Title: 2005 Title 24 Nonresidential Acceptance Requirements Mechanical Designer Training
12005 Title 24 Nonresidential Acceptance
RequirementsMechanical Designer Training
- Presented by
- Tav Commins
- California Energy Commission
2Overview
- First Energy Codes for California developed in
1973. - Code is updated every three years.
- Residential Code and Nonresidential Code
3Overview
- Two ways to comply (Prescriptive and Performance)
- Prescriptive Listed values for efficiency of
equipment, walls and the maximum amount of glass
that may be installed. - Performance The building is modeled using a
approved computer program.
4Overview
- All conditioned buildings must comply with the
energy code. - All nonconditioned commercial buildings must
comply with the indoor lighting requirements.
5Overview
- October 1st 2005 latest code revision went into
place. - Commercial and Residential buildings now require
verification that key pieces of equipment were
installed properly.
6When must the tests be conducted?
- All new construction
- In existing buildings when that piece of
equipment is replaced.
7Overview
- Building Efficiency is a product of
- Design, materials equipment
- Installation and set-up
- Occupant patterns and control
- Traditional standards
- Specify materials, equipment, controls
- Law of diminishing returns for more eff equip
- 2005 Title 24 Part 6 Energy Standards
- Assure equipment works as intended
8What is Acceptance Testing?
- Two components of acceptance testing
- Construction inspection
- Is the specified equipment that is required to be
installed actually there - Equipment testing
- Does the equipment work as intended
- Functional performance tests
- Does Not replace commissioning
- Commissioning broader scope
9Project Overview
Definition of Acceptance Testing Requirements
- Acceptance Testing requirements are defined as
the application of targeted inspection checks and
testing to determine whether specific building
systems conform to the criteria set forth in the
Standards and to the plans and specifications.
10Is Acceptance Testing Needed?
- PIER Small Commercial HVAC survey
http//www.energy.ca.gov/reports/2003-11-17_500-03
-082.PDF - Small commercial buildings lt 4 yrs old
- 64 of economizers failed
- Cooling energy increased by 37
- 38 of supply fans cycling during occupancy
- Violation of Title 24, 121(c)1
- 30 unoccupied fan operation
- Increase of fan and heating energy
- 8 no outside air
- 8 simultaneous heating and cooling
11What Systems are Included
- HVAC
- All packaged HVAC systems
- All built-up HVAC systems
- Hydronic systems
- Lighting Controls
12Acceptance Tests
- Required self-certification that equipment was
tested and works as intended by the Standards - Liability trail results from cheating on test
- Only one test (air distribution
efficiency-leakage) requires 3rd party testing - Home Energy Rating Service (HERS)
13Resources
- 2005 Building Energy Efficiency Standards for
Residential and Nonresidential (Title 24) - 2005 Nonresidential Energy Compliance Manual
- Chapter 4 Mechanical Systems
- Chapter 8 Acceptance Requirements
- End of Manual - Compliance and Acceptance Forms
- CEC Resources
- http//www.energy.ca.gov/title24
- CEC Bldg Standards Hotline (800)772-3300
14Acceptance Chapter (Chapter 8) Nonresidential
Manual
- Overview of compliance process
- At-A-Glance - 2 page overview of test
- Purpose ? Estimated Time
- Benefits ? Warnings or Cautions
- Instrumentation ? Test conditions
- Acceptance Criteria
- Detailed test description
15Acceptance and Compliance Forms
- Found in Appendix A of the Nonresidential Manual
- Compliance forms
- Filled out by designer
- MECH-1-C (C for compliance)
- Acceptance Forms
- Filled out by person conducting test
- Usually contractor, TAB or commissioning agent
- MECH-1-A (A for acceptance)
16Compliance Forms
- Compliance documentation with equipment
specification and forms - MECH-1-C lists all tests and which equipment must
by tested - MECH-1-C lists designated personnel to perform
tests - MECH-3-C lists design minimum outside air
- Criteria for outside air tests (NJ.3.1 3.2)
17Acceptance Forms
- Installing contractor or other eligible
professional conducts tests and fills out
MECH--A acceptance forms - Equipment test - until it passes all tests
- Completed forms handed to inspector along with
other documentation - Certificate of Occupancy Granted
18Designer Has a Big Impact on Ease and Cost of
Acceptance Tests
- Designer clearly identifies tests
- Problem if covered equipment not specified on
MECH-1-C form and later needs testing - Designer specifies equipment
- Pre-calibrated equipment is cheaper
- Designer builds in test capabilities
- Test ports and pre-installed gages
- Valves for isolating equipment
19Key Statements in MECH-1-C
- The plans meet code
- I am qualified to sign these forms
- List of all mechanical acceptance tests with
blanks for - Equipment to be tested
- Who will test equipment
- Installing Contractor
- Design Professional
- Agent Selected by Owner
20MECH-1-C Note to Bidders
- Since the MECH-1-C will be part of the plans,
completion of this section will allow the
responsible party to budget accordingly - Be careful to budget appropriately
- Make note of this section to potential bidders
21(No Transcript)
22(No Transcript)
23People Certified to Perform Tests
- The installing contractor, engineer of record,
TAB contractor, or owners agent (i.e. 3rd party
Cx provider) - The building inspector has the authority to
require the Acceptance Agent to demonstrate
competence, to his/her satisfaction
24Equipment Specification
- Equipment specification can reduce level of
