Title: DEVELOPMENT CONTRIBUTIONS POLICY
1DEVELOPMENT CONTRIBUTIONS POLICY
- Public Meeting
- 11 April 2007
2What are Development Contributions?
- contributions of money or land to fund the costs
of - reserves,
- network infrastructure (water supply and
conservation, wastewater collection treatment and
disposal, surface water management and transport)
and - community infrastructure (leisure facilities).
- when a new development (that will increase the
- demand for services) is undertaken.
3What will development contributions be used for?
- to pay for new infrastructure or for increasing
the capacity of existing infrastructure required
as a result of growth. - Not to be used to pay for renewing existing
infrastructure or catch up a backlog of upgrading
to reach agreed Levels of Service, other than
capacity increase to cater for extra demand as a
result of growth. -
4Why does the Council have development
contributions?
- It is in response to the steady growth of
Christchurch. - With growth will come an increased demand for
reserves, network infrastructure (e.g. water
supply) and community infrastructure (e.g.
facilities). - In the past, dividends from Council investments
together with rates, have mostly paid for the
additional infrastructure.
5Why does the Council have development
contributions? cont.
- There have been some financial contributions from
developers (eg reserve contributions) but until
2002 LGA Act, ability to collect was limited. - Development contributions enable the Council to
obtain a larger share of the cost of growth
related new infrastructure from developers, i.e.
those who are creating the growth.
6Why does the Council have development
contributions? cont.
- (NOTE Developers are any applicant for a
resource consent, building consent or service
connection where a development contribution is
payable.) - The Councils proposed 10 year capital works
programme has been costed at 1.4 billion. - Of this 324.7M is attributable to growth, with
273M estimated to be recoverable from DCs. - This amounts to 19.5 of that total capex being
met from DCs.
7When were they first introduced?
- First introduced to both CCC and the then BPDC
on 1 July 2004 (ie as part of the 2004-14
LTCCPs). - They apply to any application for resource
consent, building consent or a service connection
lodged and granted on or after 1 July 2004. - The 2006-16 LTCCP incorporated a revised and
expanded Development Contribution Policy - (Christchurch City area) and the existing Policy
(Banks Peninsula area). -
8Background to Current Review
- Draft 2006-16 DCP used new methodology, added new
areas of charging, resulting in a significant
increase from the 2004 charges. - Development community expressed concerns through
submission process about quantum and timing of
changes - Council decision, June 06
- - 12 month freeze (04 charges retained)
- - Further review, with Working Party
- - Banks Peninsula DCP to be integrated via
SCP in 2007
9The DCPR Working Party
- 9 development industry reps.
- 4 Councillors, inc the Mayor
- Independent Chair - David Caygill
- Terms of Reference
- To review the basis, structure and application
of the 2006-16 Development Contributions Policy
as adopted by the Council on 30 June 2006, and,
if appropriate, to recommend a revised policy for
the Council to consider as part of an amended
LTCCP in 2007.
10Working Party reported back to the Council in
February 2007
- Most of its recommendations were agreed to and
have been incorporated in the reviewed Policy,
including - Some technical/wording improvements
- On-going liaison with development community
- Independent review of level of costs allocated to
growth - Changes to ensure better causal link between
charges and growth - Small unit weighting for multiple res. Units
- Move from based to HUE cost based approach for
reserves single catchment as an interim measure - Credits for undeveloped residential lots
quantum confirmed - Charging for past projects confirmed
- Banks Peninsula charging regime confirmed
mostly a single, city-wide catchment - Improvement of alignment of DCPs of adjoining
councils via UDS.
