ESCO Concept State of Israel Ministry of National Infrastructure - PowerPoint PPT Presentation

1 / 57
About This Presentation
Title:

ESCO Concept State of Israel Ministry of National Infrastructure

Description:

... of Heating, Refrigerating & Air Conditioning Engineers ... An industrial air compressor of 200 kW. With hours of operation assumed to be 3,500 hours/year ... – PowerPoint PPT presentation

Number of Views:100
Avg rating:3.0/5.0
Slides: 58
Provided by: mni98
Category:

less

Transcript and Presenter's Notes

Title: ESCO Concept State of Israel Ministry of National Infrastructure


1
ESCO ConceptState of IsraelMinistry of
NationalInfrastructure
  • Pierre Baillargeon
  • December 11, 2004
  • Jerusalem, Israel

2
Introduction to MV Protocol
  • A MV protocol is a set of standardized
    procedures used to quantify the amount of energy
    savings generated by a project
  • There are several sources that provide general
    protocols and approaches to MV
  • These should be adapted for each specific project

3
Introduction to MV Protocol
  • Essential component to insure success of energy
    efficiency projects (sustainability)
  • Allows to perform energy and demand savings
    calculations with accuracy
  • Proves that the guaranteed savings are achieved
  • Demonstrates to financiers that a cash-flow is
    generated
  • Awareness and information to customers employees
  • Accuracy acceptable

4
Introduction to MV Protocol
  • To allocate the risk related to variation in
    parameters affecting energy usage
  • To determine the efficiency of implemented
    equipments
  • To follow up the energy savings trend
  • To establish the monetary savings amounts

5
Introduction to MV Protocol
  • Principle of MV
  • Baseline A term often used in MV to refer to
    the energy usage prior to the installation of an
    energy efficiency project

6
Introduction to MV Protocol
  • It is then very important to assess a precise
    baseline
  • Not only the consumption history
  • Must include facility operation conditions
  • Hours of operation
  • Temperature maintained
  • Occupancy level
  • Production
  • Etc.

7
Introduction to MV Protocol
  • The adjustments take into account variation in
    parameters that affect consumption
  • Ex Production for a plant
  • The adjustments allow to see what would have been
    the consumption of the facility in the baseline
  • Or the corrected actual consumption

8
Introduction to MV Protocol
  • The energy savings cannot be measured directly
    (most often)
  • Either the Baseline or the Post-Retrofit values
    are theoretical
  • They represent what should have been the baseline
    consumption or the actual consumption without the
    energy consumption measures

9
Introduction to MV Protocol
  • Baseline Historic data Adjustment for weather
    (the theoretical value)

10
Introduction to MV Protocol
  • What is the scope of the measurement?

Measure Isolation
Whole building
11
Introduction to MV Protocol
  • Whole building
  • Usually the Baseline and the Post-Retrofit are
    based on the buildings utilities billing
  • There could be adjustment factors to take into
    consideration various changes
  • Changes between baseline period and actual period
    include occupancy, level of comfort, etc.

12
Introduction to MV Protocol
  • General guidelines to prepare a protocol has been
    developed over the years by various organizations
  • Most of them originate from US organizations

13
Well-Known MV Protocols
  • IPMVP International Performance Measurement and
    Verification Protocol
  • Collaborative effort of many countries. Initially
    funded by DOE
  • Now an independent organization EVO
  • Web site http//www.evo-world.org

14
Well-Known MV Protocols
  • FEMP Federal Energy Management Program
  • Provides guidelines and methods for measuring and
    verifying the savings associated with US federal
    agency performance contracts

15
Well-Known MV Protocols
  • EPA / MERVC Monitoring, Evaluation, Reporting,
    Verification, and Certification
  • EPA Environmental protection agency
  • Designed to include environmental impact
    assessments

16
Well-Known MV Protocols
  • ASHRAE 14P American Society of Heating,
    Refrigerating Air Conditioning Engineers
  • International engineering association
    (headquarters in USA) closely involved in energy
    efficiency
  • Covers well the cost-accuracy relationship for a
    protocol

17
Technical Aspects
  • Approach
  • The energy consumption before and after
    implementation of a measure can be determined by
    different methods
  • Direct measurements of equipment consumption and
    demands
  • Parameters agreed between the owner and the
    subcontractor/ESCO
  • Engineering calculations
  • Billing analysis
  • Computer simulations, ex. DOE-2
  • Or a mix of several above methods

18
The International Protocol (IPMVP)
Four Options
  • Option A Partially Measured Retrofit Isolation
  • Option B Retrofit Isolation with full
    measurement
  • Option C Whole Building
  • Option D Calibrated simulation

19
The International Protocol (IPMVP)
Four Options
  • Options A and B
  • Measure Isolation
  • Options C and D
  • Whole building approach

