Title: Monday Lot B was paved Saturday and striped Sunday
1Monday Lot B was paved Saturday and striped
Sunday
2Monday Concrete drive to the loading dock, done
last week
3Tuesday Installation of handrails
4Tuesday Sprinkler work in the Art room in E-wing
5Tuesday 6 coats of wax made the cafeteria floor
look great!
6Tuesday Outdoor Dining
7Tuesday Steps from senior lot to front entrance
8Tuesday Mechanical work in guidance
9Wednesday rough grading of lot A
10Wednesday rough grading of lot A also
handrails installed
11Wednesday Electricians work in outdoor dining
by café doors
12Wednesday acoustic panels are installed on the
cafeteria walls
13Wednesday fresh sidewalk from outdoor dining to
lot C
14Wednesday new biology room E-wing
15Thursday Floor tile installation picks back up
in the existing biology rooms
16Thursday ActivBoard installation in one of the
new biology rooms
17Thursday Auditorium mosaic tile work
18Friday Setting light poles in lot B
19Friday - Auditorium
20Friday - xxx
21Friday - Auditorium
22Friday - Auditorium
23Friday Auditorium lobby
24Friday Auditorium lobby
25Friday Cafeteria courtyard
26Friday Outdoor dining Electricians working by
the doors
27Friday Outdoor dining
28Friday - xxx
29Friday Topsoil spreading in the islands
30Friday Outdoor Dining Loading Dock (now with
dock bumpers)
31Friday Last night floor tile was installed down
the ramp into E-wing
32Friday Last night floor tile was installed down
the hall by Special Ed.
33Friday E-wing
34Friday Staff restroom in E-wing
35Friday Business or marketing room
36Friday new Biology room in E-wing
37Friday new Biology room in E-wing
38Friday a different new Biology room in E-wing
39Friday - Corridor