Argonne PowerPoint Presentation - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

Argonne PowerPoint Presentation

Description:

PAC07, Albuquerque, NM. 2. IPNS RCS RF System Block Diagram: 3 ... Final amplifier uses two Eimac 3CW150000H3 water-cooled power triodes in a ... – PowerPoint PPT presentation

Number of Views:104
Avg rating:3.0/5.0
Slides: 10
Provided by: wwwacc
Category:

less

Transcript and Presenter's Notes

Title: Argonne PowerPoint Presentation


1
KEK/ISIS/ANL LOI Amplifier/Second Harmonic RF
Collaboration Meeting
Tuesday, 26th of June, 2007 PAC07, Albuquerque,
NM
2
IPNS RCS RF System Block Diagram
3
Third Cavity Installed in L6 Straight Section
4
Third Cavity and Final Amplifier
  • Final amplifier uses two Eimac 3CW150000H3
    water-cooled power triodes in a grounded-grid,
    cathode-driven, push-pull topology.
  • Operated Class A.
  • Plate power supplied by an 8 kV, 24 A DC power
    supply.
  • Typical operating point
  • Vplate 8 kVDC
  • Vgrid -320 VDC
  • Zero-signal plate current/tube 5 A

5
Final Plate Supply, Cavity Bias Supply and
Filament and Grid Supply Cabinet
Cavity Bias Supply 0 to 1000 A DC Final Grid
and Filament Cabinet
Final Plate Supply 8 kV, 24 A DC
6
Predriver and Driver Amplifiers
  • Predriver amplifier uses two Eimac YU-106
    water-cooled power triodes in a grounded-grid,
    cathode-driven, push-pull topology.
  • Operated Class A.
  • Plate power supplied by a 5 kV, 4 A DC power
    supply.
  • Typical operating point
  • Vplate 5 kVDC
  • Vgrid 35 VDC
  • Zero-signal plate current/tube 1 A
  • Driver amplifier uses two Eimac 4CW25000A
    water-cooled power tetrodes in a grid-driven,
    push-pull topology.
  • Operated Class A.
  • Plate power supplied by a 5 kV, 10 A DC power
    supply.
  • Typical operating point
  • Vplate 5 kVDC
  • Vscreen 1.5 kVDC
  • Vgrid -300 VDC
  • Zero plate current/tube 3 A

7
Timeline
  • Summer Shutdown, 2005 Disassembled test stand
    and moved equipment into place.
  • Winter Shutdown, 2005-2006 Installed third
    cavity in RCS.
  • March, 2006 Operated all three cavities with
    beam (3rd cavity operated in fundamental mode).
  • Septemember, 2006 Operated 3rd cavity in
    second harmonic mode (for first 4ms of cycle)
    with beam.

8
Results with Second Harmonic
Rectified fundamental and second harmonic gap
voltage.
Single-turn, vector sum of gap voltages, at 1.8
ms after injection.
Bunch profile without second harmonic, at 1.8 ms
after injection.
Bunch profile with second harmonic, at 1.8 ms
after injection.
Time
Injection
Mountain range plot starting at injection without
second harmonic, duration 4 ms.
Mountain range plot starting at injection with
second harmonic, duration 4 ms.
9
Future Plans
Write a Comment
User Comments (0)
About PowerShow.com