Title: REVIEW OF THE PUBLIC PRIVATE PARTNERSHIP PRISON CONTRACTS
1REVIEW OF THE PUBLIC PRIVATE PARTNERSHIP PRISON
CONTRACTS
2TASK TEAM TERMS OF REFERENCE
- To understand output specifications, costing
assumptions, project finance and risk allocation. - To identify capital and operational costs.
- To identify features for re-negotiation to
address DCS affordability constraints. - To establish a sound methodological basis for
comparison with existing and recently constructed
conventional prisons. - To report to Ministers of Correctional Services,
Finance, Public Works and Portfolio Committee.
3TASK TEAM MEMBERS
4TASK TEAM FINDINGS
- Part I Existing PPP Transactions
- Overview of existing PPP transactions.
- Options for Re-negotiation of Existing Contracts.
- Conclusions and Recommendations.
- Part II Future Prison Projects
- Illustrative comparisons of Public and PPP
Prisons - Future Evaluation Methodology Feasibility
Protocol. - Conclusions and Recommendations.
- Part III Recommendations for Next Steps
5PART I EXISTING PPP PRISONS TRANSACTIONS
61. OVERVIEW OF EXISTING PPP PRISONS TRANSACTIONS
7BLOEMFONTEIN PRISON PPPPARTIES TO THE CONTRACT
8LOUIS TRICHARDT PRISON PPPPARTIES TO THE CONTRACT
9DCS SPECIFICATIONS
- Specifications based on inputs rather than
outputs or outcomes. - Specifications imported from UK prison ideal
and high level. - No prior feasibility undertaken to ensure
- Affordability limits
- Optimal value for money
- Optimal risk transfer
10DCS SPECIFICATIONS DESIGN
- Cell configuration (2-man and 4-man cells).
- Security.
- Special centres (e.g. assessment, visitors,
special treatment). - Utilities.
- Service centres (e.g. catering, health,
religious). - External works.
11DCS DESIGN SPECIFICATIONS EXAMPLES
- Cell size 5.5m2 single or 8m2 double.
- Cell height 2.7m.
- Minimum 5 layers of security.
- Telephone monitoring system.
- CCTV, cameras, x-rays, etc.
- Minimum requirement according to Health and
National Building Regulations.
12DCS SPECIFICATIONS OPERATIONS
- Goal 1 Keep inmates in custody
- Central control, number of prisoners per cell,
supervision, security during visits, escorts,
special category prisoners, roll checks, etc. - Goal 2 Order, control and safety
- Regulating remedy deficiencies, grievance
procedures, use of force, financial transactions,
repairs, maintenance, drug control measures, etc. - Goal 3 Decent conditions for inmates
- Admission times, personal hygiene clothing,
bedding, cell equipment, meals, healthcare, etc. - Goal 4 Prepare for return to community
- Legal rights representation, official visits,
unofficial visits, etc.
13DCS SPECIFICATIONS OPERATIONS
- Goal 5 Structured Day Programmes
- Structured Day Programme, times of unlocking,
activities, time outdoors, social work services,
religion, work, education training programmes,
physical education library, psychologists, etc. - Goal 6 Deliver services with maximum efficiency
- Strategic development plans, personnel policies,
equal opportunities, drug alcohol free
work-place, conditions of service, uniforms,
recruitment selection and training. - Goal 7 Promote community involvement
- Community participation and vice versa, formal
informal community development, employment to
local community, local PR policy.
14OVERVIEW
15FEES PAYABLE BY DCS
16COMPARISON OF FEE STRUCTURE
- Fee comparison complicated by
- Different start dates.
- K-Factor
- Real increases above inflation.
- Bloemfontein from 0.623 to 0.789 six monthly.
- Louis Trichardt six monthly increases
- Years 2-3 6
- Years 4-5 5
- Year 6 4
- Years 7-9 2
- Years 10-13 1
- Years 14-25 3 decrease each 6 months
- Net Present Value of all fees (8 discount rate)
- Bloemfontein R1.3 billion
- Louis Trichardt R1.2 billion
17REAL INDEXED FEE ADJUSTED FOR K-FACTOR
18BREAKDOWN OF OPERATING COSTS (BLOEMFONTEIN)
19BREAKDOWN OF OPERATING COSTS (LOUIS TRICHARDT)
20EXISTING PPP PRISONS FINANCE
21 RISK ALLOCATIONTECHNICAL / OPERATIONAL
22RISK ALLOCATION LEGAL / FINANCIAL
232. OPTIONS FOR RE-NEGOTIATION OF EXISTING
CONTRACTS
24OPTIONS FOR RE-NEGOTIATION
- Construction Expenditure
- None.
- Operating Expenditure
- Changes in levels of service.
- Amendments to fee payment structure.
- Change in prisoner numbers.
- Refinancing
- Possible conversion of debt portfolio to
inflation-linked funding.
25OPTIONS FOR RE-NEGOTIATIONOPERATING EXPENDITURE
- Staff costs
- Hours out of cell.
- Service specifications.
- Rehabilitation and Health Care
- Change in specifications.
- Fee payment structure
- Amendments to K-factor adjustments to improve
cashflows. - Change in Prisoner Numbers
- Bloemfontein 2 new units.
- Louis Trichardt convert 2-bed cells to 4-bed
cells and use reception/special
treatment centre.
26OPTIONS FOR RE-NEGOTIATIONINDICATIVE FEE
CALCULATION
27OPTIONS FOR RE-NEGOTIATIONREFINANCING
- Methodology
- Net Present Value of unexpired portion of debt
(settlement estimate). - Convert into new CPI-linked bond debt and
calculate new repayments and NPVs. - Compare with existing payments.