11- Decision made on setting contribution charges,
taking into account likely impact on the market
of significant increases, in early years of
implementation - Developers to pay full costs of growth
- Charges to be transitioned in over 3 years
- No transition for reserves contributions
12 Financial Basis of the DC Policy
13Topics covered in this section
- Basis of the charge
- What is the growth in the community
- What is a Household Unit Equivalent
- What is the Capital expenditure response to that
growth - The DC charges
- When do we charge
- What credits are applied
- Assessments
- Examples
14Basis of the charge Growth in the Community
- Residential 12,500 new households over the next
ten years - Non residential
- New lots 542 based on average size
- New GFA 600,000 m2 (gross floor area)
- New ISA 900,000 m2 (impervious surface area)
15Basis of the charge Units of demand - HUEs
- Council response to growth is to supply more
assets - To maintain levels of service within the expanded
city - Services are organised into activities water,
transport etc - Unit of demand per activity for growth in the
asset base is expressed as an Household Unit
Equivalent or HUE
16Basis of the charge HUEs
- This is how are all land uses are converted to a
common charge basis - HUE Basic unit of charge one per household
unit - Straightforward for residential developments
one per household - Non residential developments require an
equivalence, uses - gross floor area (GFA) for buildings developed or
- impervious surface area (ISA)
17Basis of the charge Application of HUEs
- Residential -
- one per household unit
- Subject to a Small unit adjustment
- where less than 100 m2 down to 60 m2 building
Floor area - Eg 80 m2 has 80 HUE
- Non residential see equivalence tables
- DCs for all land uses
- Reserves one HUE charge per lot
- Surface water management 3.75 HUE /1000 m2 of
ISA for all non residential land uses - DC depends on land use - per 1000 m2 of gfa
- Water supply - 3 to 5 HUE
- Waste water collection and treatment 3.6 to 5.7
HUE - Transport 1 to 3.5 HUE
18Basis of the charge Capital expenditure
- Capital expenditure based on the service
activities - Planned capital expenditure necessary to maintain
levels of service when the growth occurs, within - Water supply
- Waste water
- Transport
- Surface water management
- Reserves
- Community infrastructure
- The demand for the expanded capital expenditure
converted into a cost per HUE (a unit of demand)
for each activity
19Water Supply and Conservation
- Drivers
- Replacement of assets that have reached the end
of their useful life - Reliability of supply
- Drinking Water Standards
- NRRP
- Provide for future development
20Water Supply and Conservation
- Catchment (serviced land only)
- a single catchment for the Greater Christchurch
area as network is largely interconnected. - Ten year total capital programme
112.3
million - Growth Component
Total capital costs attributed to growth - 26.9 million (23.9 of the total capital
programme) - Estimated funds from development
contributions 22.9 million
(20.4 of the total capital programme)
21Water Supply and Conservation
22Water Supply and Conservation
- Full DC HUE Charge - 2009/2010
- 2,292.49 (charge excludes gst)
- (i.e. the charge that would apply to a new
residential unit or approximately a 300 m2 gross
floor area non residential unit)
23Water Supply and Conservation
- Key Projects supporting development
- New Wells and Pumping Stations
- New water mains
- Additional Reservoir Storage
24Wastewater
- Drivers
- Replacement/ renewal of assets
- Major Sewer Upgrades
- To meet growth Levels of Service.
- To meet Resource Consent conditions
- Pumping Station Upgrades
- Ocean Outfall
- Treatment Plant Upgrades
25Wastewater
- Catchment (serviced land only)
- a single catchment for the Greater Christchurch
area - Total capital programme
340.7 million - Growth Component
- Total capital costs attributed to growth
- 81.2 million (23.8 of the total capital
programme) - Estimated funds from development
contributions - 79.0 million (23.2 of the total
capital programme)
26Wastewater
27Wastewater
- Full DC HUE Charge 2009/10
- 6,841.47 (charge excludes gst)
- (i.e. the charges that would apply to a new
residential unit or approximately a 300 m2 gross
floor area non residential unit)
28Wastewater
- Key Projects supporting development
- New sewer pipes
- New or upgrades to pumping stations
- Major Trunk sewer extensions
- Storage
- Improvements and upgrades to waste water
treatment plants - Construction of Ocean Outfall
29Transport
- Drivers
- Provide travel facilities for people living ,
working and visiting the City. - Street corridors also provide access for utility
services. - Integrating land use planning with planning of
transport (and other) infrastructure - Ensuring the citys transport infrastructure
meets current and future needs -
30Transport
- Catchment
- a single catchment for the Greater Christchurch
area as network is interconnected. - Total capital programme
649.9 million - Growth Component
- Total capital costs attributed to growth
- 28.3 million (4.3 of the total
capital programme) - Estimated funds from development
contributions 24.0 million
(3.7 of the total
capital programme)
31Transport
32Transport
- Full DC HUE Charge 2009/10
- 1,697.11 (charge excludes gst)
- (i.e. the charge that would apply to a new
residential unit or approximately a 160 m2 gross
floor area non residential unit)
33Transport
- Key Projects supporting development
- Road widening schemes e.g. Ferry Road, Hills
Road, four laning - Expansion of Bus Exchange
- Intersection improvements
34Surface Water Management
- Drivers
- Meet levels of service
- Protect surface water, groundwater and springs
resource. - Preserve natural features including watercourses
and wetlands. - Meet the demands of infill and greater density in
inner suburbs.
