KOPIO Closeout BNL, April 22, 2005 - PowerPoint PPT Presentation

About This Presentation
Title:

KOPIO Closeout BNL, April 22, 2005

Description:

We thank the KOPIO Collaboration and the RSVP Project Office for frank and open ... At the conceptual level KOPIO appears to be well thought-out and ingenious. ... – PowerPoint PPT presentation

Number of Views:33
Avg rating:3.0/5.0
Slides: 23
Provided by: profkar
Learn more at: https://www.c-ad.bnl.gov
Category:

less

Transcript and Presenter's Notes

Title: KOPIO Closeout BNL, April 22, 2005


1
KOPIO CloseoutBNL, April 22, 2005
  • The KOPIO Sub-panel
  • Marj Corcoran
  • Peter Denes
  • Karol Lang
  • Dick Loveless
  • Leo Piilonen
  • Stan Wojcicki
  • NSF, NSERC observers

,
2
Preamble
  • We thank the KOPIO Collaboration and the RSVP
    Project Office for frank and open discussions and
    presentations.
  • We have been impressed with the amount of effort
    put into the planning of the experiment.
  • At the conceptual level KOPIO appears to be well
    thought-out and ingenious.
  • It is also understood that limited funds
    available so far have led to a yet-incomplete
    detailed design but we have not identified any
    show-stoppers.
  • We were unable to thoroughly review the physics
    capabilities
  • but have no reason to doubt the claims presented
    in the CDR.
  • Findings and recommendations of the recent
    Ritchies Panel have been largely accepted by
    KOPIO.
  • We are reminded, however, that the past history
    teaches that upgrades will be necessary to reach
    the design sensitivity
  • Below are our findings, comments and
    recommendations.

3
First physics run in 2012
4
KOPIO breakout sessions
  • Presentations by
  • Mike Marx Status and plans
  • Dana Beavis Vacuum (WBS 1.2.1)
  • Toshio Numao Preradiator (WBS 1.2.2)
  • Nello Nappi KOPIO Trigger (WBS 1.2.7)
  • Oleg Mineev Photon veto (WBS 1.2.5)
  • Vladimir Issakov Calorimeter (WBS 1.2.3)
  • Doug Bryman - Backgrounds
  • Discussions with sub-system managers
  • Vacuum (WBS 1.2.1) Lang, Piilonen ?? Beavis
    an eng
  • Preradiator (WBS 1.2.2) Loveless ?? Numao
  • Calorimeter Photon Veto (WBS 1.2.3/1.2.5) -
    Corcoran, Lang ?? Issakov, Mineev
  • Charged Particle Veto (WBS 1.2.3) - Piilonen ??
    Frank
  • Trigger, DAQ (WBS 1.2.7/1.2.8) Denes ?? Nappi,
    Kettel, Schamberger
  • Offline (WBS 1.2.9) Piilonen ?? Poutissou
  • No discussions on System Integration and Project
    Services (WBS 1.2.10/1.2.11)

5
1.2.1 Vacuum - Findings
  • System consists of
  • Upstream Vacuum Decay Vessel ( 1418k)
  • Vacuum Transitions (windows membrane) (
    359k)
  • D4 Vacuum Box ( 238k)
  • Downstream Veto Vacuum Tank ( 393k)
  • Vacuum Pumping Station ( 630k)
  • Management Activities (includes ¼ engineer for 4
    years) ( 167k)
  • Biggest technical challenge
  • 12m3, 10-7 Torr, 7 X0
  • Investigated many options
  • Beryllium, Carbon fiber, Al Honeycomb, Aluminum
  • Carbon fiber 1/5 scale under construction in
    Russia
  • Spun aluminum seems best vendor quotes and
    fabrication plan
  • (SPINCRAFT) a vessel for 381k
  • Will order 2 vessels, the first one for tests
  • Membrane to separate 10-3 and 10-7 Torr vacuums.
  • Charge Particle Veto (CPV) to reside inside 10-3
    volume

