DEVELOPMENT CONTRIBUTIONS POLICY
  • Public Meeting
  • 18 April 2007

2
What are Development Contributions?
  • contributions of money or land to fund the costs
    of
  • reserves,
  • network infrastructure (water supply and
    conservation, wastewater collection treatment and
    disposal, surface water management and transport)
    and
  • community infrastructure (leisure facilities).
  • when a new development (that will increase the
  • demand for services) is undertaken.

3
What will development contributions be used for?
  • to pay for new reserves and infrastructure or
    for increasing the capacity of existing
    infrastructure required as a result of growth.
  • In the past, dividends from Council investments
    together with rates, have mostly paid for the
    additional infrastructure.  
  • Not to be used to pay for renewing existing
    infrastructure or catch up a backlog of upgrading
    to reach agreed Levels of Service, other than
    capacity increase to cater for extra demand as a
    result of growth.


4
Why does the Council have development
contributions?
  • There have been some financial contributions from
    developers (e.g. reserve contributions) but until
    2002 LGA Act, ability to collect was limited.
  • Development contributions enable the Council to
    obtain a larger share of the cost of growth
    related new infrastructure from developers, i.e.
    those who are creating the growth.

5
Why does the Council have development
contributions? cont.
  • (NOTE Developers are any applicant for a
    resource consent, building consent or service
    connection where a development contribution is
    payable.)
  • The Councils proposed 10 year capital works
    programme (reserves and infrastructure) has been
    costed at 1.4 billion.
  • Of this 324.7M is attributable to growth, with
    273M estimated to be recoverable from DCs.
  • This amounts to 19.5 of that total capex being
    met from DCs.

6
When were they first introduced?
  • First introduced to both CCC and the then BPDC
    on 1 July 2004 (ie as part of the 2004-14
    LTCCPs).
  • They apply to any application for resource
    consent, building consent or a service connection
    lodged and granted on or after 1 July 2004.
  • The 2006-16 LTCCP incorporated a revised and
    expanded Development Contribution Policy
  • (Christchurch City area) and the existing Policy
    (Banks Peninsula area).

7
Background to Current Review
  • For the old CCC area (but not BPDC), Draft
    2006-16 DCP used new methodology, added new areas
    of charging, resulting in a significant increase
    from the 2004 charges.
  • Development community expressed concerns through
    submission process about quantum and timing of
    changes
  • Council decision, June 06
  • - 12 month freeze (2006 charges aligned with
    2004 charges)
  • - Further review, with Working Party
  • - Banks Peninsula DCP to be integrated via
    SCP in 2007

8
The DCPR Working Party
  • 9 development industry reps.
  • 4 Councillors, inc the Mayor and Cr Bob Parker
  • Independent Chair - David Caygill
  • Terms of Reference
  • To review the basis, structure and application
    of the 2006-16 Development Contributions Policy
    as adopted by the Council on 30 June 2006, and,
    if appropriate, to recommend a revised policy for
    the Council to consider as part of an amended
    LTCCP in 2007.
  • The Working Party reported back to Council in
    February 2007
  • with some 16 recommendations, most of which the
    Council has
  • agreed to.

9
Council decision on DCP 23 March 07
  • Revised DCP, incorporating changes requested by
    Working Party, plus technical and other
    improvements recommended by staff, approved by
    Council for consultation. DCP now includes
    former BPDC.
  • Decision made on setting contribution charges,
    taking into account likely impact on the market
    of significant increases, in early years of
    implementation
  • Developers to pay full costs of growth
  • Charges to be transitioned in over 3 years
  • No transition for reserves contributions

10
Financial Basis of the DC Policy
11
Topics covered in this section
  • Basis of the charge
  • What is the growth in the community
  • What is a Household Unit Equivalent
  • What is the Capital expenditure response to that
    growth
  • The DC charges
  • When do we charge
  • What credits are applied
  • Assessments
  • Examples

12
Basis of the charge Growth in the Community
  • Residential 12,500 new households over the next
    ten years
  • Non residential
  • New lots 542 based on average size
  • New GFA 600,000 m2 (gross floor area)
  • New ISA 900,000 m2 (impervious surface area)