20
IPMVP - Option A Partially Measured Retrofit
Isolation
  • Option A
  • For simple measures where the hours of operation
    are considered constant
  • Or where an ESCO does not want to guarantee
    variations in operating hours that are under the
    control of customers
  • Or where the customer agrees with a simplified
    approach to reduce MV cost
  • Only the power reduction is measured in Option A

21
IPMVP - Option A Partially Measured Retrofit
Isolation
  • Comparison of the baseline and demand after
    measure implementation
  • Applicable to
  • individual systems or equipment
  • One or several equipments can be measured to
    obtain an average (sample size)
  • Can be a one-time measurement or repeated at
    regular intervals (months, year)

22
IPMVP - Option A Partially Measured Retrofit
Isolation
  • How
  • Savings calculated by measuring the power of
    specific equipment before and after EE
    implementation
  • Hours Estimated (agreed by contract for ESCO
    contract)
  • Energy consumption is calculated mathematically

23
IPMVP - Option A Partially Measured Retrofit
Isolation
  • Advantage low cost
  • Disadvantage low accuracy, high uncertainties
  • Often used for simple measures (light
    replacement, etc.) where hours of operation are
    easily estimated
  • Allows to verify if the installed equipment
    performance is the same as specified

24
IPMVP - Option A Power Measurement
  • The resulting savings can be affected by
  • variation of equipment efficiency
  • bad or non-functioning equipment
  • of construction cost 1-5
  • Accuracy 20

25
IPMVP - Option A Power Measurement
Example
  • An industrial air compressor of 200 kW
  • With hours of operation assumed to be 3,500
    hours/year
  • Tariff USD 0.12/kWh

26
IPMVP - Option A Power Measurement
  • Instantaneous measurement
  • prior and after EE measures
  • leaks and power reduced by 20
  • Savings (200 kW x 20) x 3,500 hrs x USD
    0.12/kWh
  • USD 16,800

27
Option B Retrofit Isolation
  • Measured demand and consumption approach
  • Demand and hours of operation are measured before
    implementation
  • Demand and consumption are also measured after
    implementation

28
Option B Retrofit Isolation
  • Applicable when the power varies
  • e.g. motors load variation in a variable speed
    system
  • Could be applied for short-term comparison (1
    hour, 1 week, 1 month)
  • Or for long term (continuous with savings
    monthly evaluation)

29
Option B Retrofit Isolation
  • How
  • Savings are calculated by comparing energy
    consumption of a given period before and after EE
    project implementation

30
Option B Retrofit Isolation
  • Advantage results are more accurate than in
    option A
  • Real hours of operation
  • Variation of demand accounted for
  • Disadvantage More complex and more expensive
    than option A
  • Require more equipment kW meter, hour meters or
    kWh loggers

31
Option B Retrofit Isolation
  • Accuracy/cost
  • of implementation cost 3-10
  • Accuracy 10-20

32
Option B Retrofit Isolation
Example
  • Same scenario as for option A
  • Compressor 200 kW
  • EE measures leak reductions
  • Measurements for consumption
  • Before
  • After

33
Option B Retrofit Isolation
  • Baseline
  • Data logger installed on compressor
  • For 1 entire week
  • Weekly consumption 14,200 kWh
  • Annual consumption calculated based on
    measurements
  • Company closes during three weeks/year
  • An. Cons. 14,200 x 49
  • 695,800 kWh/year

34
Option B Retrofit Isolation
  • Measurements after project implementation
  • Data logger on compressor
  • For two weeks 22,150 kWh
  • An. Cons. 22,150 x (49/2)
  • 542,675 kWh/year
  • Savings
  • (695,800-542,675) 153,125 kWh
  • Monetary
  • 153,125 kWh x USD 0.12/kWh
  • USD 18,375

35
Option C Whole Building
  • Whole facility approach using utility meter data
    (billing follow-up)
  • Appropriate for large-scale projects
  • Energy saving should be important (20 or more)
  • Important parameters affecting energy usage can
    be clearly identified (baseline and after
    implementation)

36
Option C Whole Building
  • Billing and adjustment factors are continually
    gathered
  • For the baseline period
  • After implementation
  • Often used for commercial buildings with simple
    adjustment factors
  • Industrial processes can also use this approach
    if adjustment factors are linear
  • Difficult for diversified production

37
Option C Whole Building
  • Appropriate to calculate the cumulative impact of
    projects in which components cannot be isolated
  • If individual measure saving evaluation is not
    required
  • Often the only approach to measure soft savings
    (training, awareness)

38
Option C Whole Building
  • When independent variables linked to the use of
    energy are simple and easy to monitor
  • Advantages C takes into account
  • entire installation
  • interactive effects between EE measures
  • Disadvantages
  • more expensive than option A or B
  • require monthly calculation