28OPTIONS FOR RE-NEGOTIATION RE-FINANCING
ASSUMPTIONS
29OPTIONS FOR RE-NEGOTIATIONRE-FINANCING BENEFITS
(BLOEMFONTEIN)
30OPTIONS FOR RE-NEGOTIATIONRE-FINANCING BENEFITS
(LOUIS TRICHARDT)
313. CONCLUSIONS RECOMMENDATIONS EXISTING PPP
CONTRACTS
32CONCLUSION EXISTING CONTRACTS
- The PPP Prison Projects delivered according to
DCS specifications, notably achieving - Competitive construction costs.
- Construction on time, on budget.
- Fast-track delivery (lt 2years full capacity).
- Comparative operating costs.
- Significant black equity and sub-contracting
- Significantly higher-quality facilities.
- Significantly higher-levels of service.
- Appropriate risk allocation.
- But
33CONCLUSIONS PROBLEMS WITH EXISTING CONTRACTS
- DCS specifications were too high (the PPP prisons
remain driven by DCS input specifications). - Relatively high cost of debt.
- Higher than normal return on equity.
- Additional budgeting pressures for DCS.
- Despite overcrowding in DCS system, no ability to
over-populate PPP prisons.
34RECOMMENDATION EXISTING PROJECTS
- Operating
- Engage contractors in order to improve Value for
Money by - Reviewing standards and specifications.
- Amending fee payment structure.
- Consider options for extra prisoners on a
marginal cost per prisoner basis. Proposed
Feasibility Protocol will be used by DCS to
determine optimal value for money - Finance
- Engage contractors to
- Improve cash flows and NPV and
- Consider converting debt portfolio to
inflation-linked funding.
35PART II FUTURE PRISON PROJECTS
361. ILLUSTRATIVE COMPARISONSPUBLIC AND PPP
PRISONS
37BARRIERS TO DIRECT COMPARISON BETWEEN PPP AND
PUBLIC PRISONS
- CAPITAL COSTS
- Dates of construction
- Type of prison
- Inmates per cell
- Location
- Risk transfer
- Split functions DPW/DCS
- Inclusion of staff housing
- Capacities
- Security levels
- Technology and design
- OPERATING COSTS
- Overcrowding
- Standards of facilities
- Standards of activities
- Hours out of cell
- Rehabilitation
- Health facilities
- Risk transfer penalties
- In-house food services
- Availability of information
38ILLUSTRATIVE COMPARISON RISK TRANSFER IN RESPECT
OF CAPITAL COST
39 REASONS FOR DIFFICULTIES IN COMPARING PRISON
CONSTRUCTION COSTS
- Prisons differ by
- Type (e.g. super max, max, medium, youth centres,
etc.) - Size (inmates varies from lt1000 to gt3000).
- Constructed at different times, different
operating philosophies. - Different geographic locations
construction/logistical problems. - DCS does not have a cost centre focus PPP
operators have different cost allocation
structures. - Functions and costs split between DCS DPW.
- Historical procurement problems created
inefficiencies.
40ILLUSTRATIVE COMPARISON FUNDED CONSTRUCTION
COST FORGOVERNMENT
41ILLUSTRATIVE COMPARISON OPERATING COSTS
42 REASONS FOR DIFFICULTIES IN COMPARING PRISON
OPERATING COSTS
- Overcrowding of public prisons.
- Prisons differ by
- Type (e.g. super max, max, medium, youth centres,
etc.) - Standards of facilities (health, catering,
recreation, etc.) - Standards of activities (education, vocational
training, work). - Hours out of cell.
- Different operating philosophies, often result of
different design. - DCS does not have a cost centre focus to
accounting. - PPP operators have different cost allocation
structures. - Risk transfer differs.
432. FUTURE EVALUATION METHODOLOGY FEASIBILITY
PROTOCOL
44PROPOSED FUTURE EVALUATION METHODOLOGY FOR NEW
PRISONS
- Applicable for projects as both PPP and
conventional procurement. - Purpose is to assess all options based on clear
output specifications. - For all choices, DCS needs to demonstrate
- Affordability
- Value for Money
- Acknowledgement and treatment of risk
45FUTURE EVALUATION METHODOLOGY FEASIBILITY
PROTOCOL
46FUTURE EVALUATION METHODOLOGY FEASIBILITY
PROTOCOL
47FUTURE EVALUATION METHODOLOGY FEASIBILITY
PROTOCOL
48FUTURE EVALUATION METHODOLOGY FEASIBILITY
PROTOCOL
493. CONCLUSIONS RECOMMENDATIONS FUTURE PRISON
PROJECTS
50RECOMMENDATION FEASIBILITY PROTOCOL FOR FUTURE
PROJECTS
- DCS to clearly establish output specifications
(for design operations). - Establish budget constraints.
- Develop comparable accounting standards for both
PPP and DCS-operated prisons. - Adopt clear rules for DCS staff movement during
any future PPP procurements. - Comprehensive feasibility
- Cost private design, finance, build and operate,
versus - Risk-adjusted Public Sector Comparator.
- Results
- If clear distinction Adopt.
- If depends on assumptions Policy decision or
pilot comparisons.
51PART IIITASK TEAMS RECOMMENDATIONS FOR NEXT
STEPS
52TASK TEAMS RECOMMENDATIONS FORNEXT STEPS
53TASK TEAMS RECOMMENDATIONS FORNEXT STEPS
54MINISTERS OF CORRECTIONAL SERVICES, FINANCE,
PUBLIC WORKS andPARLIAMENTARY PORTFOLIO
COMMITTEE ON CORRECTIONAL SERVICES
REVIEW REPORT SUBMITTED TO