Title: Center St. Bridge Expansion
1Center St. Bridge Expansion
- Anthony Podegracz, P.E.
- Kimley-Horn and Associates
2Center St. Bridge Expansion
- Cantilevered Bikeway/Walkway Phase I of Piru
Rail/Trail Project - Owner Ventura County Transportation Commission
- Project Manager Ventura County Public Works
Agency - Design Consultant Kimley-Horn and Associates,
Inc - Contractor Mendez Concrete
- Construction Contract Award 1,696,582
- Final Construction Cost 1,696,192
3Center St. Bridge Expansion
- Center St. Bridge
- Rural Community link over Piru Creek
- 409 Existing Cast-in-place Box Girder with
Superelevated Curve - Two lane bridge with 4 Shoulders
4Center St. Bridge Expansion
- Project Constraints
- Environmental
- Sensitive Creekbed
- Swallow Nesting
- Structural
- Minimum Alterations to Bridge
- New Deck must be able to Support Vehicles
- Restricted Access
- 24 Circular Holes in Bottom of Bridge
- No Equipment allowed in Creekbed
5Center St. Bridge Expansion
- Cantilevered Walkway
- Separate Bikes and Peds from Roadway
- 10 Wide Exodermic Deck System attached to
Existing Cast-in-place Box Girder - Lightweight System
- No Structural Modification required on existing
Bridge - Post-tensioned
6Center St. Bridge Expansion
- Approach Wall
- Hollow Box Wall
- Poured-in-place Retaining Wall System attached to
Existing Retaining Wall - Minor Modifications to Existing Roadway
- All work completed within existing County
Right-of-way
7Center St. Bridge Expansion
- Construction Methods
- No Creekbed Access
- Work done from Above
- Contractor Basket
- Work within Existing Bridge
- Access Holes in Bottom of Existing Bridge
- Additional Temporary Holes Added to Top of Bridge
Due to High Water Level
8Center St. Bridge Expansion
- Construction Process
- Web Plates Attached
9Center St. Bridge Expansion
- Construction Process
- Post-Tension Bars Attached and Tensioned
10Center St. Bridge Expansion
- Construction Process
- Falsework and Deck System Placed
11Center St. Bridge Expansion
- Construction Process
- Deck Poured
12Center St. Bridge Expansion
- Construction Process
- Approaches Completed and Railing Attached
13Center St. Bridge Expansion
- Started February 2005
- Completed October 2005