39
Option C Whole Building
  • Accuracy/Cost
  • of implementation cost 5-15
  • Accuracy 5-10 (annual)
  • Accuracy 20 (monthly)

40
Option C Whole Building
  • A cement industry implements an EE project with
    three EE measures
  • Burner replacement
  • Insulation of furnaces doors
  • Heat recovery system to produce hot water

41
Option C Whole Building
  • Project implemented in 2000
  • Baseline was 1999
  • Production increased by 20 from 1999 to 2001
    (linear relationship)
  • Energy bill of year 1999 was
  • USD 4.5 million
  • The adjusted baseline will be
  • 4.5 x 1.2 USD 5.4 million
  • Energy bill of 2006
  • USD 3.9 million
  • Savings for 2006
  • 5.4 3.9 USD 1.5 million

42
Option D Calibrated Simulation
  • Calibrated simulation approach
  • Savings determined by simulation
  • Computer model for the Baseline
  • Post-Retrofit either
  • Computer model
  • Real billing data

43
Option D Calibrated Simulation
  • For new constructions when the baseline cannot be
    established from history
  • When option C is too expensive or difficult to
    apply
  • Adjustment factor non linear
  • Too many changes to allow tracking
  • A calibrated model can be agreed between parties
    (customer ESCO)

44
Option D Calibrated Simulation
  • Advantages
  • Does not require field survey
  • Including interactive effects of individual EE
    measures
  • Disadvantages
  • Expensive if a detailed analysis is required
  • Simulation skills needed
  • GIGO (Garbage IN, Garbage OUT)

45
Option D Calibrated Simulation
  • Accuracy/Cost
  • of implementation cost 5-15
  • Accuracy 10

46
Option D Calibrated Simulation
  • A school is planning to add more m2 of classes
  • Two design approaches
  • Use same design as existing (baseline scenario)
  • Classes with EE lighting, ventilation with HE
    motors, VSD, high efficiency pumps
  • Air conditioning interaction to be considered

47
Option D Calibrated Simulation
  • Simulation for new extension
  • Done with DOE 2 software
  • Takes into account all operating parameters
  • Power, consumption, tariff, real number of
    production hours, etc.
  • Interactive effects of individual EE measures
  • Efficient motor dissipates less heat
  • Requires less air conditioning

48
Option D Calibrated Simulation
  • Simulation - reference scenario
  • Simulated energy bill of USD 160,000/yr
  • Simulation - EE scenario
  • Simulated energy bill of USD 130,000/yr
  • Savings estimated by comparison of the two
    simulations USD 30,000/yr

49
IPMVP Summary
  • Options
  • For measure isolation A B
  • For whole facility C D
  • Measurement period (usually)
  • One time (spot check) A, B, D
  • Limited time A, B, D
  • Entire Post-Retrofit Period C

50
MV Plan
  • For each individual project, the generic MV
    protocol selected (for instance IPMVP) must be
    adjusted
  • To exactly describe the steps, methods,
    measurements
  • It should be a clear, precise document showing
    all individual steps needed to perform the MV

51
MV Plan
  • Contents
  • Identification of the options for the MV plan
    for a measure
  • Baseline description
  • Historic data
  • Adjustment factors
  • Detailed procedures to be followed for the
    measurement campaign
  • Data to collect
  • Frequency
  • Sampling if large quantity of equipment
  • Who measures?
  • Who witnesses from the customers side?
  • Who should provide additional data?

52
MV Plan
  • Calculation method for savings
  • Rate structure to be used
  • In case of fuel switching, reference price
  • Minimum, maximum prices
  • MV cost vs accuracy analysis
  • Report frequency
  • Reporting format

53
Cost of Measurement and Verification
  • Varies according to
  • Selected MV option
  • Number of individual equipment measured
  • Frequency/duration of verification
  • Complexity of energy savings measures
  • Number of external factors affecting the results
    (adjustments)

54
Cost of Measurement and Verification
  • Varies according to (contd)
  • Number of similar energy savings measures
  • Required accuracy
  • Reporting requirement
  • Staff experience

55
Precision vs Cost
  • Higher precision means higher cost
  • Larger Sampling larger quantity of equipment to
    measure means higher cost for MV
  • Type of approach measuring power and
    kilowatt-hours (A) instead of partial isolation
    (B) need more equipment and resources
  • Higher frequency checking the savings at regular
    intervals (e.g. monthly) is more expensive than
    spot checking

56
Cost vs Savings
Savings
Monthly check
Cost of MV/Savings
Simple 1 time check
MV cost
Complexity of the process
57
Thanks
Write a Comment
User Comments (0)
About PowerShow.com