35Surface Water Management
- Catchment
Ten catchments based on natural drainage
areas- Avon, Halswell, Estuary, Heathcote,
Otukaikino, Styx, Akaroa, Lyttleton, Northern
Bays and Southern Bays. - Total capital programme
82.0 million - Growth Component
- Total capital costs attributed to growth
- 21.4 million (26.1 of the total capital
programme) - Estimated funds from development
contributions 15.0 million
(18.3 of the total capital programme)
36Surface Water Management
- Full DC HUE Charges 2009/10
- - is dependent on catchment
- Avon - 1,721.12
(charges exclude gst) - Halswell - 2,132.45
- Estuary - 2,153.38
- Heathcote - 2,721.12
- Otukaikino - 419.20
- Styx - 506.30
- Peninsula - Nil (no capital
projects at present) -
- (i.e. the charge that would apply to a new
residential unit or to an approximately 270 m2
impervious surface area non residential unit) -
37Surface Water Management
- Key Projects supporting development
- Land purchases to accommodate retention basins
- Land purchases to increase capacity of water ways
- Improvements to existing pipe networks to
increase capacity
38Reserves
- Drivers
- Level of Service criteria used,
- 13 ha / 1000 population for Regional Parks and
Reserves - 4.7 ha / 1000 population for local parks
- (approx 120 m2 per lot)
- Therefore increased population through new
development the key driver. - Maintaining Garden City Image
39Reserves
- Catchment
- A single catchment for the Greater Christchurch
area. - Total capital programme
170.0 million - Growth Component
- Total capital costs attributed to growth
- 160.6 million (94.4 of the total capital
programme) - Estimated funds from development
contributions 137.1 million
(80.6 of the total capital programme)
40Reserves
- Full DC HUE Charge 2009/10
- 12,272.00 (charge excludes gst)
- (i.e. the charge that would apply to a new
residential unit or non residential unit) - Charged when
- At any subdivision creating new lots
- On construction of second additional dwelling
on any lot - Subject to the maximum
- 7.5 of the value of additional lots
- 20 m2 of land value
- No transitional discount for Reserves
41Reserves
- Key Projects supporting development
- Land purchases for new reserves to meet level of
service target - Land purchases for new local parks to meet level
of service - Provision of infrastructure and planting on new
reserves and local parks
42Leisure Facilities
- Drivers
- Provide a range of community facilities that
support the growth and development of the City -
43Leisure Facilities
- Catchment
Six catchments - East, North, West,
South, - Lyttleton / Mt Herbert and Akaroa / Wairewa.
- Total capital programme
45.9 million - Growth Component
- Total capital costs attributed to growth
- 6.3 million (13.7 of the total capital
programme) - Estimated funds from development
contributions 5.0 million
(10.9 of the total capital programme)
44Leisure Facilities
- Full DC HUE Charges 2009/10
- (i.e. the charge that would apply to a new
residential unit - there is no non residential
charge) - East - 672.67 (charges exclude gst)
- North - 1,079.59
- West - 1,743.34
- South - 464.2
- Lyt./Mt H - nil (no capital projects at
present) - Ak./Wai. - nil
-
-
45Leisure Facilities
- Key Projects supporting development
- Jellie Park redevelopment and expansion.
- New multi use facility in the North of the city.
- Redevelopment and upgrades to existing leisure
facilities around the City.
