Title: Generation Interconnection Services


1
  • Generation Interconnection Services

2
Todays Topics
  • GIS Role in CSI
  • Application and Agreement
  • Project Review
  • Inspection
  • Overall Timeline
  • Resources

1
3
GIS Role
  • One point of contact for customer (or authorized
    agent) with regard to interconnecting systems
  • Coordinate various activities, including
    engineering, metering, and contract
    administration
  • Responsible to ensure system is installed as
    design indicates and operating according to Rule
    21
  • Two types of solar interconnections NEM and
    non-NEM options

4
Interconnection Application and Agreement
  • A separate application and process from CSI
    (recently updated)
  • Process runs parallel with CSI/SGIP
  • Application must be complete and include required
    documents for review
  • Execute Inspection and Interconnection Agreement
    before a system is permitted to operate

5
Project Review
6
Inspection
  • Check system to ensure built as designed (matches
    SLD)
  • Install bi-directional meter (NEM)
  • Verify installation of AC disconnect and
    appropriate signage (if required)
  • Install Net Gen Output Meter, if needed

7
Process Improvement
  • Change in AC disconnect requirement policy
    November 2006
  • NEM-MT has been approved to simplify projects
    with solar combined with other generation
    technologies
  • Underway simplification of application, to be
    combined with the Agreement for NEM

8
Overall Timeline
  • NEM projects- generally less than 30 business
    days
  • Non-NEM- within 60 days, if all required
    docs/signatures and construction is on schedule

9
(No Transcript)
10
(No Transcript)
11
(No Transcript)
12
Resources
  • Standard NEM http//www.pge.com/suppliers_purchas
    ing/new_generator/solar_wind_generators/standard_e
    _net/
  • Expanded NEM http//www.pge.com/suppliers_purchas
    ing/new_generator/solar_wind_generators/expanded_e
    _net/
  • Non-NEM projects http//www.pge.com/suppliers_pur
    chasing/new_generator/retail_generators/
  • Contact gen_at_pge.com, or 415-972-5676