NERCs Licensing, Monitoring, Compliance and Enforcement Procedures - PowerPoint PPT Presentation

1 / 40
About This Presentation
Title:

NERCs Licensing, Monitoring, Compliance and Enforcement Procedures

Description:

Technology and scale. Siting and electrical connection ... Pay back period. Assessment of competition and market share. Pricing strategy and projected price ... – PowerPoint PPT presentation

Number of Views:84
Avg rating:3.0/5.0
Slides: 41
Provided by: yomiop
Category:

less

Transcript and Presenter's Notes

Title: NERCs Licensing, Monitoring, Compliance and Enforcement Procedures


1
NERCs Licensing, Monitoring, Compliance and
Enforcement Procedures
  • Presented by
  • NERC Legal, Licensing Enforcement Division
  • NERC/NARUC Workshop, Abuja
  • July 14- 18, 2008

2
Acronyms
  • NERC Nigerian Electricity Regulatory Commission
  • EPSR Act Electric Power Sector Reform Act 2005
  • PHCN Power Holding Company of Nigeria
  • SCs Successor Companies
  • IPPs Independent Power Producers

3
Outline
  • Licensing under EPSR Act 2005
  • Types of Licences
  • Eligibility for Licence
  • Legal Requirement
  • Technical Requirements
  • Commercial Requirement
  • Licence Application Procedure under NERC
  • Monitoring, Compliance Enforcement
  • Monitoring
  • Compliance Enforcement

4
Licensing under EPSR Act 2005
  • A key function of NERC is regulation of market
    participants via issuance of licences and other
    regulatory tools - S.32(2)(d) EPSR Act
  • The Act provides that no person except in
    accordance with a licence shall engage in the
    business of electricity generation, transmission,
    system operation, distribution or trading S.62
    EPSR Act
  • NERC has the authority to issue both Interim and
    Regular licences under the Act. NERC has issued
  • Interim licence to PHCN S. 7 EPSR Act
  • Interim generation, transmission, distribution
    and trading licences to SCs S.23 EPSR Act
  • 24 generation licenses to IPPs
  • 2 Distribution Licences to IPPs

5
Licensing under EPSR Act 2005(cont.)
  • Regular licences issued by NERC include
  • Generation licence
  • Grid connected
  • Off-Grid
  • Embedded Generation
  • Transmission licence
  • System Operations licence
  • Distribution licence
  • Grid Connected
  • Off-Grid
  • Trading licence
  • Temporary Bulk Purchase Resale Licence

6
Licensing under EPSR Act 2005(cont.)
  • The Act excludes the following activities from
    the requirement for a licence
  • Captive generation generation for own use
  • Electricity generation not exceeding 1MW in
    aggregate at a site
  • Electricity distribution not exceeding 100KW in
    aggregate at a site
  • In furtherance of its licensing function, the
    Commission has published Regulations on
    Application for Licences Licence and Operating
    Fees Regulation
  • Application for Licence Regulation is currently
    under amendment

7
Eligibility
  • Every applicant for a licence must satisfy three
    broad eligibility criteria viz Legal, Technical
    Commercial
  • LEGAL REQUIREMENTS
  • Incorporation of Company in Nigeria
  • Submission of Audited Company reports for the
    last three years for existing companies
  • Submission of Company Tax Clearance Certificate
  • Objects of the company must include the licensed
    business being applied for.
  • Legal Due Diligence carried out on company and
    major shareholders to ensure suitability

8
Eligibility Technical Requirements
  • Technical experience in the electricity industry
  • Knowledge of the electricity industry
  • Area of expertise (Generation, Transmission,
    Distribution, Marketing, Equipment Manufacturing)
  • Skills and knowledge of Directors and top
    management
  • Environmental Impact Assessment Certification

9
Technical Requirements (cont.)
  • Agreement / MoU with third Parties
  • Network Connection (TCN or Disco)
  • Fuel Supply (NNPC/NGC)
  • EPC
  • Station Type (Coal, Gas, Hydro, Nuclear, Wind
    etc)
  • Technology Type (CCGT, IGCC, etc.)
  • Layout design of facilities

10
SITE SPECIFIC INFORMATION
  • SITE SPECIFIC REQUIREMENTS
  • Location map showing nearby settlements, roads,
    transmission lines, rivers
  • Dam showing water spillage area
  • Water Source and pipe line(s)
  • Waste (liquid solid) Disposal area
  • Noise Level

