Title: Thurmond Project Briefing


1
US Army Corps of Engineers Savannah District
2
Request for Information (RFI) System
Presented by Mr. William Plunkett, Assistant
Chief, Engineering Division Savannah
District March 29, 1999
3
RFI System
  • The Request for Information (RFI) system is a
    web-based application which allows A-E firms,
    bidders and construction contractors to directly
    input their questions to a collaborative
    database.

4
RFI DATABASE
Collaborative Database
Bidders RFIs During Solicitation Process
Architect - Engineer RFIs During The Design
Process
  • Contractor
  • RFIs During the
  • Construction Process
  • Shop Drawing Submittals
  • warranty corrections

5
RFI System Description
  • Utilizes existing software
  • Access through internet web browser
  • Creates all request for information and responses
    in written form
  • Provides for a common data base which is
    accessible to all authorized parties

6
RFI System Description
  • Time/date stamps all activities
  • E-mail notification of all activities
  • Provides centralized archive of all RFIs on the
    project
  • Allows direct link to lessons learned system
  • Allows contractual oversight by CT/CD/EN/PM

7
RFI System Status
  • The construction contractor version of the RFI
    system has successfully completed its field test
    and is in the process of deployment
  • The A-E version has been completed and will enter
    a short field test prior to deployment
  • The Bidder, Shop Drawing and warranty versions
    are in the development stage

8
Construction RFI Process
Area/Resident
Collaborative
Project
Contractor
Office
Database
Engineering
Decides if technical
Enters RFI into the
assistance is needed
database and
from Project
notifies the Area/
Engineering
Resident Office
Action
Monitors, Schedules,
Evaluates and
and
Assigns to
Implements RFI
Appropriate Designer
Initiates Request for
Provides Necessary
Information
Technical Response
Lotus Notes
Application
Answer to RFI
Resolution
Request and
Directs Contractor
response available
to perform work
to all for review
9
Construction RFI Process
  • Contractor enters RFI
  • Construction Division (field) issues RFI
    requirement
  • EN issues RFI task to engineer of record
  • Engineer of record issues RFI technical response
  • EN issues final RFI response
  • Construction Division issues final RFI response
    to contractor

10
A-E RFI Process
11
A-E RFI Process
  • A-E enters RFI
  • Engineering Division (EN) Project Engineer issues
    RFI requirement and assigns RFI task to EN staff
    or to Project Management Division
  • Assignee reviews RFI and responds to EN Project
    Engineer
  • EN Project Engineer consolidates responses from
    assignees, formalizes a response and issues RFI
    reply

12
Bidder RFI Process
  • Bidder enters RFI
  • Contracting Division Contract Specialist issues
    RFI requirement and assigns RFI task to
    Engineering Division or to Project Management
    Division
  • Assignee reviews RFI and responds to Contract
    Specialist
  • Contract Specialist consolidates responses from
    assignees, formalizes a response and issues RFI
    reply

13
Warranty Process
  • Installation enters warranty request
  • Construction Division (field) issues warranty
    requirement to contractor
  • Contractor corrects warranty items and issues
    response
  • Construction Division (field) closes warranty
    requirement and issues conformation that
    corrective action has been taken

14