Dealing with Free Markets and Demand Response - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Dealing with Free Markets and Demand Response

Description:

Adopted a phase-in approach to customer choice (from large to small) beginning ... statewide stakeholder workshop process which kicked off on April 29th, and ... – PowerPoint PPT presentation

Number of Views:36
Avg rating:3.0/5.0
Slides: 19
Provided by: william598
Category:

less

Transcript and Presenter's Notes

Title: Dealing with Free Markets and Demand Response


1
Dealing with Free Markets and Demand Response
  • PLMA Fall Conference
  • September 29, 2004
  • William P. McNeil
  • Director Regulatory Strategy

2
Background on Illinois Restructuring
  • General Assembly passed Electric Service
    Customer Choice and Rate Relief Law of 1997
  • Adopted a phase-in approach to customer choice
    (from large to small) beginning on 10/1/99
    through 5/1/02
  • For largest utilities, residential rates were
    reduced 20 from their 1997 levels (15 on 8/1/98
    and 5 on 5/1/02)
  • Base rates were frozen (other than for rate cuts)
    at their 1996 levels through a mandatory
    transition period, which goes through 2006
  • Utilities were allowed to collect transition
    charges (CTCs) from shopping customers through
    2006

3
The IDC Model
  • The Illinois law permitted utilities to compete
    for customers (and pre-qualified them as RESs)
    both within their service territories and
    anywhere else in the State
  • In 1998, the Commission opened a rulemaking
    proceeding to establish Codes of Conduct
    providing competitive safeguards (i.e.
    separation) between a utilitys merchant
    functions and its delivery functions
  • One of the models proposed by the ComEd was
    called the Integrated Distribution Company model,
    or IDC.
  • Under this model, if a utility agreed to strict
    limitations on its ability to market its
    generation services in any way, it would receive
    a waiver from the functional separation rules.
  • All of the Illinois utilities are currently
    operating under this approved model

4
Competitive Service Declarations
  • The Illinois Restructuring Act contains a
    provision allowing utilities to petition the ICC
    to declare a specific service Competitive
  • The utility must show that there are competitive
    suppliers of the service, and that customers can
    reasonably obtain the service from the market,
    and if fact, the utility has already lost
    significant market share of that service
  • If the Commission approves the petition, the
    utilities obligation to offer the service under a
    tariff (cost based) expires after 3 years
  • ComEd has successfully petitioned the ICC to
    declare bundled electric service for customers
    over 3 MW competitive

5
Current update on retail competition (for ComEd)
6
ComEd has built a significant DR portfolio
7
Current stakeholder process for post 2006
  • The Commission sponsored a statewide stakeholder
    workshop process which kicked off on April 29th,
    and concluded early September.
  • A variety of issues regarding the regulatory
    framework for post 2006 were examined and
    debated. Five separate workshops were conducted
    (meeting weekly or bi-weekly through the summer).
    Focus areas included
  • Power Procurement Utility Service Obligations
  • Rate Design Energy Assistance
  • Competition
  • Demand Response was identified early in the
    process (by Commission staff) as an important
    element of the post 2006 framework. This has
    been reinforced by the Lt. Governors Task Force
    and public positions of the ICC

8
Questions raised in Workshop process
  • Should incentives be put in place to encourage
    consumers to make their demands more
    price-responsive?
  • What form might such incentives take?
  • How should costs related to energy efficiency and
    demand reduction be charged in rates?
  • Should there be an interruptible rate option for
    transmission and distribution services and/or
    generation services? How should such a rate be
    designed?
  • Should existing real-time tariffs be modified to
    encourage customer interest in such tariffs? If
    so, what modifications are necessary?
  • Which types of time-based rates, ranging from TOU
    to Critical Peak Pricing to Day Ahead Real Time,
    are appropriate for which customer classes? What
    has customer acceptance of such been in Illinois
    and other states to date?
  • To what extent is existing infrastructure a
    barrier to wider deployment of time-based rates?