6
1.2.1 Vacuum - Findings
  • Costs and Schedule
  • Probed down to level 5 cost drivers

1.2.1 Vacuum - Comments
  • In the past invested heavily in engineering of
    the tank good call!
  • More engineering necessary and is budgeted!
  • Need to integrate Charge Particle Veto
  • mounting
  • feedthroughs
  • define the membrane
  • Costing on D4 and D/S vacuum box agrees with past
    experience
  • Need to integrate the Magnet Photon veto system
  • Main cost drivers Vacuum tank, pumping station
  • Reasonable costs and schedule and the level of
    contingency

1.2.1 Vacuum - Recommendation
  • Complete the design CPV engineering integration

7
1.2.2 Preradiator - Findings
  • The preradiator is a 3 x 3 m2 sandwich of 256
    (2x2x64) cathode strip drift chambers and 288x27
    6 scintillator planks (8 mm thick) with Pb
    radiators
  • Designed to measure gamma ray location with a
    position accuracy of 5mm and an angular accuracy
    of 25mrad.
  • The cathode strip chambers consist of 75K
    channels of anode (wire TDCs) and 75K channels
    of cathode (strips ADCs).
  • On the outside of the scintillator-drift chamber
    sandwich is an array of 32x36 external photon
    vetos, which are made of Pb-scintillator.
  • The Triumf group is responsible for the
    preradiator including the front-end chamber
    electronics.
  • They will provide and install all parts of the
    preradiator except the external veto counters.
  • 5M from Canada
  • The estimated cost of the complete preradiator is
    22.6M with a contingency of 5.4M (31).

8
1.2.2. Preradiator - comments
  • The cathode strip drift chambers are well-suited
    to measuring the position and angle of the ?o
    conversion.
  • This is a well-developed technology used in other
    contemporary experiments
  • The WBS structure shows good detail and is fairly
    complete
  • Contingency of 31 seems small for a project of
    this size and development
  • Labor costs for chambers are comparable to
    materials costs (reasonable) but labor costs for
    electronics seems small
  • Electronics testing is part of vendor delivery --
    may need additional testing of assembled systems
  • Includes funding for 3 years of a system engineer
  • .

9
1.2.2 Preradiator findings/comments
  • The estimated base cost for the chamber
    electronics (not including contingency) is 6.53M
  • 32/channel for both anode and cathode
  • Labor for all electronics costed under anode,
    should be redone
  • Spares (about 10) should be included
  • Scintillator design uses extruded planks with
    holes
  • WLS shifting fibers inserted into holes -- nice
    design
  • Cathode strip chambers are excellent antennas
  • Solid grounds are essential
  • May need considerable work/testing during
    installation at Brookhaven
  • Triumf group is likely to need additional
    people/support to complete this project
  • responsibility for installing/integrating the
    photon vetos not designated

10
1.2.3 Calorimeter - comments
  • The design of the lead/scintillator modules is
    well-thought-out and complete. Costing was well
    documented and based on extensive experience.
  • The Calorimeter will be a shashlyk structure
    fabricated in Russia.
  • The group at Vladimir has an impressive track
    record in producing such devices, including
    Phenix, LHCb, and HERA-B.
  • They can produce the modules very
    cost-effectively.

11
1.2.5 Photon Vetoes - Findings
  • The photon vetoes consist of four different
    subsystems
  • Upstream Veto Barrel Veto Magnet Veto
    Downstream Veto
  • Shashlyk log lead/scintillator technology
  • These systems need a single-photon veto
    inefficiency on the order of 10-4 for KOPIO to
    succeed.
  • Where possible E949 phototubes will be recycled,
    resulting in considerable cost savings.
  • Shashlyk technology also used in the Preradiator
    photon veto.

