Title: ESCO Concept State of Israel Ministry of National Infrastructure
1 ESCO ConceptState of IsraelMinistry of
NationalInfrastructure
- Pierre Baillargeon
- December 11, 2004
- Jerusalem, Israel
2Introduction to MV Protocol
- A MV protocol is a set of standardized
procedures used to quantify the amount of energy
savings generated by a project - There are several sources that provide general
protocols and approaches to MV - These should be adapted for each specific project
3Introduction to MV Protocol
- Essential component to insure success of energy
efficiency projects (sustainability) - Allows to perform energy and demand savings
calculations with accuracy - Proves that the guaranteed savings are achieved
- Demonstrates to financiers that a cash-flow is
generated - Awareness and information to customers employees
- Accuracy acceptable
4Introduction to MV Protocol
- To allocate the risk related to variation in
parameters affecting energy usage - To determine the efficiency of implemented
equipments - To follow up the energy savings trend
- To establish the monetary savings amounts
5Introduction to MV Protocol
- Principle of MV
- Baseline A term often used in MV to refer to
the energy usage prior to the installation of an
energy efficiency project
6Introduction to MV Protocol
- It is then very important to assess a precise
baseline - Not only the consumption history
- Must include facility operation conditions
- Hours of operation
- Temperature maintained
- Occupancy level
- Production
- Etc.
7Introduction to MV Protocol
- The adjustments take into account variation in
parameters that affect consumption - Ex Production for a plant
- The adjustments allow to see what would have been
the consumption of the facility in the baseline - Or the corrected actual consumption
8Introduction to MV Protocol
- The energy savings cannot be measured directly
(most often) - Either the Baseline or the Post-Retrofit values
are theoretical - They represent what should have been the baseline
consumption or the actual consumption without the
energy consumption measures
9Introduction to MV Protocol
- Baseline Historic data Adjustment for weather
(the theoretical value)
10Introduction to MV Protocol
- What is the scope of the measurement?
Measure Isolation
Whole building
11Introduction to MV Protocol
- Whole building
- Usually the Baseline and the Post-Retrofit are
based on the buildings utilities billing - There could be adjustment factors to take into
consideration various changes - Changes between baseline period and actual period
include occupancy, level of comfort, etc.
12Introduction to MV Protocol
- General guidelines to prepare a protocol has been
developed over the years by various organizations - Most of them originate from US organizations
13Well-Known MV Protocols
- IPMVP International Performance Measurement and
Verification Protocol - Collaborative effort of many countries. Initially
funded by DOE - Now an independent organization EVO
- Web site http//www.evo-world.org
14Well-Known MV Protocols
- FEMP Federal Energy Management Program
- Provides guidelines and methods for measuring and
verifying the savings associated with US federal
agency performance contracts
15Well-Known MV Protocols
- EPA / MERVC Monitoring, Evaluation, Reporting,
Verification, and Certification - EPA Environmental protection agency
- Designed to include environmental impact
assessments
16Well-Known MV Protocols
- ASHRAE 14P American Society of Heating,
Refrigerating Air Conditioning Engineers - International engineering association
(headquarters in USA) closely involved in energy
efficiency - Covers well the cost-accuracy relationship for a
protocol
17Technical Aspects
- Approach
- The energy consumption before and after
implementation of a measure can be determined by
different methods - Direct measurements of equipment consumption and
demands - Parameters agreed between the owner and the
subcontractor/ESCO - Engineering calculations
- Billing analysis
- Computer simulations, ex. DOE-2
- Or a mix of several above methods
18The International Protocol (IPMVP)
Four Options
- Option A Partially Measured Retrofit Isolation
- Option B Retrofit Isolation with full
measurement - Option C Whole Building
- Option D Calibrated simulation
19The International Protocol (IPMVP)
Four Options
- Options A and B
- Measure Isolation
- Options C and D
- Whole building approach
20IPMVP - Option A Partially Measured Retrofit
Isolation
- Option A
