1Why BSF? Why now? What does it mean for you?
2Why BSF? Building Schools for the Future multi
million pound national project to improve school
environments for the next generations. Why now?
Our school was lucky we are in Phase I of many
phases and we are one of the very first schools
to have a complete rebuild. Other schools are not
so lucky!
3- What does it mean for you?
- BSF will bring to Allerton High
- Fitness Studio
- Activity Studio
- Brand new Sports Hall
- New Hall with bleacher seating
- 2 Drama Studios
- Multi-faith Hall, classrooms support areas
4- What does it mean for you?
- BSF will bring to Allerton High
- Outdoor classrooms
- Lockers in public street area
- Glass walls and door panels
- Dining Hall and eating space
- Wireless enabled throughout
- Break-out areas
5What does it mean for you? BSF means you can get
involved in shaping the way the new school will
look, run, feel Design Festival needs 100
students Student Council needs to advise
us Student/parent/carer consultations. Paint,
furniture, break-times, lunch-times, room
layouts, etc., etc., etc.!
6ALLERTON HIGH SCHOOL PHASE 1 FEB 2007 APR
2007 ENABLING EARLY WORKS
7ALLERTON HIGH SCHOOL PHASE 2 APR 2007 JUL
2008 CONSTRUCTION
SCHOOL DELIVERY ACCESS
PUPIL ACCESS 3
TEMPORARY SPORTS CHANGING ROOM TOILET
TOWER CRANE 55m RADIUS
SCHOOL STAFF CAR PARK
FENCED CONSTRUCTION SITE
SITE OFFICES, STORES, WELFARE FACILITIES CAR
PARK
PUPIL ACCESS 1 2
STONE PATH TO PERIMETER FOR CLEAN ACCESS
CONSTRUCTION ACCESS
8ALLERTON HIGH SCHOOL PHASE 3 JUL 2008 AUG
2008 DECANTING SCHOOL OPENING
CHANGING ROOM TOILET REMOVED
CHANGE FENCE LINE
MOVE PLANNED FOR SUMMER HOLIDAY PERIOD
REMOVE SITE OFFICES, STORES, WELFARE FACILITIES
CAR PARK
SCHOOL ACCESS
LANDSCAPE NEW SCHOOL CAR PARK
9ALLERTON HIGH SCHOOL PHASE 4 SEP 2008 JUN
2009 DEMOLITION LANDSCAPING
POTENTIAL ARCHAEOLOGICAL INVESTIGATION FENCE
LOCALLY
DEMOLITION FENCE LINE
DEMOLISH OLD SCHOOL. COMPLETE PITCH LANDSCAPING
PUPIL ACCESS 3
SITE OFFICES, STORES, WELFARE FACILITIES, CAR
PARK FOR COMPLETION PHASE
ACCESS TO DEMOLISH LANDSCAPE
PUPIL ACCESS 1 2
NOTE ALL TEMPORAY FACILITIES REMOVED AT THE END
OF THIS STAGE
10Timeline
Timeline
Preferred Bidder Oct 06
Financial Close Feb 07
Open NewSchool
2006
2007
2008
2009
Spring
Summer
Autumn
Summer Hols
Summer
Spring
Autumn
Summer Hols
Summer
Spring
Autumn
Jun- Sep
ICT
Enabling Early Work
Service Commencement
Build
Decant
Planning Approval
Demolition/ Landscaping
Design
11September 2008.. Youll be here!!