Title: CHP Interconnection Standardization and Precertification
1CHP Interconnection Standardization and
Precertification
- Francis Cummings
- Policy Director,
- Massachusetts Renewable Energy Trust,
- Massachusetts Technology Collaborative
- April 6th, 2005
Annual Spring Meeting, Northeast Combined Heat
and Power Initiative Realizing the Benefits of
a Regional CHP Market Empire State Plaza,
Albany NY
23 Topics
- Interconnection
- collecting data
- network challenges
- Role of DG in Distribution Planning
- Next Steps in MA
- Please visit the DG Collaboratives website
- http//www.masstech.org/renewableenergy/public_pol
icy/dg/meeting_index.htm - These slides are not complete without the
accompanying oral remarks, which do not
necessarily represent the views of MTC.
3Interconnection Screens
4Interconnection Screens
5Interconnection collecting data
- Time cost of process across 4 utilities
- Tracking data for DG approvals since 4/04
- Consistent format analysis
- Performance of spot network case study
- Spot interconnections nationwide
6DG Application Censusfor the period Q2 2004 - Q4
2004 (Draft)
7Data across 4 MA utilities (DRAFT)
8Interconnection network challenges
- Seeking network solutions (technical, liability)
- Spot grid/area networks
- Substantial year-long technical analysis debate
- MA utilities reluctant to connect additional case
studies - Area/grid (downtown) networks
- Interest in solar PV connections to Boston
network - Few precedents (e.g., ConEd)
- National coordination of state initiatives
- MA DG Collaborative to send consultant to
national venues - Multi-state exchange of data on existing new
case studies
9 - Performance of spot network case study
- GSA building on NSTAR network
- Williams Building, Boston
- Data monitoring analysis ongoing by Bill Feero
- CHP PV
10Interconnection collecting data
- Spot interconnections nationwide
- Nationwide list of network interconnections
- http//www.masstech.org/renewableenergy/public_pol
icy/dg/resources/network.htm
11List of network interconnections - 1
12List of network interconnections - 2
13Next Steps in MA
- Work Plan for next year July 2005 - May 2006
- streamlined process
- research
- national coordination
- final recommendations
- MTC funding for TD congestion relief pilots
- Other ongoing activities
- Unresolved treatment of rate issues in generic
case (DTE 02-38)
14Draft report for review comment
- Please visit our website for our draft report,
which will be submitted to the DTE in May 05 - http//www.masstech.org/
- renewableenergy/public_policy/dg/meetings/
- 2005_annualreportreview.htm
- Comments are welcome -- especially from
Collaborative participants interested in signing
on to the Report.