Title: Dealing with Free Markets and Demand Response
1Dealing with Free Markets and Demand Response
- PLMA Fall Conference
- September 29, 2004
- William P. McNeil
- Director Regulatory Strategy
2Background on Illinois Restructuring
- General Assembly passed Electric Service
Customer Choice and Rate Relief Law of 1997 - Adopted a phase-in approach to customer choice
(from large to small) beginning on 10/1/99
through 5/1/02 - For largest utilities, residential rates were
reduced 20 from their 1997 levels (15 on 8/1/98
and 5 on 5/1/02) - Base rates were frozen (other than for rate cuts)
at their 1996 levels through a mandatory
transition period, which goes through 2006 - Utilities were allowed to collect transition
charges (CTCs) from shopping customers through
2006
3The IDC Model
- The Illinois law permitted utilities to compete
for customers (and pre-qualified them as RESs)
both within their service territories and
anywhere else in the State - In 1998, the Commission opened a rulemaking
proceeding to establish Codes of Conduct
providing competitive safeguards (i.e.
separation) between a utilitys merchant
functions and its delivery functions - One of the models proposed by the ComEd was
called the Integrated Distribution Company model,
or IDC. - Under this model, if a utility agreed to strict
limitations on its ability to market its
generation services in any way, it would receive
a waiver from the functional separation rules. - All of the Illinois utilities are currently
operating under this approved model
4Competitive Service Declarations
- The Illinois Restructuring Act contains a
provision allowing utilities to petition the ICC
to declare a specific service Competitive - The utility must show that there are competitive
suppliers of the service, and that customers can
reasonably obtain the service from the market,
and if fact, the utility has already lost
significant market share of that service - If the Commission approves the petition, the
utilities obligation to offer the service under a
tariff (cost based) expires after 3 years - ComEd has successfully petitioned the ICC to
declare bundled electric service for customers
over 3 MW competitive
5Current update on retail competition (for ComEd)
6ComEd has built a significant DR portfolio
7Current stakeholder process for post 2006
- The Commission sponsored a statewide stakeholder
workshop process which kicked off on April 29th,
and concluded early September. - A variety of issues regarding the regulatory
framework for post 2006 were examined and
debated. Five separate workshops were conducted
(meeting weekly or bi-weekly through the summer).
Focus areas included - Power Procurement Utility Service Obligations
- Rate Design Energy Assistance
- Competition
- Demand Response was identified early in the
process (by Commission staff) as an important
element of the post 2006 framework. This has
been reinforced by the Lt. Governors Task Force
and public positions of the ICC
8Questions raised in Workshop process
- Should incentives be put in place to encourage
consumers to make their demands more
price-responsive? - What form might such incentives take?
- How should costs related to energy efficiency and
demand reduction be charged in rates? - Should there be an interruptible rate option for
transmission and distribution services and/or
generation services? How should such a rate be
designed? - Should existing real-time tariffs be modified to
encourage customer interest in such tariffs? If
so, what modifications are necessary? - Which types of time-based rates, ranging from TOU
to Critical Peak Pricing to Day Ahead Real Time,
are appropriate for which customer classes? What
has customer acceptance of such been in Illinois
and other states to date? - To what extent is existing infrastructure a
barrier to wider deployment of time-based rates?
9Procurement models being considered
Full Requirements Procurement
Portfolio Manager Approach
- Utility procures full requirements in single
process - Suppliers carry risk of matching load variances
(serve a percentage of the load shape) - Cost of risk made part of competitive process and
incorporated in rates - Risk management in the hands of those willing to
hold it
- A regulatory process decides what products,
resources or fuel types are to be purchased - Utility procures products to best fit expected
load according to plan - Actual load will be greater than or less than
procured power in every hour - The volume risk is increased by the option for
customers to switch (especially if contracts are
long term) - A regulatory process determines prudence (after
the fact)
10General approach to defining DR strategy
- Step 1 Interview internal stakeholders
- Structure the interviews
- Make sure to cast a wide net
- Close the loop
- Step 2 Create strategic alternative scenarios
- Make sure that all of the beliefs are embedded
in at least one of the scenarios - Using the two extremes can be a good approach
- Step 3 Small teams fully develop the case for
each alternative - Must agree on common evaluation criteria
- Each team needs a champion
- Step 4 Choose the best alternative and develop
rationale - Take to Senior Management
- Internalize with key managers of affected areas
11What we asked in the interviews
- Questions
- How should we value demand response? What are
the appropriate metrics (time horizon)? Is there
a value attributable to the wires? What risks
are there for ComEd to offer / not offer DR? - What is the business case? How should it be
funded? Are there non-economic factors? What
regulatory support is needed? - What should ComEds role be? Is it OK if we let
the current portfolio expire? - What overlap do you see with any other
strategies? What involvement do you want to have
in this strategy?
12What we learned from the interviews
- There are very diverse views across an important
management level of the company -- Some opinions
were strong - Views ranged from if customers want it, they can
get it from PJM to its the right and
appropriate thing for ComEd to do - Economics were the major concern. Many existing
programs do not fund themselves - All recognized some non-economic value and the
external support for certain DR programs
13Strategic Option 1 Grow the Business
- The first option analyzed was to not only
maintain the entire current portfolio
(economically rationalized), but to set up a
stand-alone group focused on growing DR as an
attractive business within ComEd. - Key considerations include
- Can a business case be made which would pass
internal thresholds? - Is it consistent with ComEds business model?
- How would it fit with the expected procurement
model? - What risks would ComEd assume?
- Impact / Affect on retail market development?
14Strategic Option 2 Full Exit
- The second option considered was the other
extreme Full Exit. Under this option ComEd
would simply eliminate all existing tariffs and
walk away from all programs at the end of 2006. - Key considerations include
- Potential loss of gt 1,000 MW of DR
- Inconsistent with State and regulatory policy
goals - Reaction of important stakeholders in the post
2006 debate - Customer satisfaction / reaction
- Loss of any benefit to the wires
15Strategic Option 3 Transition / Partial Exit
- This represents the middle ground. The option is
defined as maintaining a presence in DR which is
acceptable to customers, regulators, and policy
makers while minimizing risks and costs to ComEd
and allowing for transition to a markets approach
over time. - Key considerations include
- Aligning customer incentives with PJM markets
- Integration with procurement methodology
- Cost recovery, if programs dont self fund
- Transition plan for phasing out legacy programs
- How to facilitate or stimulate development of
competitive DR markets
16Where did we land?
17How ComEds programs will fit within the PJM
framework
18Final Recommendations
- Update DR portfolio to better fit post 2006
environment - Continue current transition toward DR programs
that are economically viable within PJM
framework. - Eliminate legacy programs which no longer make
sense (Riders 26, 27, 30, 32) - Maintain DR programs important to key
stakeholders (e.g. Nature First, Residential real
time pricing). - Let the DR markets develop over the next 2-3
years - Watch for emergence of Curtailment Service
Providers (CSP). - Evaluate changes, and continue in the stakeholder
process for in PJM DR framework. - Actively pursue recognition of long-term capacity
value of DR at PJM. - Track evolving customer interest and
participation in DR. - Reevaluate DR involvement in 2008
- Assess new economics driven by evolving PJM
programs, wholesale markets, and enabling
technologies. - Look for right timing / opportunity to exit
involvement in competitive retail market segments
once alternative providers have fully developed
capabilities