Injector Physics C'LimborgDeprey - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

Injector Physics C'LimborgDeprey

Description:

Gun Solenoid moved as close as possible to cathode. Bucking Coil added (PRD written) ... CR material: 1mm thick, quartz, to be replaced with aerogel later ... – PowerPoint PPT presentation

Number of Views:47
Avg rating:3.0/5.0
Slides: 26
Provided by: hel85
Category:

less

Transcript and Presenter's Notes

Title: Injector Physics C'LimborgDeprey


1
Injector PhysicsC.Limborg-Deprey
  • GTL final design
  • Wakefield budget
  • Final Modifications
  • Commissioning Readiness
  • Schedule
  • Feedback systems
  • An example of tuning procedure
  • Steering in L0a

2
Injector
?Gun installation Nov. 2006 ? Gun Region
July 2006 ? Accel Region June
2006 ? Heater Region June 2006 ? Wall
Region October 2005 ? Waveguide
October 2005 ? Injection Region Aug-Nov
2006 ? Spect Region Aug-Nov 2006
  • Injector Commissioning Start December 2006

3
Gun to Linac Region
4
GTL Design
  • Normal incidence
  • Mirror size (14mm x 10 mm)
  • No second Valve in GTL
  • All wakefield computed
  • (see next slides)
  • Diagnostics units finalized
  • accommodate 20 mm screens
  • wakefield mitigation
  • Gun Solenoid moved as close as possible to
    cathode
  • Bucking Coil added (PRD written)
  • cancels the 55 Gauss Bz field on cathode
  • Compatibility with gun bake cathode removal

5
GTL Design
  • Pending issues
  • lt1.05 permeability of VV01
  • Impact on Bsolenoid falling edge to be measured
  • Choice of material for injector mirror
  • Optical path for CRG1 light
  • Finalization of GTL BPMs to meet 20 ?m resolution
  • Alignment laser specifications
  • Final GTL design review next week

Courtesy J.Langton
6
Wakefield Budget
  • ??projected lt1.2 mm-mrad
  • with no error simulations show 1.0 mm-mrad
  • Stability of electro- magnetic components to meet
    less than 10 increase
  • lt10 increased from total wakefield effects over
    the whole beamline
  • GTL area is critical region

Injection mirror with 1mm beam offset
7
Wakefield from Injection Mirror
MAFIA Simulations, Courtesy Cho-Kuen Ng
L
(2)
(3)
(1)
d
8
Wakefield Mitigation in GTL
  • Pumping slots
  • 0.24 V/pC/m per unit
  • 3 units at 0.6 m
  • 3 units at 1.2 m
  • Negligible emittance growth
  • Combined Diagnostics chambers
  • Wakefield Mitigated
  • small gaps

Pumping slot
Courtesy J.Langton
Courtesy Cho-Kuen Ng
9
Wakefield Mitigation in GTL
Bellows
  • Bellows
  • Sleeve on each 7
  • Small step transition
  • instead of 25V/pC/m

Sleeve
  • Spectrometer bend chamber
  • Wakefield mitigation movable plug
  • Eliminates any wakefield
  • Small gap

Straight beam
  • Gaps
  • 1mm gap 3V/pC/m

Beam to Spectrometer
Plug out
Courtesy J.Langton
10
Wakefield in Radiation Stopper
  • Radiation Stopper not an issue
  • LCLS-TN-05-15
  • "Wakefield Calculations for Radiation Stopper
    1  (RST1)
  • Wrms lt 0.077V/pC on axis
  • ??/? lt 0.1
  • due to small ?? 1.5 m

MAFIA computations Courtesy Cho-Kuen Ng
11
Final changes in Accelerator Region
Courtesy P.Stephens
12
Beamline Modifications
  • L0a moved downstream by 8 cm
  • Ok with emittance compensation
  • Solenoid 2 reduced to 20 cm effective length
    magnet (Req. sent out)
  • higher Bfield for same focal length
  • higher Bfield is not an issue
  • Suppressed one out of 2 BPMs in L0a-L0b drift
  • 4 inch Phase monitor fits in
  • Valve moved from L0a entrance to L0a-L0b drift
  • Mu-shield metal wrapped around all possible
    location
  • PRD 1.1-009
  • Unfortunately not possible in GTL

13
Diagnostics
  • Critical decisions
  • Specifications for screens and resolution
    finalized (PRD out)
  • CR material 1mm thick, quartz, to be replaced
    with aerogel later
  • OTR cameras orientation to increase depth of
    field
  • Streak camera ordered
  • Choice of CCD cameras finalized
  • Remaining issues
  • Optical path for CRG1 light
  • 2nd pick-up on toroid for BCS
  • Alignment laser spec. to be finalized
  • Finalization (Resolution) of BPM design for large
    aperture pipe

