strains

22
Site-Specific Seismic Hazard Assessment
  • Earthquake sources
  • Updated Central US recurrence relations
  • Refined NMSZ characteristic earthquake models
  • Finite-source and rupture directivity effects
  • Seismic wave propagation
  • Constrained attenuation relations
  • Site effects
  • Detailed site characterization
  • Site response including effectsof deep, soft
    sediments
  • Liquefaction-relatedground failures

23
Site-Specific Design Spectra and Time Histories
  • Uniform hazard response spectra
  • 475, 1000 and 2,475-year return periods

Current Rock Spectra
Current Surface Spectra
Previous Rock Spectra
Previous Surface Spectra
24
Site-Specific Design Spectra and Time Histories
  • Time histories
  • Modified recorded time histories from other
    seismic zones
  • Two-component ground motions accounting for
    spatial coherency

25
Liquefaction Evaluation
  • Liquefaction initiation
  • Simplified method using detailed SPCPT profiles
    to evaluation liquefaction susceptibility
  • Shear wave velocity profiles
  • Permanent ground deformations
  • Empirical methods
  • MAE-developed models
  • Residual shear strength
  • Empirical methods based on SPT
  • Method based on critical state soil mechanics
  • Mitigation Alternatives

26
Task B Structural Evaluation
  • Linear multi-mode analysis
  • Existing structure with new site-specific ground
    motions
  • Existing structure with ground motions updated
    for soil modifications
  • Retrofitted Structure
  • Pseudo static push-over analysis
  • Large capacity isolation bearings in main span
  • C/D ratios for critical components

27
SAP2000 Model
4,245 Frame Elements 17,910 DOF
28
Task C Non-Linear Analysis with SSI
29
Structural Model SAP2000 and ZeusNL
Gap opening due to transverse rotation
Gap opening due to vertical rotation
30
Soil and Foundation Modeling
Soil Profile
5
10
15
20
25
30
35
40
45
50
55
59
Bent No.
270
1
3
250
Mississippi River
1
2
5
5
4
6
6
200
Elevation in feet
7
5
150
8
7
100
31
Foundation Types by Geometry
Soil Foundation Modeling
Type 1
Type 2
Type 3
Type 4
Type 5
Type 6
Type 8
Type 9
Type 10
Type 7
32
3-D Foundation Model
  • Foundation class 05 (Bent 10)

33
Foundation Property Evaluation
Soil Foundation Modeling
  • Lumped springs based on sophisticated soil model
  • Better approximation than closed-form spring
    derivation
  • Ignore interaction between different DOFs

34
Task D Quantities and Cost Estimates
  • Develop conceptual cost estimates for retrofit
    alternatives
  • Design Risks
  • Performance Objectives
  • Retrofit Levels
  • Constructability review

35
Alternative Retrofit Levels
  • Full retrofit
  • Ground improvement
  • Main spans
  • High capacity isolation bearings
  • Member and connection strengthening
  • Foundation modifications
  • Approach spans
  • Ductility enhancement
  • Foundation strengthening
  • Bearing replacement
  • Restrainers
  • Partial Retrofit
  • Retrofit to initiation of significant
    liquefaction and ground failures
  • Retrofit to initiation of significant foundation
    failures
  • Main spans only

36
Summary
  • Seismic retrofit of this bridge presents a
    challenging project
  • Seismic evaluation advances the previous study
    and combines state-of-the practice with
    state-of-the art
  • Study designed to develop retrofit alternatives

37
Acknowledgments
  • MoDOT
  • MAE Center
  • Amr Elnashai
  • Youssef Hashash
  • Aman Mwafy
  • Glenn Rix
  • Paul Bodin
  • FMSM

38
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com