Title: Overview of WSDOT Capital Project Management
1Overview of WSDOT Capital Project Management
- Preliminary Report
- Keenan Konopaski, JLARC Analyst
- Dan Estrada and Roberta Manshel, Gannett Fleming
- December 17, 2004
2Scope of Review
- A pre-audit (overview of issues)
- Focused on management methods/structures used to
deliver capital projects - Limited to highway and ferry projects
- The beginning of the audit process, to help TPAB
consider future audit steps - Some initial management recommendations to WSDOT,
when practical and supportable
3Objectives of Review
- Describe procedures/processes
- Describe organizational structures
- Review reporting/information systems
- Review critical path management
- Review risk management
- Identify options for future TPAB audits and/or
evaluations
4Background on Capital Program
- 10 year cost of approximately 10 billion
- About 1,300 projects in 10 year plan
- Wide range in project sizes (100K to 500M)
- Multiple types of projects (highways, structures,
vessels, ferry terminals, etc.) - Several programmatic purposes (mobility, safety,
preservation, etc.) - New gas tax (Nickel fund) is designated by
Legislature on line-item basis for specific
projects
5Challenge for Methodology
- How do we get substantive insight into specific
project management techniques for this large,
diverse capital program? - Approach Select projects for detailed reviews
with diversity in mind, and highlight differences
between stronger and weaker practices - Result Identify existing strengths and gaps for
opportunities to extend practices or review more - Caveat Findings from example projects represent
diversity of practices in place
6Criteria for Selecting Projects
- Half of selected projects faced challenges
- Projects past design and into construction
- Representation from multiple regions
- Diversity in size
- Diversity in type (interchange, ferry terminal,
etc.) - Diversity in project management tools and systems
used - Diversity in design approach (consultants vs
staff)
7Projects Reviewed by Consultant
- Shaw Island Slip Reconstruction
- SR 527 Widening - 164th to 132nd St SE
- I-5 196th (SR 524) Interchange
- Southworth/Fauntleroy Slip Reconstructions
- SR 16 HOV - Olympic Dr to Union Ave
- SR 161 - 234th to 204th St E
- SR 500 - NE 112th Interchange
- I-90 Build Lanes from Argonne to Sullivan
8Projects Reviewed (contd)
9Conclusions
- WSDOT has diversity in its project delivery
practices. - WSDOT is continuing to improve its practices with
initiatives focused on project management
principles and tools. - While WSDOT encourages local innovation to help
improve project delivery, some additional
standardization of successful minimum
requirements can provide benefits.
10Conclusions (contd)
- Examples of exemplary practices are in place, but
arent universally adopted because - they are relatively new,
- implementation is slow due to the size and
decentralization of WSDOT organization, or - there are resource constraints.
11Conclusions (contd)
- WSDOT has initiated efforts to shift its capital
delivery orientation from a program-focused to a
project-focused perspective. - A lack of standardized definitions poses
challenges to project reporting, communication,
and clear expectations for accountability. - Constraints in automated systems limit analysis
and flexible reporting.
121. Describe Procedures/Process
- Capital program involves three inter-related
processes
Project Delivery
13All Projects Have Common Tasks
Finalize design work
142. Describe Organizational Structures
- Decentralized approach to project delivery
- HQ units provide standards, tools, technical
assistance, oversight - Regions/modes have responsibility for day-to-day
management of individual projects - Organizational approaches vary by region/mode
- Project teams use varieties of matrix
management structures
15Example of matrix structure
163. Review Reporting/IT Systems
- Numerous silo information systems support
project delivery and house project data - Systems are not well integrated or flexible
- Review identified examples of inconsistent
information across reports - Several reporting processes require significant
manual intervention by staff - Opportunities exist to improve efficiency and
reliability of information with system linkages,
though costs and benefits should be examined
174. Critical Path Management
- Consultant found varied application of scheduling
practices for the example projects
185. Risk Management
- Consultant found varied application of risk
management practices for the example projects
19Cost/Schedule Performance
- Review focused on management methods, and not
actual performance outcomes for project delivery - However, JLARC revisited highway cost/schedule
data analyzed in a 1998 performance audit - Recent cost overruns on construction contracts
decreased from prior audit (from 10 to 6) - Proportion of contract change orders that were
avoidable and no value add decreased (from
38 to 29) - Recent time overruns on construction contracts
compared to initial awards increased (from 3 to
8)
20Cost/Schedule Performance (contd)
- Construction cost and time overruns are
inevitable on capital projects - Project budgets include contingency estimates,
and historically these have covered overruns at
WSDOT - JLARC did not examine how WSDOT overruns
currently compare to other jurisdictions
21Management Recommendations
- Rec. 1 WSDOT should extend the application of
existing principles and tools, and put management
steps in place to confirm their adoption - Managing Project Delivery (MPD)
- Project Delivery Information System (PDIS)
- Primavera Project Planner for the Enterprise (P3e)
22Management Recommendations (contd)
- Rec. 2 WSDOT should develop a plan and timeline
for implementing consultant recommendations,
focused primarily on - Using existing exemplary practices to develop
minimum standards/templates for critical path and
risk management techniques - Improving project communication by documenting
terms and definitions and - Confirming the consistency and currency of
reporting information.
23Management Recommendations (contd)
- Rec. 3 WSDOT should conduct an assessment of the
effectiveness of current information systems and
options for addressing any deficiencies.
24Management Recommendations (contd)
- Rec. 4 WSDOT should develop criteria for
extending Cost Risk Estimating and Management
(CREM) analyses to a wider universe of projects.
256. Options for Future Audits/Reviews
- Audit the effectiveness of Managing Project
Delivery (MPD) and the Project Delivery
Information System (PDIS) in improving project
delivery (with delayed audit start time). - Conduct an assessment of project delivery
performance measures, comparing WSDOT results to
similar programs at other states. - Audit the practice of determining construction
contractor pay estimates. - Conduct an assessment of alternative contracting
methods, such as alliance contracting.