12
1.2.5 Photon Vetoes - comments
  • The designs of the lead/scintillator modules
    seemed to be well-thought-out and complete.
    Costing was well documented and based on
    extensive experience.
  • Support structures In all cases except the
    barrel veto, the mechanical design of the support
    structure is yet to be designed.
  • Responsibility for installing/integrating the
    photon vetos not designated
  • Hermeticity is crucial to the success of the
    experiment. Therefore, the design of the support
    structure, especially ensuring it introduces no
    gaps or inert material is of utmost importance.
  • Spares For devices which are using 949 PMTs,
    there are some spare phototubes. For detectors
    which need new PMTs, no spares are in the
    baseline. None of the detectors have spare
    front-end electronics. But it is clear that the
    experiment cannot tolerate even one dead channel
    in the photon vetoes

1.2.5 Photon Vetoes - recommendations
  • Assign responsibility and provide adequate
    engineering to develop designs for the photon
    veto support structures and integration.

13
1.2.6 Photon Catcher findings/comments
  • The photon catcher is the an aerogel-lead device
    sensitive to the Cherenkov radiation produced by
    photons which convert in the lead. The
    sensitivity to neutrons is only 0.3, but even so
    this detector produces about 4-5 dead time.
  • This detector is the responsibility of the
    Japanese group, who has assumed all financial
    costs.
  • The Photon Catcher needs to achieve an
    inefficiency of 10-2, so the requirements are not
    nearly as stringent as for the other photon
    vetoes.
  • The Monte Carlo studies have been validated with
    beam tests at KEK, resulting in excellent
    agreement with Monte Carlo and data.

14
1.2.4 Charged Particle Veto - Findings
  • Cost 2.63M 1.27 3.35M
  • Schedule detector construction/installation
    done by FY08, electronics delivered by FY09
  • Thin segmented scintillator envelope inside
    vacuum tank to detect charged particles with
    gt99.99 efficiency and 100 solid angle scints
    overlap no cracks except for beamline
  • Barrel design, construction, assembly by Zurich
    design is advanced
  • Downstream design, construction, assembly by BNL
    design is conceptual
  • Front-end electronics shares common design with
    other systems, but who constructs, assembles and
    maintains it?
  • Each scint viewed by 3 or 2 direct-mount
    phototubes for redundancy this detector is
    inaccessible
  • Integration with vacuum vessel is needed at early
    stage of vacuum vessel design feedthroughs at
    vacuum vessel flanges for low voltage and LED
    monitor high/low vacuum barrierincluding
    mounting schemeand its contribution to the
    inert-material budget in front of each scint
    support structure heat-conduction scheme
  • Steeper charged particle entrance angle into
    downstream scints ? need thin scint coating
    MgF2? instead of wrapping to meet the
    inert-material budget is this lt20 mg/cm2 or lt8
    mg/cm2?

15
1.2.4 Charged Particle Veto - comments
  • The Charged Particle Veto is well designed. Some
  • issues vis a vis integration with the vacuum
    vessel
  • (feedthroughs, support, heat transfer, high/low
    vacuum
  • barrier) need to be resolved.
  • The costs of this subsystem, probed down to WBS
  • level 7 for the cost-drivers, are
    well-documented with
  • price quotations for materials/equipment and
    reasonable
  • estimates for fabrication/installation. No
    spares.
  • Fairly complete WBS. All aspects of the necessary
    work, including material procurement, design,
    labour, tooling, integration, and installation
    are included. Not clear who is responsible for
    the readout electronics, though.

