Title: NERCs Licensing, Monitoring, Compliance and Enforcement Procedures
1NERCs Licensing, Monitoring, Compliance and
Enforcement Procedures
- Presented by
- NERC Legal, Licensing Enforcement Division
- NERC/NARUC Workshop, Abuja
- July 14- 18, 2008
2Acronyms
- NERC Nigerian Electricity Regulatory Commission
- EPSR Act Electric Power Sector Reform Act 2005
- PHCN Power Holding Company of Nigeria
- SCs Successor Companies
- IPPs Independent Power Producers
3Outline
- Licensing under EPSR Act 2005
- Types of Licences
- Eligibility for Licence
- Legal Requirement
- Technical Requirements
- Commercial Requirement
- Licence Application Procedure under NERC
- Monitoring, Compliance Enforcement
- Monitoring
- Compliance Enforcement
4Licensing under EPSR Act 2005
- A key function of NERC is regulation of market
participants via issuance of licences and other
regulatory tools - S.32(2)(d) EPSR Act - The Act provides that no person except in
accordance with a licence shall engage in the
business of electricity generation, transmission,
system operation, distribution or trading S.62
EPSR Act - NERC has the authority to issue both Interim and
Regular licences under the Act. NERC has issued - Interim licence to PHCN S. 7 EPSR Act
- Interim generation, transmission, distribution
and trading licences to SCs S.23 EPSR Act - 24 generation licenses to IPPs
- 2 Distribution Licences to IPPs
5Licensing under EPSR Act 2005(cont.)
- Regular licences issued by NERC include
- Generation licence
- Grid connected
- Off-Grid
- Embedded Generation
- Transmission licence
- System Operations licence
- Distribution licence
- Grid Connected
- Off-Grid
- Trading licence
- Temporary Bulk Purchase Resale Licence
6Licensing under EPSR Act 2005(cont.)
- The Act excludes the following activities from
the requirement for a licence - Captive generation generation for own use
- Electricity generation not exceeding 1MW in
aggregate at a site - Electricity distribution not exceeding 100KW in
aggregate at a site - In furtherance of its licensing function, the
Commission has published Regulations on
Application for Licences Licence and Operating
Fees Regulation - Application for Licence Regulation is currently
under amendment
7Eligibility
- Every applicant for a licence must satisfy three
broad eligibility criteria viz Legal, Technical
Commercial - LEGAL REQUIREMENTS
- Incorporation of Company in Nigeria
- Submission of Audited Company reports for the
last three years for existing companies - Submission of Company Tax Clearance Certificate
- Objects of the company must include the licensed
business being applied for. - Legal Due Diligence carried out on company and
major shareholders to ensure suitability
8 Eligibility Technical Requirements
- Technical experience in the electricity industry
- Knowledge of the electricity industry
- Area of expertise (Generation, Transmission,
Distribution, Marketing, Equipment Manufacturing) - Skills and knowledge of Directors and top
management - Environmental Impact Assessment Certification
9Technical Requirements (cont.)
- Agreement / MoU with third Parties
- Network Connection (TCN or Disco)
- Fuel Supply (NNPC/NGC)
- EPC
- Station Type (Coal, Gas, Hydro, Nuclear, Wind
etc) - Technology Type (CCGT, IGCC, etc.)
- Layout design of facilities
10 SITE SPECIFIC INFORMATION
- SITE SPECIFIC REQUIREMENTS
- Location map showing nearby settlements, roads,
transmission lines, rivers - Dam showing water spillage area
- Water Source and pipe line(s)
- Waste (liquid solid) Disposal area
- Noise Level
11PLANT SPECIFIC REQUIREMENTS
- Total Capacity
- Number of Generating Units
- Size of each Generating unit (MW)
- Station Load
- Who will build the sub station
- Plan for power evacuation
- Time line for project implementation including
proposed Commissioning Date
12PLANT SPECIFIC REQUIREMENTS
- Rated Capacity (MW/ MVA)
- Terminal Voltage
- Efficiency
- Ancillary Services Capability
- Terminal Voltage (KV)
- Protection Measures
- Make and characteristics of water turbine
- Single line diagram of power plant
13KEY CONSIDERATIONS
- Suitability of station to Nigerian Condition
- Ability of station to perform in Nigeria
- Competency of project sponsor and technical
partners - Realistic and achievable project timeline
14Eligibility Commercial requirements
- A five year Business Plan is required which will
include - Technology requirements.