46Capex DC charges
47The DC charges - charged to developments
- Development generates additional demand for
services - In this context developments are
- Subdivisions creating new lots
- Construction of new households, or
- Construction of other GFA and ISA on lots
- Charge for each activity per HUE assessed for
each development
48The DC charges - on Subdivision
- Each lot on subdivision will incur one HUE charge
for each activity. - For all the activities where the services are
available - Less credit against the charge,
- being the greater of
- Credit of one HUE charge for each existing lot
- Credit of GFA/ISA/HUE equivalents for existing
developments - Demolition / destruction of previous developments
- The HUE credits from the development demolished,
subject to - Replacement development within ten years,
- Non residential only - un-developed pre-existing
lots - Credit of the average HUE for zone based on lot
area where - the lot was created before 1 July 2004, and
- Is undeveloped at the time of subdivision
49The DC charges At Building Consent
- Residential -
- All additional residential units incur HUE
charges, subject to - a small residential unit adjustment (not for
Reserves DC charge). - Demolition credits use it or loose it after ten
years. - Non residential
- Charge based on HUE calculated for the
development - Less credits - the greater of
- one HUE charge if the lot was inside the serviced
area, or - average for zone based on lot area where
- the lot was created before 1 July 2004, and
- Is still undeveloped at the time of subdivision,
or - Demolition / destruction of previous developments
- The HUE credits from the development demolished,
subject to the replacement commenced within ten
years
50The DC charge discounts
- Current 06/07 charge is 15 of full charge
- The proposed full DC charge has been reduced for
2007/08 by 57 - The discount is reduced 2008/9 to 28, and
- the discount is removed in 2009
- Reserves DCs are not discounted
- The full reserves fee has been charged in the
past - The basis of charge has changed.
- Subject to the reserves maximum
51The DC charges
- No other remissions are provided
52Assessments
53(No Transcript)
54(No Transcript)
55(No Transcript)
56(No Transcript)
57(No Transcript)
58(No Transcript)
59Conclusion
60- North Shore Decision
- Consultation process and times
- Question time
61- North Shore City Council DCP High Court Decision
has now been released. - This was about the legality of parts of the Noth
Shore DCP. - Councils around NZ, including CCC, are currently
studying the implications of the decision. - Decision may be appealed , so law is still not
clear! - Some elements of our DCP will need to be adjusted
- DCP will be amended as needed prior to final
approval in June.
62Consultation Process
- Public consultation on DCP (and Annual Plan and
some other LTCCP issues) from 11 April 11 May - Hearings from 28 May-5 June
- Council decisions by 30 June
- New DCP to take effect from July 1
63Public Meetings
- Date Wednesday 11 April
- Topic Development Contributions
- Venue Our City, Cnr Oxford Terrace and Worcester
Street, Christchurch - Time 5.30 7.30 pm
- Date Monday 16 April
- Topic Annual Plan amendments to the Long-Term
Council Community Plan (including the Development
Contributions Policy) - Venue Council Chambers, 163-173 Tuam Street,
Christchurch - Time 7 9pm
64- Date Wednesday 18 April
- Topic Annual Plan amendments to the Long-Term
Council Community Plan (including the Development
Contributions Policy) - Venue Diamond Harbour Community Centre, Waipapa
Avenue, Diamond Harbour - Time 7 9pm
- Date Tuesday 24 April
- Topic Annual Plan amendments to the Long-Term
Council Community Plan (including the Development
Contributions Policy) - Venue Akaroa Sports Complex, Recreation Ground,
Akaroa - Time 1 3pm
- Date Thursday 3 May
- Topic Development Contributions
- Venue Council Chambers, 163 -173 Tuam Street,
Christchurch - Time 5.30 - 7.30 pm
65Question time!
- Note should there be any contradiction between
the statements in the seminar slides and the
draft policy text, the specific text of the
policy will apply
66CCC Contacts
- Simon Louttit, Development Contributions Mgr,
Regulation Democracy Services, ph 941 6221 - Geoff Barnes, Funds and Financial Policy Mgr,
Corporate Services, ph 941 8447 - Terry Howes, Asset Network Planning Mgr, City
Environment, ph 941 8160 - Dave Hinman, Principal Adviser, Strategy and
Planning, ph 941 8804
67The End