Lean Production Management - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

Lean Production Management

Description:

Operations in Indianapolis, Seattle and Portland, Oregon. Brief Timeline of Industrial Efficiency ... Group review of the current plan, usually weekly ... – PowerPoint PPT presentation

Number of Views:108
Avg rating:3.0/5.0
Slides: 20
Provided by: daveko9
Category:

less

Transcript and Presenter's Notes

Title: Lean Production Management


1
Lean Production Management
  • Improving Construction Reliability and Efficiency

2
BMW Constructors, Inc
  • Industrial construction refining, chemical,
    power, pharmaceutical, biotech, high-purity
    industries
  • Local office for greater Chicago area in Munster
  • Operations in Indianapolis, Seattle and Portland,
    Oregon

3
Brief Timeline of Industrial Efficiency
  • Henry Fords assembly line
  • Toyota manufacturing method
  • Improvements migrate to US auto industry
  • Lean Manufacturing
  • Lean Construction

4
Implementing Lean
  • Lean is not a software initiative
  • Results are accomplished through behavior
    modification
  • Cultural change requires constant, unflagging
    commitment
  • Project manager and key staff are primarily
    drivers of the Lean work processes

5
Group Planning is the Core of Lean
  • Plan work sequences as one democratic
    collaborative group including crew foremen
  • Plan what is best for the project as a whole, not
    what may be best for a single discipline
  • Identify the ideal construction activity sequences

6
(No Transcript)
7
Identify and Solve Constraints
  • After full development of the ideal sequence
    plan, work in constraints that can not be
    mitigated materials, equipment, etc.
  • Assign every constraint that inhibits the ideal
    sequences to a team member for solution
  • Management and staff facilitate planning and
    resolve constraints

8
Lean Planning
Lean Planning
9
The Plan is Never Finished
  • As conditions change, replan the affected
    activities
  • Group review of the current plan, usually weekly
  • Pull additional knowledge and new participants
    into the planning group

10
Develop Standard Processes
  • Created for work objects foundations, steel
    members, pipe spools, cables, conduit, equipment,
    specialty items, tie Points, instruments
  • Work flow streams mapped to drive out waste
    perform only activities that add value
  • (22) LB CS Spool w/ PWHT

11
Crew Daily Commitments
  • Each foreman makes detailed work commitments for
    the next day
  • Accomplished commitments are tracked
  • Reasons for unmet commitments are tracked
  • Staff and management facilitate solutions to
    eliminate the reasons for missed commitments
  • All in a positive, supportive effort to get
    better!

12
(No Transcript)
13
(No Transcript)
14
Refinery Process Unit Results
  • Installed pipe _at_ at 1.99 man hour per foot, vs.
    2.39 for nearly identical 2003 unit
  • Installed steel _at_ 15.8 man hours per ton vs. 23.9
    for 2003 unit
  • Scaffold use 11.5 of direct field craft hours
    experience is usually 15
  • Small amount of craft overtime - 7

15
Multiple Refinery Units Results
  • Project completed in company record time very
    tight completion target
  • 9.5 productivity improvement as measured by
    owners cost engineers
  • Owner reports construction labor cost reduction
    of 10 million

16
Architectural Rebuild Results
  • After seeing Lean in operation, the contract
    construction management company embraced and
    supported Lean
  • Completed project using 15 less construction
    labor man hours in a very competitive lump sum
    environment
  • The guys in the field ran the job management
    was easy

17
Feedback from our Owners
  • Lean with self-managed contractors enables
    quicker responses to issues
  • Creates strong sense of contractor and craft
    ownership
  • Develops one unified project team of owner,
    engineer, contractor and laborer
  • Work always kept in front of crafts high
    productivity and high craft morale

18
Owners View of Implementation
  • Contractor management must be enthusiastically
    supportive of Lean
  • Takes up a lot of supervisors time up front,
    until they realize the benefits of planned work
  • Big learning curve

19
Lean Changes Strategy and Roles
  • Managers must let go and let their field
    supervisors develop plans
  • Managers are facilitators, not directors
  • Managers and superintendents must be PATIENT
  • Go slow to go fast!
Write a Comment
User Comments (0)
About PowerShow.com