- Describe the technology to be deployed
- Specific requirements
- Plant-specific
- Technology and scale
- Siting and electrical connection
- Fuel source and availability
- Construction, timing and operation (COD)
- Micro assumptions (load factor)
- Auxiliary and sent out energy
- Tariff assumptions MYTO
15Commercial requirements ( cont.)
- Business plans ( to determine project viability
and financing decisions) - Macro assumptions (inflation, fuel price
assumption) - Project cost
- Financial assumptions
- Funding sources and structure
- Pay back period
- Assessment of competition and market share
- Pricing strategy and projected price
- Experience and expertise of management team
- Proposed organizational structure
16Application for Licence Procedure
- PRELIMINARY ENQUIRY
- Before a prospective applicant can apply for a
licence, the following steps should be followed - Applicant should conduct study to ensure
applicant can meet industry requirements - Applicant should confirm whether a licence is
required for the business - If a licence is required, an application form
can be obtained from NERCs office or from NERCs
website - Submit completed application form along with
relevant documents/information and licence
application fee to NERC
17Application for Licence Procedure (CONT.)
- NERC reviews application form and documents for
adequacy - If application is complete, NERC acknowledges it
as duly made and requests the applicant to
publish the mandatory statutory public notice in
two dailies - If application is incomplete, NERC will inform
the applicant accordingly - If applicant fails to provide information within
prescribed time, the application is discarded - If applicant provides required information, NERC
acknowledges it as duly made and requests the
applicant to publish the mandatory statutory
public notice in two dailies - Publication must be in one newspaper of national
circulation and another circulating in the area
where the proposed project is to be sited - Notice should state that objections and
representations should be made to NERC within 21
days of the publication
18Application for Licence Procedure (CONT.)
- Applicant must furnish NERC with copies of the
published notices - Where there is no objection to the application
after the 21-day period, NERC will carry out a
legal, technical and commercial evaluation of the
application - Where there are objections to the application
received within the 21 days period, NERC will
consider the objection and may place the
application for hearing based on the objection
filed in respect of the application - NERC will give notice of such hearing to the
applicant, the person objecting and other persons
as NERC may consider appropriate
19Application for Licence Procedure (CONT.)
- NERCs findings at the hearing would be in
writing and signed appropriately - Where NERC decides in favour of the applicant,
NERC will carry out a legal, technical and
commercial evaluation of the application - After the evaluation, a recommendation is made to
Commission to grant or refuse licence - Commission considers the recommendation and makes
its decision - Time between due acknowledgement of receipt of
application and the date when the application is
granted/refused must not exceed 6 months
20Application for Licence Procedure (CONT.)
- When granted, NERC will inform the applicant of
the approval and the conditions to be satisfied
including payment of licence fee for the grant.
NERC also issues a timeline for conditions to be
met up to the Commissioning of the project.