- For simple measures where the hours of operation
are considered constant - Or where an ESCO does not want to guarantee
variations in operating hours that are under the
control of customers - Or where the customer agrees with a simplified
approach to reduce MV cost - Only the power reduction is measured in Option A
21IPMVP - Option A Partially Measured Retrofit
Isolation
- Comparison of the baseline and demand after
measure implementation - Applicable to
- individual systems or equipment
- One or several equipments can be measured to
obtain an average (sample size) - Can be a one-time measurement or repeated at
regular intervals (months, year)
22IPMVP - Option A Partially Measured Retrofit
Isolation
- How
- Savings calculated by measuring the power of
specific equipment before and after EE
implementation - Hours Estimated (agreed by contract for ESCO
contract) - Energy consumption is calculated mathematically
23IPMVP - Option A Partially Measured Retrofit
Isolation
- Advantage low cost
- Disadvantage low accuracy, high uncertainties
- Often used for simple measures (light
replacement, etc.) where hours of operation are
easily estimated - Allows to verify if the installed equipment
performance is the same as specified
24IPMVP - Option A Power Measurement
- The resulting savings can be affected by
- variation of equipment efficiency
- bad or non-functioning equipment
- of construction cost 1-5
- Accuracy 20
25IPMVP - Option A Power Measurement
Example
- An industrial air compressor of 200 kW
- With hours of operation assumed to be 3,500
hours/year - Tariff USD 0.12/kWh
26IPMVP - Option A Power Measurement
- Instantaneous measurement
- prior and after EE measures
- leaks and power reduced by 20
- Savings (200 kW x 20) x 3,500 hrs x USD
0.12/kWh - USD 16,800
27Option B Retrofit Isolation
- Measured demand and consumption approach
- Demand and hours of operation are measured before
implementation - Demand and consumption are also measured after
implementation
28Option B Retrofit Isolation
- Applicable when the power varies
- e.g. motors load variation in a variable speed
system - Could be applied for short-term comparison (1
hour, 1 week, 1 month) - Or for long term (continuous with savings
monthly evaluation)
29Option B Retrofit Isolation
- How
- Savings are calculated by comparing energy
consumption of a given period before and after EE
project implementation
30Option B Retrofit Isolation
- Advantage results are more accurate than in
option A - Real hours of operation
- Variation of demand accounted for
- Disadvantage More complex and more expensive
than option A - Require more equipment kW meter, hour meters or
kWh loggers
31Option B Retrofit Isolation
- Accuracy/cost
- of implementation cost 3-10
- Accuracy 10-20
32Option B Retrofit Isolation
Example
- Same scenario as for option A
- Compressor 200 kW
- EE measures leak reductions
- Measurements for consumption
- Before
- After
33Option B Retrofit Isolation
- Baseline
- Data logger installed on compressor
- For 1 entire week
- Weekly consumption 14,200 kWh
- Annual consumption calculated based on
measurements - Company closes during three weeks/year
- An. Cons. 14,200 x 49
- 695,800 kWh/year
34Option B Retrofit Isolation
- Measurements after project implementation
- Data logger on compressor
- For two weeks 22,150 kWh
- An. Cons. 22,150 x (49/2)
- 542,675 kWh/year
- Savings
- (695,800-542,675) 153,125 kWh
- Monetary
- 153,125 kWh x USD 0.12/kWh
- USD 18,375
35Option C Whole Building
- Whole facility approach using utility meter data
(billing follow-up) - Appropriate for large-scale projects
- Energy saving should be important (20 or more)
- Important parameters affecting energy usage can
be clearly identified (baseline and after
implementation)
36Option C Whole Building
- Billing and adjustment factors are continually
gathered - For the baseline period
- After implementation
- Often used for commercial buildings with simple
adjustment factors - Industrial processes can also use this approach
if adjustment factors are linear - Difficult for diversified production
37Option C Whole Building
- Appropriate to calculate the cumulative impact of
projects in which components cannot be isolated - If individual measure saving evaluation is not
required - Often the only approach to measure soft savings
(training, awareness)
38Option C Whole Building
- When independent variables linked to the use of
energy are simple and easy to monitor - Advantages C takes into account