13
Basis of the charge Units of demand - HUEs
  • Council response to growth is to supply more
    assets
  • To maintain levels of service within the expanded
    city
  • Services are organised into activities water,
    transport etc
  • Unit of demand per activity for growth in the
    asset base is expressed as a Household Unit
    Equivalent or HUE

14
Basis of the charge HUEs
  • This is how all land uses are converted to a
    common charge basis
  • HUE Basic unit of charge one per household
    unit
  • Straightforward for residential developments
    one per household (subject to small unit
    discount)
  • Non residential developments require an
    equivalence dependent on land use
  • gross floor area (GFA) for buildings developed or
  • impervious surface area (ISA)

15
Basis of the charge Application of HUEs
  • Residential -
  • one per household unit
  • Subject to a Small unit adjustment
  • where less than 100 m2 down to 60 m2 building
    Floor area
  • E.g. 80 m2 has 80 HUE
  • Non residential see equivalence tables
  • DCs for all land uses
  • Reserves one HUE charge per lot
  • Surface water management 3.75 HUE /1000 m2 of
    ISA for all non residential land uses
  • DC depends on land use - per 1000 m2 of gfa
  • Water supply - 3 to 5 HUE
  • Waste water collection and treatment 3.6 to 5.7
    HUE
  • Transport 1 to 3.5 HUE

16
Basis of the charge Capital expenditure
  • Capital expenditure based on the service
    activities
  • Planned capital expenditure necessary to maintain
    levels of service when the growth occurs, within
  • Water supply
  • Waste water
  • Transport
  • Surface water management
  • Reserves
  • Community infrastructure
  • The demand for the expanded capital expenditure
    converted into a cost per HUE (a unit of demand)
    for each activity

17
Water Supply and Conservation
  • Capital Programme Drivers
  • Replacement of assets that have reached the end
    of their useful life
  • Reliability of supply
  • Drinking Water Standards
  • NRRP
  • Provide for future development

18
Water Supply and Conservation
  • Catchment (serviced land only)
  • a single catchment for the Greater Christchurch
    area as network is largely interconnected.
  • Full DC HUE Charge - 2009/2010
  • 2,292.49 (charge excludes gst)
  • (i.e. the charge that would apply to a new
    residential unit or approximately a 300 m2 gross
    floor area non residential unit)

19
Water Supply and Conservation
  • Key Projects supporting development
  • New Wells and Pumping Stations
  • New water mains
  • Additional Reservoir Storage

20
Wastewater
  • Capital Programme Drivers
  • Replacement/ renewal of assets
  • Major Sewer Upgrades
  • To meet growth Levels of Service.
  • To meet Resource Consent conditions
  • Pumping Station Upgrades
  • Ocean Outfall
  • Treatment Plant Upgrades

21
Wastewater
  • Catchment (serviced land only)
  • a single catchment for the Greater Christchurch
    area
  • Full DC HUE Charge 2009/10
  • 6,841.47 (charge excludes gst)
  • (i.e. the charges that would apply to a new
    residential unit or approximately a 300 m2 gross
    floor area non residential unit)

22
Wastewater
  • Key Projects supporting development
  • New sewer pipes
  • New or upgrades to pumping stations
  • Major Trunk sewer extensions
  • Storage
  • Improvements and upgrades to waste water
    treatment plants
  • Construction of Ocean Outfall

23
Transport
  • Capital Programme Drivers
  • Provide travel facilities for people living ,
    working and visiting the City.
  • Street corridors also provide access for utility
    services.
  • Integrating land use planning with planning of
    transport (and other) infrastructure
  • Ensuring the citys transport infrastructure
    meets current and future needs

24
Transport
  • Catchment
  • a single catchment for the Greater Christchurch
    area as network is interconnected.
  • Full DC HUE Charge 2009/10
  • 1,697.11 (charge excludes gst)
  • (i.e. the charge that would apply to a new
    residential unit or approximately a 160 m2 gross
    floor area non residential unit)

25
Transport
  • Key Projects supporting development
  • Road widening schemes e.g. Ferry Road, Hills
    Road, four laning
  • Expansion of Bus Exchange
  • Intersection improvements

26
Surface Water Management
  • Capital Programme Drivers
  • Meet levels of service
  • Protect surface water, groundwater and springs
    resource.
  • Preserve natural features including watercourses
    and wetlands.
  • Meet the demands of infill and greater density in
    inner suburbs.