(Annexure A) - If NERC intends to refuse an application, it
shall notify the applicant in writing of its
intention and give the applicant 15 days from the
date of notification to make representations on
the matter - Where no representation is made, NERC will
re-state (in writing) the reasons for refusal of
the application - Where an unsuccessful representation is made,
NERC will state (in writing) the reasons for
refusal of the representation - Applicant has a right of Appeal to the Commission
and may revert to the Federal High Court on
questions of Law
21Grounds for Refusal of Licence
- Applicant fails to meet the required criteria
- Legal
- Technical
- Commercial
- Applicant fails to produce upon request
additional information within the time specified
by NERC - NERC is of the opinion that the information
provided by the applicant is false or misleading
22Application, Licence and Operating Fees
- S/N Licence Category
- Grid-Connected Validity Period Application Fees
(N) Licence Fees (US) Licence Amendment Fees
(N) Annual Operating Levies - 1 Generation 10
- Above 1MW-10MW 50,000 2,500 50,000 1.5 of
Licensees Charges/kWh - Above 10MW-100MW 100,000 25,000 100,000
- Above 101MW-250MW 200,000 50,000 200,000
- Above 251MW-500MW 300,000 75,000 300,000
- Above 501MW-1000MW 400,000 100,000 400,000
- Above 1000MW 500,000 200,000 500,000
- 2 Transmission 10 1,000,000 250,000 1,000,000
- 3 System Operations 10 1,000,000 250,000 1,000,000
- 4 Distribution/Trading 10 1,000,000 50,000 1,000,0
00
23Application, Licence Operating Fees
- S/N Licence Category
- Off Grid Operations Validity Period Application
Fees (N) Licence Fees (US) Licence Amendment
Fees (N) Annual Operating Levies - 1 Above 1MW-10MW 1 10,000 1,000 500 None
-
- 11MW-20MW 10,000 2,000 1,000
- 21MW-30MW 10,000 2,500 1,250
- 31MW-40MW 10,000 3,000 1,500
- 41MW-50MW 10,000 3,000 1,500
- 51MW-100MW 20,000 5,000 2,500
- Above 100 MW 50,000 6,000 3,000
- 4 Distribution/Trading 10 100,000 10,000 5,000 1.5
of tariff charge/kWh
24CHALLENGES IN LICENSING
- Licence Tenure limited to 10 years S 71(10) EPSR
Act - Multiple sites licensing
- Payment of licence fees and operating levies by
SCs - Fulfillment of post- licensing milestones
- Issue of multiple documentations and agreements
for licensees - Development of appropriate licensing regime
regulatory framework for renewables - Ensuring smooth interface with other sister
agencies e.g Rural Electrification Agency, Energy
Commission of Nigeria
25For Further Information
- For more information on the Licensing Procedure,
copies of the following documents can be obtained
from NERCs office or downloaded from NERCs
website, www.nercng.org - NERC Regulation on Application for Licences
- NERC Regulation on Business Rules of the
Commission - Handbook on Application for Licences
- Regulation on Licence and Operating Fees
- Electric Power Sector Reform Act 2005
26Monitoring, Compliance and Enforcement
- Monitoring and enforcing licence conditions,
including codes and standards are two key
functions of NERC. - A Draft Guideline on Monitoring and Enforcement
has been developed and is before the Commission
for Approval
27Monitoring
- Licence monitoring is undertaken through a number
of activities including - Post Licence issuance monitoring (NERC Annexure
A) - NERCs licences are currently issued subject to
fulfilment of some conditions (contained in
Annexure A) within 12 months of grant of licence
including - Obtaining Registered Title Deed to Site
- Off-take Arrangements
- Approved Environmental Impact Assessment Report
- Fuel Supply Arrangement
- EPC Contract
- Financing Agreement
- Connection Agreement
- Pre-construction Agreements
- Site Mobilization
- Commissioning of plant to be achieved within
36-48monthe depending on plant type
28Monitoring (cont.)
- Complaints Customer complaints are the most
common, and typically the best, avenue for
effective licensee monitoring. Reviewing
complaints received from other licensees as well
as customers will ensure monitoring. (Regulations
on Customer Complaints Handling Procedure has
been developed by NERC) - Regulatory Returns All licensees are required to
complete and submit an annual return that
contains a mixture of financial, business
performance and operational performance data
additional periodic reporting are also be
required to be submitted
29Monitoring (Cont.)
