Located about 5 mm from electron beam. Detection of Compton electrons ... Amplifier. Design complete. Being manufactured. Complete testing to be done. Trigger ... – PowerPoint PPT presentation

Number of Views:40
Avg rating:3.0/5.0
Slides: 11
Provided by: alexandre53
Category:

less

Transcript and Presenter's Notes

Title: Compton polarimeter Electron detector upgrade and status


1
Compton polarimeterElectron detector upgrade
andstatus
  • PREX/Happex
  • Collaboration
  • Meeting
  • May 17th 2007
  • Alexandre Camsonne

2
Electron detector
  • 4 planes microstrip 128 strips
  • Located about 5 mm from electron beam
  • Detection of Compton electrons using 3rd dipole
    of the chicane as analyzer

3
Upgrade
  • Mechanical
  • New vertical motion system and accomodation of
    the new electronics
  • Electronics
  • Switch to 192 microstrips for improved resolution
    to reduce systematics
  • DAQ
  • Analysis

4
Mechanical design
  • Design Clermont-Ferrand
  • Complete
  • Most parts in procurement
  • http//clrwww.in2p3.fr/meca/plans/Site-web/Cebaf/T
    JN-DetE/TJN-DetE-P2.html
  • Control motion
  • Motor ordered
  • Controls/interlocks to be developed

5
Mechanical design
  • Integration JLab
  • CAD drawings from Clermont Ferrand to check for
    interference
  • Support stand design complete

6
Electronics
  • Detectors strips at Clermont Ferrand
  • 4 planes 192 strips
  • Amplifier
  • Design complete
  • Being manufactured
  • Complete testing to be done
  • Trigger
  • Work on board routing in process
  • Design done 1 or 2 months
  • Test card trigger done for test in July

7
DAQ
  • Trigger and readout similar to previous detector
  • Crl to be adapted
  • Synchronization/integration with photon detector
    ( coincidence trigger)
  • Work will start by spring 2008 when everything at
    JLab ( 2 months )

8
Analysis
  • Reuse of Etienne Burtin, Stephanie Escoffie
    software
  • Addition of David Lhuillier improvements
  • Scaling of old software or rewriting of
    software ?

9
Man power
  • Clermont
  • Bernard Michel ( Electronics )
  • Michel Brossard ( Physicist )
  • Guy Savinel (?) ( Mechanical)
  • Jefferson Laboratory
  • Sue Witherspoon (EPICS Slow control)
  • Alexandre Camsonne ( DAQ / Analysis)
  • More people ?

10
Conclusion
  • Mechanical design complete
  • Progress on the electron detector electronics
  • Final date for installation to be determined
  • All components ready by end of 2007 ready for
    installation beginning 2008