- entire installation
- interactive effects between EE measures
- Disadvantages
- more expensive than option A or B
- require monthly calculation
39Option C Whole Building
- Accuracy/Cost
- of implementation cost 5-15
- Accuracy 5-10 (annual)
- Accuracy 20 (monthly)
40Option C Whole Building
- A cement industry implements an EE project with
three EE measures - Burner replacement
- Insulation of furnaces doors
- Heat recovery system to produce hot water
41Option C Whole Building
- Project implemented in 2000
- Baseline was 1999
- Production increased by 20 from 1999 to 2001
(linear relationship) - Energy bill of year 1999 was
- USD 4.5 million
- The adjusted baseline will be
- 4.5 x 1.2 USD 5.4 million
- Energy bill of 2006
- USD 3.9 million
- Savings for 2006
- 5.4 3.9 USD 1.5 million
42Option D Calibrated Simulation
- Calibrated simulation approach
- Savings determined by simulation
- Computer model for the Baseline
- Post-Retrofit either
- Computer model
- Real billing data
43Option D Calibrated Simulation
- For new constructions when the baseline cannot be
established from history - When option C is too expensive or difficult to
apply - Adjustment factor non linear
- Too many changes to allow tracking
- A calibrated model can be agreed between parties
(customer ESCO)
44Option D Calibrated Simulation
- Advantages
- Does not require field survey
- Including interactive effects of individual EE
measures - Disadvantages
- Expensive if a detailed analysis is required
- Simulation skills needed
- GIGO (Garbage IN, Garbage OUT)
45Option D Calibrated Simulation
- Accuracy/Cost
- of implementation cost 5-15
- Accuracy 10
46Option D Calibrated Simulation
- A school is planning to add more m2 of classes
- Two design approaches
- Use same design as existing (baseline scenario)
- Classes with EE lighting, ventilation with HE
motors, VSD, high efficiency pumps - Air conditioning interaction to be considered
47Option D Calibrated Simulation
- Simulation for new extension
- Done with DOE 2 software
- Takes into account all operating parameters
- Power, consumption, tariff, real number of
production hours, etc. - Interactive effects of individual EE measures
- Efficient motor dissipates less heat
- Requires less air conditioning
48Option D Calibrated Simulation
- Simulation - reference scenario
- Simulated energy bill of USD 160,000/yr
- Simulation - EE scenario
- Simulated energy bill of USD 130,000/yr
- Savings estimated by comparison of the two
simulations USD 30,000/yr
49IPMVP Summary
- Options
- For measure isolation A B
- For whole facility C D
- Measurement period (usually)
- One time (spot check) A, B, D
- Limited time A, B, D
- Entire Post-Retrofit Period C
50MV Plan
- For each individual project, the generic MV
protocol selected (for instance IPMVP) must be
adjusted - To exactly describe the steps, methods,
measurements - It should be a clear, precise document showing
all individual steps needed to perform the MV
51MV Plan
- Contents
- Identification of the options for the MV plan
for a measure - Baseline description
- Historic data
- Adjustment factors
- Detailed procedures to be followed for the
measurement campaign - Data to collect
- Frequency
- Sampling if large quantity of equipment
- Who measures?
- Who witnesses from the customers side?
- Who should provide additional data?
52MV Plan
- Calculation method for savings
- Rate structure to be used
- In case of fuel switching, reference price
- Minimum, maximum prices
- MV cost vs accuracy analysis
- Report frequency
- Reporting format
53Cost of Measurement and Verification
- Varies according to
- Selected MV option
- Number of individual equipment measured
- Frequency/duration of verification
- Complexity of energy savings measures
- Number of external factors affecting the results
(adjustments)
54Cost of Measurement and Verification
- Varies according to (contd)
- Number of similar energy savings measures
- Required accuracy
- Reporting requirement
- Staff experience
55Precision vs Cost
- Higher precision means higher cost
- Larger Sampling larger quantity of equipment to
measure means higher cost for MV - Type of approach measuring power and
kilowatt-hours (A) instead of partial isolation
(B) need more equipment and resources - Higher frequency checking the savings at regular
intervals (e.g. monthly) is more expensive than
spot checking
56Cost vs Savings
Savings
Monthly check
Cost of MV/Savings
Simple 1 time check
MV cost
Complexity of the process
57Thanks