Title: SCIPC


1
SCIPC WG5 (L0)
Breese Quinn, Ela Barberis, Bill Cooper, Eric
Kajfasz, Elizaveta Shabalina, Taka Yasuda,
Eckhard von Toerne
Agenda Monday 17 May 2004
  • 1530 Introduction (05')    Breese Q. 
  • 1535 L0 Design Review (20')    Andrei
    N.
  • 1555 Pre-Inst. Plans (Fall shutdown) (20')   
    Bill C. Lyn B.
  • 1615 L0 Geometry MC (15')    Lisa S. 
  • 1630 Review Inst. Comm. Schedule (30') All 
  • 1700 Run IIa What went right/wrong? (30')All

2
L0 Design Run IIa status
  • We expect Layer 1 Micron sensors to begin to fail
    at exposures of 3-4 fb-1
  • We are seeing continuing failures of readouts in
    the current detector (84 currently enabled)

3
L0 Design Physical
  • Detector must fit between radii of 16mm beam
    pipe flange and 22.8mm SMT support structure
    openings
  • 6 phi segments, 8 z segments
  • 48 HDIs x 256 channels
  • Phi acceptance 98.4

4
L0 Design Expected Enhancement
  • Layer0 will recover b-tagging

    efficiency to original values

    before irradiation
  • If no loss model is assumed
    Layer0
    improves b-tagging
    per
    jet by 15
  • Improvement in vertex

    resolution allows

    considerable increase of

    Bs mixing reach

5
L0 Design Pitch Adapter Concern
  • Change wrt Run2B design pitch adapter
  • 1st prototype failed, vendor is trying again (due
    in a few weeks)
  • 2nd vendor is being brought in to give it a try

6
L0 Design Noise Control
  • CDF L00 had negative experience using analog
    cables large noise
  • Concluded that source of noise are poorly
    grounded conductors near sensors and analog
    cables
  • Weve done a lot of RD trying to avoid same
    mistakes
  • Found that low inductance ground connections are
    very important to equalize potential between
    different parts
  • Found a solution when Carbon Fiber support
    structure is forced to be at ground potential
    providing low inductance path

7
L0 Design Noise Control
8
L0 Design Noise Control
  • L0 module
  • L0 modules on
    grounded support
    structure

9
Fall Shutdown Plans Mechanical
  • H disk removal/repair
  • Only two H disks will remain once L0 is installed
  • All four H disks have many unusable wedges
  • H wedges will be redistributed to make two good
    H disks
  • Should the rebuilding of the H disks be done
    during this years fall shutdown or during next
    years upgrade?
  • Pro try to get as much done work ahead of time
    as possible
  • Con difficult job dont remove the H disks
    twice if you dont have to
  • Considerations
  • Beam pipe risk would have to be disconnected,
    not cut
  • Do the H disks have to be removed for clearance
    measurements anyway?
  • Likely see next slide
  • Is there enough time/manpower to get it done in
    13 weeks?
  • Lisa will ask Moscow for schedule estimate
  • What are the physics risks of failure?
  • Eckhard is pursuing this
  • General consensus is we want it done now if at
    all possible

10
Fall Shutdown Plans Mechanical
  • Measuring beam pipe region clearances
  • There is some uncertainty about the reliability
    of the clearance numbers in hand
  • One extreme or the other
  • Open heart surgery remove the beam pipe and
    probably H disks for direct measurement access
  • This does require that the beam pipe be cut
  • MRI may be possible to map the membrane
    openings with tracks
  • This needs to be determined soon by whom?
  • There is risk involved with beam pipe work, but I
    believe it comes down to two things
  • If the mapping doesnt work, this will be the
    last time to check the aperture. If we dont and
    find out next year that its too small, the game
    is over.
  • There are very careful and capable people to do
    the work.

11
Fall Shutdown Plans Electrical
  • Install 1-4 L0 modules
  • Hardware installation (Bagby, Foglesong)
  • Sensor modules in gaps on the horseshoe
  • Power supplies in the cathedral
  • SEQC firmware installed
  • Software
  • Download GUI needs to handle SVX4 chips (Bucholz)
  • Install more HV for L0
  • Hardware (Prague?)
  • Have new HV pods and fanout boxes for L0 bias
    voltages
  • Need more cabling
  • Software
  • Lots more mapping (Quinn)
  • Modify GUIs
  • Almost all of this work is in MCH2 it can start
    immediately

12
L0 Geometry in Simulation
  • Implement new SMT geometry in D0gstar (D0 Geant)
  • Modify SMT hit storage interface (simpp)
  • Modify SMT hit digitization package (d0sim)
  • Modify SMT hit packing (into raw data chunk)
    (smtraw, smtutil, pack_reco)
  • Modify SMT cluster reconstruction packages
  • Modify reconstructiongeometry and track
    reconstruction

13
L0 Software Overview
  • Huge number of tasks ZERO names!

?
?
controls
?
?
?
?
?
?
?
?
?
?
?
?
?
14
L0 Software Physics Commissioning
  • Huge number of tasks ZERO names!
  • Need a non-trivial number of workers
  • Lisa Ela are putting together a task
    list/manpower estimate
  • Will require push from management ala calorimeter
    group expansion
  • Need a L0 Physics Commissioning leader (Quinn
    find, not be!)
  • Responsible for encouraging tool development, but
    even more so for implementing a plan for studies
    using those tools to get physics quality data
  • Within the SMT/L0 group, parallel to Installation
    leaders (Bill, Lyn)
  • Integrated to the Algorithms/Tracking groups

15
SCIPC WG5 (L0) Summary
  • Two major areas of concern
  • Planning for Fall 2004 shutdown activities
  • Get as much done as is reasonably possible
  • Clearance measurements
  • H disk removal/repair
  • Cooling system studies
  • Photography
  • Many decisions to be made in the next couple of
    weeks
  • L0 Physics Commissioning
  • Run IIa did not provide a good model here
  • Enormous number of software tasks and no one is
    working on them
  • Need a person responsible for physics
    commissioning studies program within the group
  • Other
  • Review of existing Installation schedule taking
    place asynchronously offline. Will address it
    before Fresno
  • Revise Installation status
  • Include Commissioning schedule
  • SMT/L0 Integration needs to happen on a short
    timescale