Plans for NearRealTime AIRS L2 Profile Assimilation - PowerPoint PPT Presentation

1 / 6
About This Presentation
Title:

Plans for NearRealTime AIRS L2 Profile Assimilation

Description:

Aboard Aqua polar orbiter. Early afternoon equator crossing. 2378 spectral channels. 3.7 15.4 m (650 2675 cm-1) 3 x 3 footprints (50 km spatial resolution) ... – PowerPoint PPT presentation

Number of Views:35
Avg rating:3.0/5.0
Slides: 7
Provided by: wwwghccM
Category:

less

Transcript and Presenter's Notes

Title: Plans for NearRealTime AIRS L2 Profile Assimilation


1
Plans for Near-Real-Time AIRS L2 Profile
Assimilation
  • Shih-Hung Chou and Brad Zavodsky

2
AIRS Specifications
  • Aboard Aqua polar orbiter
  • Early afternoon equator crossing
  • 2378 spectral channels
  • 3.7 15.4 µm (650 2675 cm-1)
  • 3 x 3 footprints (50 km spatial resolution)
  • AMSU allows for retrievals in both clear and
    cloudy scenes
  • Version 4.0 Error Estimates (Tobin et al. 2006)
  • 0.6-1.0K over ocean ( 50o latitude)
  • 0.9-1.3K global ocean and land (in 1 km layers)
  • lt 15 RH (in 2 km layers)

3
AIRS Data Quality Indicators
  • Quality indicators (QIs) in V5
  • pressure for each sounding indicating level of
    valid data
  • level-by-level error estimates for each T and q
    profile
  • Improved retrieval algorithm
  • More data are assimilated
  • QIs allow for the maximum amount of quality
    data to be assimilated
  • assimilating a larger volume of higher quality
    data should produce an analysis that provides
    better initial conditions for the WRF

AIRS V5 PBest from JPL Focus Day
4
Near-Real-Time WRF/AIRS SimulationsInitialized
at 00Z 12 km (Using15 nodes)
wrf_real init/brdy
wrf_run to AIRS time 7-h fcst
wrf_prep 40-km NAM (00Z)
Assimilate AIRS data (ARPS)
8 min
30 min
15 min
1.5 h
AIRS data
Products to web
wrf_run (autopost) 41-h fcst
30 min
2 h 10 m/case
  • Summary
  • Total run time with 1 AIRS case 4 h 40 m
  • Each additional case 2 h 10 m
  • QPF and RAOB verifications will run when obs
    are available

5
Timeline for Near-Real-Time WRF/AIRS
SimulationsInitialized at 00Z 12 km (Using15
nodes)
520Z
620Z
900Z
1240Z
1030Z
1450Z
1520Z
WRF
WRF
Start WRF
CNTL run
AIRS run-2
AIRS run-1
Web products
7-h fcst
7-h fcst
ADAS
700Z
AIRS obs
AIRS on line
6
Products to Web
  • Daily Posting
  • Surface and Pressure-Level Maps T, q, h, and V
  • Difference Fields T, q, h, and V
  • Delayed Posting
  • Verification Statistics RAOB and NAM analysis
  • bias and RMSE
  • Qualitative Precipitation Forecast Stage IV
    precipitation
  • bias score and equitable threat score
  • Website NASA GHCC AIRS Assimilation Case Study
Write a Comment
User Comments (0)
About PowerShow.com