27
Surface Water Management
  • Catchment
  • 10 catchments based on natural drainage areas-
    Avon, Halswell, Estuary, Heathcote, Otukaikino,
    Styx, Akaroa, Lyttleton, Nrthern Bays Srthern
    Bays.
  • Full DC HUE Charges 2009/10
  • - is dependent on catchment
  • Avon - 1,721.12
    (charges exclude gst)
  • Halswell - 2,132.45
  • Estuary - 2,153.38
  • Heathcote - 2,721.12
  • Otukaikino - 419.20
  • Styx - 506.30
  • Peninsula - Nil (no
    capital projects at present)
  • (i.e. the charge that would apply to a new
    residential unit or to an approximately 270 m2
    impervious surface area non residential unit)

28
Surface Water Management
  • Key Projects supporting development
  • Land purchases to accommodate retention basins
  • Land purchases to increase capacity of water ways
  • Improvements to existing pipe networks to
    increase capacity

29
Reserves
  • Capital Programme Drivers
  • Level of Service criteria used,
  • 13 ha / 1000 population for Regional Parks and
    Reserves
  • 4.7 ha / 1000 population for local parks
  • (approx 120 m2 per lot)
  • Therefore increased population through new
    development the key driver.
  • Maintaining Garden City Image

30
Reserves
  • Catchment
  • A single catchment for the Greater Christchurch
    area.
  • Full DC HUE Charge 2009/10
  • 12,272.00 (charge excludes gst)
  • (i.e. the charge that would apply to a new
    residential unit/s or lot/s or non residential
    lot/s)
  • Note 1 Is subject to the maximum set by LGA
  • (7.5 of the value of additional lots or 20
    m2 of land value)
  • Note 2 No transitional discount for Reserves
    ie this charge applies from
  • 2007/8. Small residential unit
    discount applies for units less than 100m2

31
Reserves
  • Key Projects supporting development
  • Land purchases for new reserves to meet level of
    service target
  • Land purchases for new local parks to meet level
    of service
  • Provision of infrastructure and planting on new
    reserves and local parks

32
Leisure Facilities(Community Infrastructure)
  • Capital Programme Drivers
  • Provide a range of community facilities that
    support the growth and development of the City

33
Leisure Facilities
  • Catchment
  • Six catchments - East, North, West, South,
    Lyttleton / Mt Herbert and Akaroa / Wairewa.
  • Full DC HUE Charges 2009/10
  • (i.e. the charge that would apply to a new
    residential unit - there is no non residential
    fixed charge)
  • East - 672.67 (charges exclude gst)
  • North - 1,079.59
  • West - 1,743.34
  • South - 464.2
  • Lyt./Mt H - nil (no capital projects at
    present)
  • Ak./Wai. - nil

34
Leisure Facilities
  • Key Projects supporting development
  • Jellie Park redevelopment and expansion.
  • New multi use facility in the North of the city.
  • Redevelopment and upgrades to existing leisure
    facilities around the City.

35
Capital Programme DC Charges
  • Asset 10 year total Growth
    Component Est. DC collection
  • Cap. Program
  • Water 112.3M 26.9M (23.9) 22.9M
    (20.4)
  • Waste 340.7M 81.2M (23.8) 79.0M
    (23.2)
  • Water
  • Transport 649.9M 28.3M (4.3) 24.0M
    (3.7)
  • Surface 82.0M 21.4M (26.1) 15.0M
    (18.3)
  • Water
  • Reserves 170.0M 160.6M (94.4)
    137.1M (80.6)
  • Leisure 45.9M 6.3M (13.7) 5.0M
    (10.9)

36
The DC charges - charged to developments
  • Development generates additional demand for
    services
  • In this context developments are
  • Subdivisions creating new lots
  • Construction of new households, or
  • Construction of other GFA and ISA on lots
  • Charge for each activity per HUE assessed for
    each development