16
Electronics
Many different components in many different WBS
elements
CLOCK
  • Chamber readout owned by preradiator
  • Photon readout is common
  • Photodetector owned by subdetector
  • Rest is owned by ? (Virtual) electronics group
    or subdet.
  • Integration owned by subdetector
  • Clock owned by L1 Trig
  • L3 trigger 400 node processor farm
  • L2 trigger TBD

Anode
TDC
Cathode
ADC
40 MHz
Logic/Pattern Boards
ADC
PMT
Base
ADC
APD
Super- visor
250-500 MHz
DAQ
Front end and digitizers
Collectors
L1 Trig.
17
Electronics - comments
  • Certain elements well developed and prototyped
    others in (pre-) conceptual design
  • Significant engineering needed
  • For prototype to production board design
  • For trigger electronics design
  • For FPGA coding
  • Work estimates reasonable for an iteration
    perhaps short for final production
  • Testing and integration manpower needed
  • Schedule is tight for certain items
  • L1 trigger has 6 months float ? need
    manpower/engineering by then
  • 10x10 calo prototype assumed to use final
    electronics ? 18 months to finalize calo
    electronics

18
Electronics - comments
  • The group appropriately exercised the contingency
    methodology proposed by the project.
  • Relative to charge recognizing, importantly,
    that the construction project will include
    significant engineering design and development
    activity KOPIO presents no significant
    electronics challenges

Electronics - recommendations
  • Add people (and use that as a metric)
  • Consider forming an electronics group (at least
    for everything other than the chamber front-end)

19
1.2.9 Offline - Findings
  • Cost 0.78M 1.18 0.92M
  • Schedule hardware purchased as late as possible,
    software development schedule to be fleshed out
    in Fall 2005 with work done on collaborators
    existing equipment
  • Hardware purchase commodity components  tape
    silo (4 tape drives, 600 tapes, 1 TB/tape) for
    raw data disk farm (100 TB) for skimmed data 84
    dual-node processor farm for real-time
    processing 15 workstations network switches
    racks
  • System manager (0.5 FTE) is shared with L3
    trigger.
  • Software simulations, reconstruction,
    generation of calibration constants, quality
    assurance monitor, data analysis, skimming, data
    management
  • One professional programmer and many physicists
    to design and manage analysis framework, data
    format, data management system, detector
    description language, and documentation
  • Full-time software managers (physicists) needed
    for simulation, event reconstruction, calibration
    analysis, physics analysis, quality assurance
    monitor. Additional manpower (physicists) needed
    to do the work.

20
1.2.9 Offline - comments
  • A plan needs to be formulated this year for the
    software development effort.
  • The hardware costs of this subsystem, probed down
    to WBS level 6 for the cost-drivers, are
    well-documented with price quotations for
    equipment (based on recent TRIUMF purchases) and
    reasonable estimates for performance improvements
    in 4 years.
  • Software costs are dominated by salary of one
    computer professional. However, additional
    professionals will be needed.
  • All aspects of the necessary work, including
    equipment procurement, design, labour, tooling,
    integration, and installation, are included in
    the WBS. Timetables are to be solidified for
    software work.
  • Additional manpower needs are likely.
  • L3 and offline should consider adopting a common
    processor-node spec.

21
Contingency
  • Currently, bottoms up Lockheed formula.
  • This appears to be artificial and not adequate.
  • Top-down contingency proposed by the RSVP
    management is 45. It is more reasonable but we
    are unable to assess if it is correct.
  • This would give a total cost of KOPIO to be
  • 53M 1.45 ? 77M spares
  • We recommend that KOPIO refines contingency
    analysis to improve credibility of the cost
    estimation.

22
Response to the charge
  • Technical approach and feasibility
  • Conduct early beam tests as feasible
  • Refine simulations to improve credibility of
    background calculations
  • Completeness of the plan (WBS)
  • Reasonably complete
  • NO spares!
  • Readiness to proceed to construction
  • Significant engineering required
  • Expansion of the Collaboration necessary
  • Likely duration of the experiment
  • Past experience for this type of experiments
    teaches that upgrades and improvements will be
    necessary to reach the design sensitivity
  • (Technical) metrics of progress
  • Adding personnel is the most critical need
  • Costs and schedule
  • Refine contingency analysis to improve
    credibility of cost estimation
Write a Comment
User Comments (0)
About PowerShow.com