11
PLANT SPECIFIC REQUIREMENTS
  • Total Capacity
  • Number of Generating Units
  • Size of each Generating unit (MW)
  • Station Load
  • Who will build the sub station
  • Plan for power evacuation
  • Time line for project implementation including
    proposed Commissioning Date

12
PLANT SPECIFIC REQUIREMENTS
  • Rated Capacity (MW/ MVA)
  • Terminal Voltage
  • Efficiency
  • Ancillary Services Capability
  • Terminal Voltage (KV)
  • Protection Measures
  • Make and characteristics of water turbine
  • Single line diagram of power plant

13
KEY CONSIDERATIONS
  • Suitability of station to Nigerian Condition
  • Ability of station to perform in Nigeria
  • Competency of project sponsor and technical
    partners
  • Realistic and achievable project timeline

14
Eligibility Commercial requirements
  • A five year Business Plan is required which will
    include
  • Technology requirements.
  • Describe the technology to be deployed
  • Specific requirements
  • Plant-specific
  • Technology and scale
  • Siting and electrical connection
  • Fuel source and availability
  • Construction, timing and operation (COD)
  • Micro assumptions (load factor)
  • Auxiliary and sent out energy
  • Tariff assumptions MYTO

15
Commercial requirements ( cont.)
  • Business plans ( to determine project viability
    and financing decisions)
  • Macro assumptions (inflation, fuel price
    assumption)
  • Project cost
  • Financial assumptions
  • Funding sources and structure
  • Pay back period
  • Assessment of competition and market share
  • Pricing strategy and projected price
  • Experience and expertise of management team
  • Proposed organizational structure

16
Application for Licence Procedure
  • PRELIMINARY ENQUIRY
  • Before a prospective applicant can apply for a
    licence, the following steps should be followed
  • Applicant should conduct study to ensure
    applicant can meet industry requirements
  • Applicant should confirm whether a licence is
    required for the business
  • If a licence is required, an application form
    can be obtained from NERCs office or from NERCs
    website
  • Submit completed application form along with
    relevant documents/information and licence
    application fee to NERC

17
Application for Licence Procedure (CONT.)
  • NERC reviews application form and documents for
    adequacy
  • If application is complete, NERC acknowledges it
    as duly made and requests the applicant to
    publish the mandatory statutory public notice in
    two dailies
  • If application is incomplete, NERC will inform
    the applicant accordingly
  • If applicant fails to provide information within
    prescribed time, the application is discarded
  • If applicant provides required information, NERC
    acknowledges it as duly made and requests the
    applicant to publish the mandatory statutory
    public notice in two dailies
  • Publication must be in one newspaper of national
    circulation and another circulating in the area
    where the proposed project is to be sited
  • Notice should state that objections and
    representations should be made to NERC within 21
    days of the publication

18
Application for Licence Procedure (CONT.)
  • Applicant must furnish NERC with copies of the
    published notices
  • Where there is no objection to the application
    after the 21-day period, NERC will carry out a
    legal, technical and commercial evaluation of the
    application
  • Where there are objections to the application
    received within the 21 days period, NERC will
    consider the objection and may place the
    application for hearing based on the objection
    filed in respect of the application
  • NERC will give notice of such hearing to the
    applicant, the person objecting and other persons
    as NERC may consider appropriate

19
Application for Licence Procedure (CONT.)
  • NERCs findings at the hearing would be in
    writing and signed appropriately
  • Where NERC decides in favour of the applicant,
    NERC will carry out a legal, technical and
    commercial evaluation of the application
  • After the evaluation, a recommendation is made to
    Commission to grant or refuse licence
  • Commission considers the recommendation and makes
    its decision
  • Time between due acknowledgement of receipt of
    application and the date when the application is
    granted/refused must not exceed 6 months

20
Application for Licence Procedure (CONT.)
  • When granted, NERC will inform the applicant of
    the approval and the conditions to be satisfied
    including payment of licence fee for the grant.
    NERC also issues a timeline for conditions to be
    met up to the Commissioning of the project.
    (Annexure A)
  • If NERC intends to refuse an application, it
    shall notify the applicant in writing of its
    intention and give the applicant 15 days from the
    date of notification to make representations on
    the matter
  • Where no representation is made, NERC will
    re-state (in writing) the reasons for refusal of
    the application
  • Where an unsuccessful representation is made,
    NERC will state (in writing) the reasons for
    refusal of the representation
  • Applicant has a right of Appeal to the Commission
    and may revert to the Federal High Court on
    questions of Law