37
The DC charges - on Subdivision
  • Each lot on subdivision will incur one HUE charge
    for each activity.
  • For all the activities where the services are
    available
  • Less credit against the charge, being the
    greater of
  • Credit of one HUE charge for each existing lot
  • Credit of GFA/ISA/HUE equivalents for existing
    developments
  • Demolition / destruction of previous developments
  • The HUE credits from the development
    demolished, subject to
  • Replacement development within ten years,
  • Non residential only - un-developed pre-existing
    lots
  • Credit of the average HUE for zone based on lot
    area where
  • the lot was created before 1 July 2004, and
  • Is undeveloped at the time of subdivision

38
The DC charges At Building Consent
  • Residential -
  • All additional residential units incur HUE
    charges, subject to
  • a small residential unit adjustment
  • Demolition credits use it or lose it after ten
    years.
  • Non residential
  • Charge based on HUE calculated for the
    development
  • Less credits - the greater of
  • one HUE charge if the lot was inside the serviced
    area, or
  • average for zone based on lot area where
  • the lot was created before 1 July 2004, and
  • Is still undeveloped at the time of subdivision,
    or
  • Demolition / destruction of previous developments
  • The HUE credits from the development demolished,
    subject to the replacement commenced within ten
    years

39
The DC charge discounts
  • Current 06/07 charge is 15 of full charge
  • The proposed full DC charge has been reduced for
    2007/08 by 57
  • The discount is reduced 2008/9 to 28, and
  • the discount is removed in 2009/10
  • Reserves DCs are not discounted
  • The full reserves fee has been charged in the
    past
  • The basis of charge has changed.
  • Subject to the reserves maximum

40
The DC charges
  • No other remissions are provided

41
Assessments
42
(No Transcript)
43
(No Transcript)
44
(No Transcript)
45
(No Transcript)
46
(No Transcript)
47
(No Transcript)
48
(No Transcript)
49
(No Transcript)
50
(No Transcript)
51
(No Transcript)
52
(No Transcript)
53
Conclusion
54
  • North Shore Decision
  • Consultation process and times
  • Question time

55
North Shore Decision
  • North Shore City Council DCP High Court Decision
    has now been released.
  • This was about the legality of parts of the Noth
    Shore DCP.
  • Councils around NZ, including CCC, are currently
    studying the implications of the decision.
  • Decision may be appealed , so law is still not
    clear!
  • Some elements of our DCP will need to be adjusted
  • DCP will be amended as needed prior to final
    approval in June.

56
Consultation Process
  • Public consultation on DCP (and Annual Plan and
    some other LTCCP issues) from 11 April 11 May
  • Hearings from 28 May-5 June
  • Council decisions by 30 June
  • New DCP to take effect from July 1

57
Public Meetings
  • Date Wednesday 11 April
  • Topic Development Contributions
  • Venue Our City, Cnr Oxford Terrace and Worcester
    Street, Christchurch
  • Time 5.30 7.30 pm
  • Date Monday 16 April
  • Topic Annual Plan amendments to the Long-Term
    Council Community Plan (including the Development
    Contributions Policy)
  • Venue Council Chambers, 163-173 Tuam Street,
    Christchurch
  • Time 7 9pm

58
  • Date Wednesday 18 April
  • Topic Annual Plan amendments to the Long-Term
    Council Community Plan (including the Development
    Contributions Policy)
  • Venue Diamond Harbour Community Centre, Waipapa
    Avenue, Diamond Harbour
  • Time 7 9pm
  • Date Tuesday 24 April
  • Topic Annual Plan amendments to the Long-Term
    Council Community Plan (including the Development
    Contributions Policy)
  • Venue Akaroa Sports Complex, Recreation Ground,
    Akaroa
  • Time 1 3pm
  • Date Thursday 3 May
  • Topic Development Contributions
  • Venue Council Chambers, 163 -173 Tuam Street,
    Christchurch
  • Time 5.30 - 7.30 pm

59
CCC Contacts
  • Simon Louttit, Development Contributions Mgr,
    Regulation Democracy Services, ph 941 6221
  • Geoff Barnes, Funds and Financial Policy Mgr,
    Corporate Services, ph 941 8447
  • Terry Howes, Asset Network Planning Mgr, City
    Environment, ph 941 8160
  • Dave Hinman, Principal Adviser, Strategy and
    Planning, ph 941 8804

60
Question time!
  • Note should there be any contradiction between
    the statements in the seminar slides and the
    draft policy text, the specific text of the
    policy will apply