Title: TAKING ON TOO MUCH WATER
1TAKING ON TOO MUCH WATER
American Bar Association Forum on the
Construction Industry
2007 Fall Meeting
- Making Sure Control and Management of Costs
Provide the Survival Kit - of Sound Evidence When Needed
John E. Bulman, Esq. Little Medeiros Kinder
Bulman Whitney Providence, RI
Patrick A. McGeehin, CPA Rubino McGeehin
Bethesda, MD
2- We all have the strength to bear the misfortunes
of others. - Francois de la Rochefoucauld, 1613-1680
3FUNDAMENTAL TENET
- Non-breaching party entitled to be put in
position it would have been absent the breach.
4FUNDAMENTAL CAVEAT NUMBER 1
- Non-breaching party only entitled to damages
reasonably in the contemplation of the parties at
the time of contracting.
FUNDAMENTAL CAVEAT NUMBER 2
Any award of damages must be reduced by the
savings obtained by the contractor as a result of
the breach (i.e., any cost or loss that he has
avoided by not having to perform).
FUNDAMENTAL CAVEAT NUMBER 3
Contractor must establish damages to a
reasonable certainty.
5SLAM DUNK ON ENTITLEMENT ? GOOD RESULT IN
ARBITRATION
6HOW DOES THE DAMAGES SHIP VEER OFF COURSE?
7IT MIGHT COST TOO MUCH TO MAKE THE SHIP AS GOOD
AS YOU PLANNED.
- Dangerously assuming that repair and replacement
costs will be awarded instead of diminution in
value economic waste doctrine.
8CAUSATION AND DAMAGES MIGHT BE LIKE TWO SHIPS
PASSING IN THE NIGHT.
- Failing to prove that the damages incurred bear
sufficient relationship to the breaches claimed.
9IN A MULTIPLE SHIP COLLISION, WHICH SHIP CAUSED
WHAT DAMAGES?
- Failure to properly allocate damages where there
are several potential contributing parties.
10BERMUDA TRIANGLE DAMAGES SPECULATIVE OR REAL?
- Pushing the envelope into speculation.
11- PROJECT COST AND FIELD RECORDS GENERAL
CONSIDERATIONS - Cost to maintain records
- Company policy issues
- Establishing detailed cost and productivity
tracking at the outset of the project - Growing from smaller to larger projects
- Availability of technology to support tracking
12- DELAY AND IMPACT ISSUES
- Problem arises keep good records
- Extra work vs. impact and inefficiency and
acceleration costs - Job-specific vs. industry wide data
- Technology leading to need for higher level of
tracking and proof
13- DAMAGES THEORIES METHODOLOGIES
- Total Cost Approach
- Jury Verdict Approach
- Modified Total Cost Approach
- Use of Inefficiency Percentages from
Published Sources - Expert estimates of inefficiency
- Measured Mile
14- Measured Mile Approach
- Most preferred method
- Productivity during abnormally disrupted period
minus productivity during normal period of work - Deduct losses resulting from disruptions which
are not compensable (e.g. weather or contractor
performance issues)
15- Measured Mile Approach
- (continued)
- Difficulty in finding period of un-impacted
performance - Comparability of the work
16- Considerations for Tracking Cost and Productivity
Data - Physical location of the work
- Type of work and sub-categories
- Timing of the performance of work
17- Considerations for Tracking Cost and Productivity
Data (continued) - Perceived differential in the impact on varied
sub-categories of work - Degree of difficulty comparison
- Materiality of the work in each area
- Cost to accumulate the costs and productivity in
question
18Types of Records and Other Issues
- Timesheets
- Equipment logs
- Diaries
- Productivity data (equivalent units per shift)
19Types of Records and Other Issues (continued)
- Project personnel instructions
- Uniqueness of each project situation
- Actual examples of successful/unsuccessful
attempts - to prove inefficiencies
20Boston Big Dig Construction Project
- Impact claims for concrete operations
- No un-impacted period
- Measured Mile calculation
- Analysis based on time only -- no sub- elements
tracked (e.g. forming, placing, - finish, etc. (no tracking by pour)
- Point and patch issues quality and timing
21Boston Big Dig Construction Project
22Boston Big Dig Construction Project
23Overseas Embassy Construction Project
- - Inefficiency claim
- - Inappropriate approach
- - Rejected by BCA Judge
-
24Overseas Embassy Construction Project
25Remediation of Landfill
- - Termination of subcontractor
- - Second set of books craft labor
database - - Self performed vs. brokered job
- - Use of consultant to do re-coding
- - Costly and inefficient approach
26Highway Bridge Construction
- Subcontractor fabrication and
inefficiencies - - No cost segregation by Pier and Bridge
27Highway Bridge Construction
28Boston Big Dig Construction Project
- - Impact claims for concrete
- operations
- - Degree of difficulty comparison
- - Costs/productivity by structure
29Boston Big Dig Construction Project
30Boston Big Dig Construction Project
31Boston Big Dig Construction Project
32Boston Big Dig Construction Project
33SOME BASIC POINTERS FOR LIFE ON THE HIGH SEAS
- Help your clients develop systems that collect
damages evidence in a coherent fashion. - Try to use the best accepted damages theory.
- Always remember causation.
- Give the fact finder the necessary tools to
perform allocation and diminution of value
assessments. - Common sense should prevail.