Presidential Program in Norway 2006 June 16, 2006 - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

Presidential Program in Norway 2006 June 16, 2006

Description:

First rich gas reached the K rsto facility on 25 July 1985, and dry gas began ... Satelite fields Statfjord st, Nord and Sygna have a separate inlet separator on ... – PowerPoint PPT presentation

Number of Views:47
Avg rating:3.0/5.0
Slides: 12
Provided by: TRO117
Category:

less

Transcript and Presenter's Notes

Title: Presidential Program in Norway 2006 June 16, 2006


1
Presidential Program in Norway 2006June 16, 2006
  • SUMMARY PRESENTATION

2
Kårsto gas processing plant
  • First rich gas reached the Kårsto facility on 25
    July 1985, and dry gas began being piped on to
    Emden (Germany) on 15 October 1985.
  • Main task of Kårsto to receive and process gas
    and condensate from the important areas of
    Norweigian continental shelf and to transport
    them to continental Europe and Norweigian
    consumers.
  • Kårsto the worlds third biggest LPG producer.
  • The main Kårsto complex occupies 108 hectares of
    a 208-hectare site.

3
Transport system in Kårsto
  • FROM
  • Norweigian Sea
  • Åsgard 42 inches
  • Capacity 69 mil scm/d
  • Rich gas
  • North Sea
  • Statpipe 30 inches
  • Capacity 25 mil scm/d
  • Rich gas
  • Sleipner condensate 20 inches
  • Capacity 200 000 b/d
  • Unstabilised condensate
  • TO
  • Statpipe 28 inches
  • Capacity 20 mil scm/d
  • Lean (sales) gas
  • Europipe II 42 inches
  • Capacity 72 mil scm/d
  • Lean (sales) gas
  • 10 mln tn NGL/condensate per year
  • Ethane 112 tn/hour
  • Propane 385 tn/hour
  • Iso-Butane 76 tn/hour
  • N-Butane 145 tn/hour
  • Naphtha 106 tn/hour
  • Condensate 351 tn/hour

4
K LAB in Kårsto
  • The Kårsto metering and technology laboratory (K
    LAB) is a large-scale facility for testing and
    qualifying equipment and processes relayting to
    hydrocarbon production and transport.
  • Assignments include calibration of wet gas and
    multiphase flow meters in the 20 150 bar range,
    qualification of gas separators, and testing of
    pumps and compressors.
  • This labarotory makes the testing of pigs which
    designed for multidiameters pipelines.
  • There is the model of subsea construction with
    pipeline and receiving terminal here.

5
ABOUT STATFJORD
  • Discovered 1974
  • Development approval 16.06.1976 by the Storting
  • On stream 24.11.1979
  • Operator Statoil ASA
  • Estimated production in 2006
  • - 86 000 barrels/d oil
  • - 1,43 billion scm gas
  • - 0,68 million tonnes NGL
  • 3 platforms Statfjord A, B, C
  • Satelite fields Statfjord Øst, Nord and Sygna
    have a separate inlet separator on Statfjord C.

6
Common information about Statfjord
  • Location the border between the Norwegian and
    British sectors.
  • New challenges
  • - modification of Statfjord B and C
  • - new export gas pipeline from platform SFB to
    UK (St. Fergus, Scotland).
  • Total CAPEX about 2 bil. dollars USA
  • - pipeline 10
  • - Statfjord B, C 60
  • - Statfjord A 30.
  • Increasing of field life at least 10 years.
  • Remaining reserves
  • - 18,4 million scm oil
  • - 26,9 billion scm gas
  • - 11,8 million tonnes NGL.

7
Statfjord late life project
Convert to gas production
Oil production
1979
2007
2020
  • The next step -change of drainage strategy

8

PROJECT DEVELOPMENT
Statoil
Gazprom - Conception (Technical Economical
ideas) - Investment Plan and Declaration of
investments to construction - Substantiation of
Investments to constructon buildings and
structures - Business Plan
9
Govermental expertises
  • Norway
  • 1 expertise after FEED stady (Ministry of Oil
    and Energy)
  • - resources expertise
  • - HSE.
  • Russia
  • 2 expertise after completion of Substantiation
    of Investments and FEED study
  • Substantiation of Investments
  • - expertise of Ministry of emergency
    situations of RF
  • - ecological expertise.
  • FEED study
  • - expertise of Ministry of emergency
    situations of RF
  • - ecological expertise.
  • - expertise of Ministry of helath protection
    and social development
  • - expertise of industrial safety
    (Rosstechnadzor)

10
The same projects
  • Langeled Gas Pipeline
  • Gas will be transported from the land facilities
    for Ormen Lange at Nyhamna via a tie-in at the
    Sleipnir riser facility to a new receiving
    terminal at Easington on the eastern coast of the
    UK.
  • 42 inch pipeline Nyhamna Sleipnir, 44 inch
    pipeline Sleipnir Easington.
  • 80 scm million/day gas the northern leg 70
    million/day gas the southern leg.
  • Length 1200 km.
  • Operation the southern leg October 2006 the
    northern leg October 2007.
  • Northern-European Gas Pipeline
  • Gas will be transported from CS Portovaya
    (Russia, Leningrad region) to Graifswald
    (Germany).
  • 48 inch pipeline 210 bar.
  • 55 billion scm/year gas.
  • Length 1200 km.
  • The pipeline has the gas branch to Sweden (16
    inch pipeline). The capasity is 3 billion
    scm/year.
  • Operation the first line 2010 the second line
    2012.

28
45
11
Thanks for attention