21
Grounds for Refusal of Licence
  • Applicant fails to meet the required criteria
  • Legal
  • Technical
  • Commercial
  • Applicant fails to produce upon request
    additional information within the time specified
    by NERC
  • NERC is of the opinion that the information
    provided by the applicant is false or misleading

22
Application, Licence and Operating Fees
  • S/N Licence Category
  • Grid-Connected Validity Period Application Fees
    (N) Licence Fees (US) Licence Amendment Fees
    (N) Annual Operating Levies
  • 1 Generation 10
  • Above 1MW-10MW 50,000 2,500 50,000 1.5 of
    Licensees Charges/kWh
  • Above 10MW-100MW 100,000 25,000 100,000
  • Above 101MW-250MW 200,000 50,000 200,000
  • Above 251MW-500MW 300,000 75,000 300,000
  • Above 501MW-1000MW 400,000 100,000 400,000
  • Above 1000MW 500,000 200,000 500,000
  • 2 Transmission 10 1,000,000 250,000 1,000,000
  • 3 System Operations 10 1,000,000 250,000 1,000,000
  • 4 Distribution/Trading 10 1,000,000 50,000 1,000,0
    00

23
Application, Licence Operating Fees
  • S/N Licence Category
  • Off Grid Operations Validity Period Application
    Fees (N) Licence Fees (US) Licence Amendment
    Fees (N) Annual Operating Levies
  • 1 Above 1MW-10MW 1 10,000 1,000 500 None
  • 11MW-20MW 10,000 2,000 1,000
  • 21MW-30MW 10,000 2,500 1,250
  • 31MW-40MW 10,000 3,000 1,500
  • 41MW-50MW 10,000 3,000 1,500
  • 51MW-100MW 20,000 5,000 2,500
  • Above 100 MW 50,000 6,000 3,000
  • 4 Distribution/Trading 10 100,000 10,000 5,000 1.5
    of tariff charge/kWh

24
CHALLENGES IN LICENSING
  • Licence Tenure limited to 10 years S 71(10) EPSR
    Act
  • Multiple sites licensing
  • Payment of licence fees and operating levies by
    SCs
  • Fulfillment of post- licensing milestones
  • Issue of multiple documentations and agreements
    for licensees
  • Development of appropriate licensing regime
    regulatory framework for renewables
  • Ensuring smooth interface with other sister
    agencies e.g Rural Electrification Agency, Energy
    Commission of Nigeria

25
For Further Information
  • For more information on the Licensing Procedure,
    copies of the following documents can be obtained
    from NERCs office or downloaded from NERCs
    website, www.nercng.org
  • NERC Regulation on Application for Licences
  • NERC Regulation on Business Rules of the
    Commission
  • Handbook on Application for Licences
  • Regulation on Licence and Operating Fees
  • Electric Power Sector Reform Act 2005

26
Monitoring, Compliance and Enforcement
  • Monitoring and enforcing licence conditions,
    including codes and standards are two key
    functions of NERC.
  • A Draft Guideline on Monitoring and Enforcement
    has been developed and is before the Commission
    for Approval

27
Monitoring
  • Licence monitoring is undertaken through a number
    of activities including
  • Post Licence issuance monitoring (NERC Annexure
    A)
  • NERCs licences are currently issued subject to
    fulfilment of some conditions (contained in
    Annexure A) within 12 months of grant of licence
    including
  • Obtaining Registered Title Deed to Site
  • Off-take Arrangements
  • Approved Environmental Impact Assessment Report
  • Fuel Supply Arrangement
  • EPC Contract
  • Financing Agreement
  • Connection Agreement
  • Pre-construction Agreements
  • Site Mobilization
  • Commissioning of plant to be achieved within
    36-48monthe depending on plant type

28
Monitoring (cont.)
  • Complaints Customer complaints are the most
    common, and typically the best, avenue for
    effective licensee monitoring. Reviewing
    complaints received from other licensees as well
    as customers will ensure monitoring. (Regulations
    on Customer Complaints Handling Procedure has
    been developed by NERC)
  • Regulatory Returns All licensees are required to
    complete and submit an annual return that
    contains a mixture of financial, business
    performance and operational performance data
    additional periodic reporting are also be
    required to be submitted