- Establishment of Key Performance Indicators for
Licensees - NERC is working with the industry to develop a
sector score card that will enable the public see
how the industry is performing - Market Monitoring NERC carries out routine
observation of the power sector through - Reading industry literature as well as general
news sources - Following financial market movements and reading
analyst reports - Investigating anti-competitive behaviour An
draft Affiliate Code of Conduct Regulations has
been developed for commissions approval prior to
issuing a Notice of proposed rule-making. - Surprise Audit or Site Visit NERC may carry out
unscheduled operational audits and site visits on
a random and periodic basis, or when there is
suspicion of a problem, . NERC can appoint
inspectors to carry out this function
30Monitoring (cont.)
This summaries the monitoring procedure
- NERC gathers and analyses information concerning
the behaviour of licensees in order to ascertain
whether any license conditions breaches are
taking place or are expected to take place - Information is gathered in a number of ways
including - -- (i) Licensee Returns
- -- (ii) Complaints
- -- (iii) Performance monitoring
- -- (iv) Market Monitoring
- -- (v) Surprise Audit or Site Visit
31Compliance and Enforcement procedure
- NERCs compliance and enforcement procedure as
contained in the draft guidelines can be
summarized as follows - NERC receives initial complaint
- NERC investigates and issues a provisional Order
if necessary - NERC proceeds to issue a Breach Notice to
Licensee where there is evidence of breach - Where Licensee provides justification for breach,
NERC reviews justification and may hold a hearing
if necessary - If justification has merit, NERC will rule
accordingly
32Compliance and Enforcement (cont.)
- 6. If justification lacks merit, NERC will issue
public notice encompassing compliance Order - If licensee rectifies breach, NERC may impose
sanction if necessary - If breach is still not rectified, NERC imposes
sanction on licensee and issues public notice of
Sanction
33Compliance Enforcement Procedures (cont.)
34Compliance Enforcement Procedures (cont.)
35Compliance Enforcement Procedures (cont.)
36Compliance Enforcement procedure (cont.)
- NERC considers it important to use the
enforcement powers it has under the EPSR Act - Enforcement can usually be carried out by using a
combination of enforcement methods including
Orders and fines - The level of fine should be commensurate with the
nature of the infringement and/or losses incurred
by affected parties - License suspension may be considered if the
licensee fails to abide by an enforcement order,
fails to pay a fine levied upon it by NERC or
fails to pay its annual fee - Preparation for suspension and revocation is
necessary to prevent it from being an empty
threat - Public engagement in the enforcement process is
both desirable and necessary naming and
shaming will also be used a tool to ensure
compliance
37Compliance Enforcement procedures (cont.)
- License revocation will only be considered in
certain circumstances - End of a suspension period if the licensee has
failed to address the breach - Repeated and wilful abuse of fundamental licence
conditions - Failure to comply with critical license
conditions e.g. health and safety terms - Repeated, demonstrable technical, managerial or
financial incompetence - If the licence was issued through fraud or
misrepresentation of critical material
information - License suspension or revocation requires the
replacement of the operating companys directors
and/or senior management (where the company is
privately held this may entail the sale of the
firm)
38Compliance Enforcement procedures (cont.)
- NERC is working with a number of Law enforcement
agencies to collaborate on Enforcement including - Economic Financial Crimes Commission
- Nigerian Police Force
- Nigerian Civil Defence Corp
- Independent Corrupt Practices Commission
- Federal High Court
39CHALLENGES IN MONITORING ENFORCEMENT
- Inability of most licensees to adhere to timeline
stipulated in Annexure A - EPSR Act provides a cap on penalties to be
imposed - EPSR Act does not give specific NERC enforcement
powers - Collaboration necessary with other agencies as
NERC may not be able to otherwise enforce some
Orders - Issue of ensuring compliance by SCs during the
transition period - Interface with courts likely to result in delays
as there are no special courts - Judges may require specialist training to
understand NERCs regulatory landscape NERC is
planning a workshop for Judges
40