9
Procurement models being considered
Full Requirements Procurement
Portfolio Manager Approach
  • Utility procures full requirements in single
    process
  • Suppliers carry risk of matching load variances
    (serve a percentage of the load shape)
  • Cost of risk made part of competitive process and
    incorporated in rates
  • Risk management in the hands of those willing to
    hold it
  • A regulatory process decides what products,
    resources or fuel types are to be purchased
  • Utility procures products to best fit expected
    load according to plan
  • Actual load will be greater than or less than
    procured power in every hour
  • The volume risk is increased by the option for
    customers to switch (especially if contracts are
    long term)
  • A regulatory process determines prudence (after
    the fact)

10
General approach to defining DR strategy
  • Step 1 Interview internal stakeholders
  • Structure the interviews
  • Make sure to cast a wide net
  • Close the loop
  • Step 2 Create strategic alternative scenarios
  • Make sure that all of the beliefs are embedded
    in at least one of the scenarios
  • Using the two extremes can be a good approach
  • Step 3 Small teams fully develop the case for
    each alternative
  • Must agree on common evaluation criteria
  • Each team needs a champion
  • Step 4 Choose the best alternative and develop
    rationale
  • Take to Senior Management
  • Internalize with key managers of affected areas

11
What we asked in the interviews
  • Questions
  • How should we value demand response? What are
    the appropriate metrics (time horizon)? Is there
    a value attributable to the wires? What risks
    are there for ComEd to offer / not offer DR?
  • What is the business case? How should it be
    funded? Are there non-economic factors? What
    regulatory support is needed?
  • What should ComEds role be? Is it OK if we let
    the current portfolio expire?
  • What overlap do you see with any other
    strategies? What involvement do you want to have
    in this strategy?

12
What we learned from the interviews
  • There are very diverse views across an important
    management level of the company -- Some opinions
    were strong
  • Views ranged from if customers want it, they can
    get it from PJM to its the right and
    appropriate thing for ComEd to do
  • Economics were the major concern. Many existing
    programs do not fund themselves
  • All recognized some non-economic value and the
    external support for certain DR programs

13
Strategic Option 1 Grow the Business
  • The first option analyzed was to not only
    maintain the entire current portfolio
    (economically rationalized), but to set up a
    stand-alone group focused on growing DR as an
    attractive business within ComEd.
  • Key considerations include
  • Can a business case be made which would pass
    internal thresholds?
  • Is it consistent with ComEds business model?
  • How would it fit with the expected procurement
    model?
  • What risks would ComEd assume?
  • Impact / Affect on retail market development?

14
Strategic Option 2 Full Exit
  • The second option considered was the other
    extreme Full Exit. Under this option ComEd
    would simply eliminate all existing tariffs and
    walk away from all programs at the end of 2006.
  • Key considerations include
  • Potential loss of gt 1,000 MW of DR
  • Inconsistent with State and regulatory policy
    goals
  • Reaction of important stakeholders in the post
    2006 debate
  • Customer satisfaction / reaction
  • Loss of any benefit to the wires

15
Strategic Option 3 Transition / Partial Exit
  • This represents the middle ground. The option is
    defined as maintaining a presence in DR which is
    acceptable to customers, regulators, and policy
    makers while minimizing risks and costs to ComEd
    and allowing for transition to a markets approach
    over time.
  • Key considerations include
  • Aligning customer incentives with PJM markets
  • Integration with procurement methodology
  • Cost recovery, if programs dont self fund
  • Transition plan for phasing out legacy programs
  • How to facilitate or stimulate development of
    competitive DR markets

16
Where did we land?
17
How ComEds programs will fit within the PJM
framework
18
Final Recommendations
  • Update DR portfolio to better fit post 2006
    environment
  • Continue current transition toward DR programs
    that are economically viable within PJM
    framework.
  • Eliminate legacy programs which no longer make
    sense (Riders 26, 27, 30, 32)
  • Maintain DR programs important to key
    stakeholders (e.g. Nature First, Residential real
    time pricing).
  • Let the DR markets develop over the next 2-3
    years
  • Watch for emergence of Curtailment Service
    Providers (CSP).
  • Evaluate changes, and continue in the stakeholder
    process for in PJM DR framework.
  • Actively pursue recognition of long-term capacity
    value of DR at PJM.
  • Track evolving customer interest and
    participation in DR.
  • Reevaluate DR involvement in 2008
  • Assess new economics driven by evolving PJM
    programs, wholesale markets, and enabling
    technologies.
  • Look for right timing / opportunity to exit
    involvement in competitive retail market segments
    once alternative providers have fully developed
    capabilities
Write a Comment
User Comments (0)
About PowerShow.com