Title: The Project Management Framework and Integration Management
1The Project Management Framework and Integration
Management
Presentation by Daisuke Kitakado, Hitoshi
Namura, Calvin Tay
2Project Phases Project Lifecycle
Source Preparing for PMP Exam (Vijay Kanabar)
P-33
3Project Management Framework
Source PMP Exam Prep (Rita Mulcahy) P-24
4Project Management Framework
Source PMP Exam Prep (Rita Mulcahy) P-24
5Project Management Framework
Source PMP Exam Prep (Rita Mulcahy) P-24
6Project Management Framework
Source PMP Exam Prep (Rita Mulcahy) P-24
7 Organizational Structures
- Functional Organization
- Projectized Organization
- Matrix Orgs (Strong/Balanced/Weak)
- Composite Organization
8Functional Organization
Project Coordination
- Project Manager has little or no authority
- Perceived scope of project limited to boundaries
of function
Source Preparing for PMP Exam (Vijay Kanabar)
P-35
9Matrix (Weak) Organization
Project Coordination
- Very similar characteristics to a functional
organization
Source Preparing for PMP Exam (Vijay Kanabar)
P-37
10Matrix (Balanced) Organization
CEO
Functional Mger (Eg. Engineering)
Functional Mger (Eg. Marketing)
Functional Mger (Eg. Manufacturing)
Functional Mger (Eg. Human Res)
Project Coordination
Staff
Staff
Staff
Staff
Project Manager
Staff
Staff
Staff
Source Preparing for PMP Exam (Vijay Kanabar)
P-38
11Matrix (Strong) Organization
CEO
Functional Mger (Eg. Engineering)
Functional Mger (Eg. Marketing)
Functional Mger (Eg. Manufacturing)
Manager of Project Managers
Project Coordination
Staff
Staff
Staff
Project Mger
Project Mger
Staff
Staff
Staff
- Advantage Org. Hangs on to skill set after
project ends - No worries of job layoffs for PM and staff
- Disadvantage staff have 2 managers
(frustration)
Source Preparing for PMP Exam (Vijay Kanabar)
P-37
12Projectized Organization
CEO
Project Manager
Project Manager
Project Manager
Project Manager
Project Coordination
Staff
Staff
Staff
Staff
Staff
Staff
Staff
Staff
- Disadvantage All staff including the PM loose
their jobs at the end of the project - The organization looses the skills of the staff
after project ends - Advantage most of org.s resources dedicated
to project
Source Preparing for PMP Exam (Vijay Kanabar)
P-36
13Composite Project Organizations
CEO
Functional Mger (Eg. Engineering)
Functional Mger (Eg. Marketing)
Functional Mger (Eg. Manufacturing)
Manager of Project Managers
Project Coordination
Staff
Staff
Staff
Project Mger
Project Mger
Staff
Staff
Staff
- Most organizations have such a mix of structures
Source Preparing for PMP Exam (Vijay Kanabar)
P-38
14Matrix Grid of Advantages/Disadvantages of
Organizational Structure Types
Source Preparing for PMP Exam (Vijay Kanabar)
P-169
15Matrix Grid of Advantages/Disadvantages of
Organizational Structure Types (Cont.)
Source Preparing for PMP Exam (Vijay Kanabar)
P-170
16Project Integration Management
- Should consist of the processes required to
ensure that the various elements of the project
are properly coordinated.
17Project Plan Development
- Integrating and coordinating all project plans
to create a consistent, coherent
18Project Plan Execution
- Carrying out the project plan by performing the
activities included therein
19Integrated Change Control
- Coordinating changes across the entire project
20Exam Questions
- A project manager is trying to complete a
software development project but cannot get
enough attention for the project. Resources are
focused on completing process-related work and
the project manager has little authority to
properly assign resources. What form of
organization must the project manager be working
in? - Functional
- Matrix
- Expeditor
- Coordinator
- 2. A detailed project schedule can be created
only after creating the - Project Budget
- Work Breakdown Structure
- Project Plan
- Detailed risk assessment
Source PMP Exam Prep (Rita Mulcahy) PP 41/42
21Exam Questions (contd)
- The previous project manager for your project,
managed it without much project organization.
There is a lack of management control and no
clearly defined project deliverables. Which of
the following would be the BEST choice for
getting your project better organized? - Adopt a life cycle approach to the project
- Develop lessons learned for each phase
- Develop specific work plans for each phase of the
project - Develop a description of the product of the
project
- 4. All the following are part of project plan
execution except? - Identifying changes
- Using a WBS
- Taking corrective action
- Setting up a project control system
Source PMP Exam Prep (Rita Mulcahy) P-65