29
Monitoring (Cont.)
  • Establishment of Key Performance Indicators for
    Licensees
  • NERC is working with the industry to develop a
    sector score card that will enable the public see
    how the industry is performing
  • Market Monitoring NERC carries out routine
    observation of the power sector through
  • Reading industry literature as well as general
    news sources
  • Following financial market movements and reading
    analyst reports
  • Investigating anti-competitive behaviour An
    draft Affiliate Code of Conduct Regulations has
    been developed for commissions approval prior to
    issuing a Notice of proposed rule-making.
  • Surprise Audit or Site Visit NERC may carry out
    unscheduled operational audits and site visits on
    a random and periodic basis, or when there is
    suspicion of a problem, . NERC can appoint
    inspectors to carry out this function

30
Monitoring (cont.)
This summaries the monitoring procedure
  • NERC gathers and analyses information concerning
    the behaviour of licensees in order to ascertain
    whether any license conditions breaches are
    taking place or are expected to take place
  • Information is gathered in a number of ways
    including
  • -- (i) Licensee Returns
  • -- (ii) Complaints
  • -- (iii) Performance monitoring
  • -- (iv) Market Monitoring
  • -- (v) Surprise Audit or Site Visit

31
Compliance and Enforcement procedure
  • NERCs compliance and enforcement procedure as
    contained in the draft guidelines can be
    summarized as follows
  • NERC receives initial complaint
  • NERC investigates and issues a provisional Order
    if necessary
  • NERC proceeds to issue a Breach Notice to
    Licensee where there is evidence of breach
  • Where Licensee provides justification for breach,
    NERC reviews justification and may hold a hearing
    if necessary
  • If justification has merit, NERC will rule
    accordingly

32
Compliance and Enforcement (cont.)
  • 6. If justification lacks merit, NERC will issue
    public notice encompassing compliance Order
  • If licensee rectifies breach, NERC may impose
    sanction if necessary
  • If breach is still not rectified, NERC imposes
    sanction on licensee and issues public notice of
    Sanction

33
Compliance Enforcement Procedures (cont.)
34
Compliance Enforcement Procedures (cont.)
35
Compliance Enforcement Procedures (cont.)
36
Compliance Enforcement procedure (cont.)
  • NERC considers it important to use the
    enforcement powers it has under the EPSR Act
  • Enforcement can usually be carried out by using a
    combination of enforcement methods including
    Orders and fines
  • The level of fine should be commensurate with the
    nature of the infringement and/or losses incurred
    by affected parties
  • License suspension may be considered if the
    licensee fails to abide by an enforcement order,
    fails to pay a fine levied upon it by NERC or
    fails to pay its annual fee
  • Preparation for suspension and revocation is
    necessary to prevent it from being an empty
    threat
  • Public engagement in the enforcement process is
    both desirable and necessary naming and
    shaming will also be used a tool to ensure
    compliance

37
Compliance Enforcement procedures (cont.)
  • License revocation will only be considered in
    certain circumstances
  • End of a suspension period if the licensee has
    failed to address the breach
  • Repeated and wilful abuse of fundamental licence
    conditions
  • Failure to comply with critical license
    conditions e.g. health and safety terms
  • Repeated, demonstrable technical, managerial or
    financial incompetence
  • If the licence was issued through fraud or
    misrepresentation of critical material
    information
  • License suspension or revocation requires the
    replacement of the operating companys directors
    and/or senior management (where the company is
    privately held this may entail the sale of the
    firm)

38
Compliance Enforcement procedures (cont.)
  • NERC is working with a number of Law enforcement
    agencies to collaborate on Enforcement including
  • Economic Financial Crimes Commission
  • Nigerian Police Force
  • Nigerian Civil Defence Corp
  • Independent Corrupt Practices Commission
  • Federal High Court

39
CHALLENGES IN MONITORING ENFORCEMENT
  • Inability of most licensees to adhere to timeline
    stipulated in Annexure A
  • EPSR Act provides a cap on penalties to be
    imposed
  • EPSR Act does not give specific NERC enforcement
    powers
  • Collaboration necessary with other agencies as
    NERC may not be able to otherwise enforce some
    Orders
  • Issue of ensuring compliance by SCs during the
    transition period
  • Interface with courts likely to result in delays
    as there are no special courts
  • Judges may require specialist training to
    understand NERCs regulatory landscape NERC is
    planning a workshop for Judges

40
  • THANK YOU ALL
Write a Comment
User Comments (0)
About PowerShow.com