14
Commissioning Schedule
  • Discussed every 5th week with LCLS
    physicists/operators group
  • To be incorporated into large .mpp document for
    links
  • Discussed weekly inside Injector group
  • (Bong, Dowell, Limborg, Loos, Schmerge )
  • Based on 2 shifts per day
  • Resource loading to be refined
  • 2 physicists per shift 1 control person 1
    operator
  • guests
  • Meeting will evolve in high level application
    discussion
  • Schedule Outline
  • Starts with RF Gun cold and hot test (summer 06)
  • First beam at 135MeV dump (Nov.22-06 ?? Dec.06)
  • 8 months of characterization and optimization
  • Deliver most stable beam for acceptable charge
    for BC1 commissioning at end of June07

15
Schedule
December 06 ?
16
Commissioning Readiness
  • Pending issues
  • Hot test schedule
  • Finalize start date, detailed schedule
  • Feedback Systems
  • Calibrations procedure
  • Magnetic calibration procedure drafted
  • Screen calibration procedure
  • High Level Applications

17
High Level Applications
  • Cathode characterization (QE, uniformity, Thermal
    emittance)
  • Steering in L0a
  • Longitudinal phase space measurements at BXG
  • Bunch length measurement with transverse RF
    deflector(s)
  • Emittance meas. (multi-wire, multi-OTR,
    quad-scan, slice)
  • Power-steering through beamlines, with corrector
    weights
  • Difference orbit fitting, including internal kick
  • Longitudinal phase space measurement at BXS
  • Tomography (Longitudinal and Transverse)

18
Feedback Systems
  • Pointing Stability (see Laser)
  • Tolerance
  • Slow (flt1Hz) lt200 ??m (or slice emittance
    degraded)
  • Fast (1Hzltflt120 Hz) lt10 ??m (1 of 10
    ?x,undulator budget)
  • Slow feedback Sensor/ actuator
  • Virtual cathode / mirrors
  • Status preliminary tests at bldg 407
  • Fast stability
  • Design constraint (Gun injection mirror
    vacuum chamber rigidly linked to optical launch
    table ,i.e. less than 10??m fast motion )
  • Charge Stability (see Laser)
  • Tolerance
  • Fast (shot-to shot) lt 2rms
  • Sensor/Actuator
  • first toroid IM01/ polarizer

19
Feedback Systems
  • Timing Stability
  • Tolerance
  • Fast stability (120Hz),
  • laser phase w.r.t master clock lt 0.5 ps rms
  • feedback system
  • sensor phase monitor signal
  • actuator locking electronics from Thales system
  • Slow stability (lt1Hz),
  • laser phase w.r.t gun phase lt /-3 ps
  • to maintain emittance within 5 of optimal

20
Steering in L0a
  • Solenoid mispositioning
  • 250 ??m, 250 ?rad
  • Earth Magnetic field 2mrad/m vert.
  • No space for mu-metal shielding in GTL
  • By 0.35 G
  • Bx 0.12 G
  • Offset as large as 3mm without steering

Solenoid
SC0
SC1
SC2
BPM2
BPM3
BPM5
Gun
L0a
21
Simulations of steering
  • Procedure
  • L0a solenoid off
  • Orthogonal knobs at SC0
  • SC0 and SC1 adjusted to steer in L0a
  • Scaling of SC0 orthogonal knobs with solenoid to
    be implemented in software when

Solenoid
SC0
SC1
SC2
BPM2
BPM3
BPM5
Gun
L0a
22
Conclusions
  • GTL Design finalized
  • L0a-L0b space issue solved
  • Laser Heater region to be detailed
  • Commissioning schedule under completion
  • Feedback systems under completion
  • High Level Applications to be written

23
Response to the April FAC Recommendations
  • Wakefield in Gun
  • Large Energy spread in gun identified to be
    related to 0-mode
  • ACD group will perform more simulations
  • 3D-ellipsoidal laser pulses
  • Presented at major conferences, in particular at
    FEL05 with good interest shown from many laser
    experts

24
BACK-UP
25
Hot test schedule
  • Objectives
  • Task1 RF Conditioning
  • Task2 Verification of thermal design (?f vs
    Power, ?f vs T)
  • Task3 Close LLRF feedback loop
  • LLRF feedback loop can only be closed if
    availability of
  • Chiller, Instrumentation of detection of phase
    from reflected power signal, Drive Amplifier
  • Four scenarios discussed

() Special PPS run klystron e beam to
spectrometer during linac downtime
Write a Comment
User Comments (0)
About PowerShow.com