acceptance testing and cost - Thermostats with Pre-programmed schedules
- Factory calibrated sensors with documentation
- Pressure sensor for Variable Frequency Drive
(VFD) control - Air flow monitoring station
- Demand Control Ventilation (DCV) CO2 sensor
calibrated 75 ppm - Supply water temp reset sensor
- Alternative is field calibration against
reference sensor by using acceptance protocols
25Air-side acceptance test forms
26Hydronic Acceptance Forms
27MECH-2-A Outside Air
- Same form used to document outside air acceptance
for - CAV constant air volume NJ.3.2
- VAV variable air volume NJ.3.1
- Measured minimum outside air must be within 10
of design minimum outside air - Test and Balance (TAB) contractor is probably the
best qualified and has proper flow measurement
tools available
28MECH-2-A VAV Outdoor Air
- Sensor used to control outdoor air flow must
have calibration certificate or be field
calibrated - Air flow monitoring station
- Pressure across dedicated fixed damper
29MECH-2-A VAV Outdoor Air
- Contractor must set minimum outdoor air within
10 of design outdoor air at full flow and at
minimum flow - Control strategies discussed in Mechanical
Chapter of Nonresidential Manual
30MECH-2-A Outside Air Measurement
- Calibrated air flow station
- Pitot traverse in a straight section of duct
- Pitot traverse across O/A inlet
31MECH-3-A Constant Volume Packaged HVAC Test
- Thermostats or zone temperature control
- Thermostat or zone temperature sensor is located
in zone served by unit - T-stat has capability of 5º deadband between
heating and cooling - Occupied, unoccupied and holiday schedule
programmed - One hour pre-occupancy purge turns on fans 1
hour before occupied. - Set-up and set-backs programmed as per design
instructions
32MECH-3-A Constant Volume Packaged HVAC Systems
- Residential thermostats wont work
- Occupied Fan must run continuously
- Unoccupied Fan runs intermittently to supply
load - Timed manual override of unoccupied settings
- Outside air damper position
- Minimum position during occupied period
- Closed during unoccupied periods
- Test likely conducted by HVAC contractor and
perhaps Controls contractor
33MECH-4-A Economizer Construction Inspection
- Likely performed by HVAC contractor
- High limit setpoint not greater than listed in
Table 144-C per Standards Section 144(e)3 - High limit sensors
- are factory calibrated with calibration
certificate or - field calibrated.
- Which is easier?
34MECH-4-A Economizer Construction Inspection
- Integrated economizer 144(e)2B
- Capable of providing partial cooling even when
additional mechanical cooling is needed to meet
the load - EMS systems cooling coil modulates to provide
remainder of load - Stand-alone systems two stage thermostat is
minimally compliant - When outdoor air temp below high limit,
economizer provides 1st stage cooling - When O/A gt high limit first stage of cooling
provided by compressor - 2nd stage of cooling provided by compressor
35MECH-4-A EconomizerEquipment testing
- Not required if economizer is factory installed
and tested - Attach manufacturers certification
- Field installed or if no factory certification
- Simulate cooling load and enable economizer
- O/A damper opens, return damper closes and relief
is provided by relief damper or exhaust damper - Mechanical cooling enabled only if economizer
cant meet load - Simulate cooling load and disable economizer
- O/A damper closes, return damper opens
- Mechanical cooling enabled
36MECH-5-A Air Distribution 144(k)
- Small (lt5,000 sf) CV systems only
- When gt 25 of duct surface is outdoors or in
unconditioned space - Place greater than 75 of ducts under insulated
roof test not needed - Ducts must be tested for duct leakage by the
installing contractor and verified by a 3rd party
HERS rater.
37MECH-5-A Construction Inspection
- Drawbands
- Stainless steel worm drive or
- UV resistant nylon duct ties
- Must use UL 181 tape or mastic
- Cloth backed duct tape not used unless with
drawbands and mastic - R-8 insulation on all ducts in unconditioned
spaces
38MECH-5-A Duct testing
39MECH5-A Leakage TestNew Construction
- Rated flow from capacity
- 400 cfm/ton
- 21.7 cfm/kBtuh heating only systems
- Seal all diffusers
- Pressurize system to 25 Pa (0.1 in WC) with fan
with calibrated orifice (duct blaster) - Measured leakage no greater than 6 of rated flow
- Conducted by HVAC contractor. Must seal all
leakes - Verified by HERS rater
40MECH-5-A Duct Sealing on Retrofits144(k),
149(b)1DE
- Applies to small Constant Volume system with
ducts in unconditioned spaces when - Any amount of ducts replaced or added, or
- Changeout of HVAC system, or
- Major repair (new condenser, new coil)
- Existing ducts
- Leakage 15 of rated supply flow, or
- gt60 reduction of leakage prior to sealing ducts
with all visible leaks sealed, or - Cant access the ducts and all visible leaks are
sealed as certified by a HERS rater - Exceptions
- Asbestos
- Existing ducts that were previously certified
41MECH-6-A Demand Control Ventilation
- Likely conducted by controls contractor
- Construction Inspection
- Sensor mounted in room between 1 and 6 ft from
floor - Calibration
- Factory calibrated with manufacturers
certification of 75 ppm accuracy - Field calibrated using reference gas or reference
sensor - Which is easier?
42MECH-6-A DCV Equipment Test
- Simulate a high CO2 load
- Decrease CO2 setpoint or breathe on sensor
- Outside air damper modulates open
- To design outside air setting from MECH-3-C
- Simulate a low CO2 load
- Increase CO2 setpoint, dont breath on sensor
- Outside air modulates to minimum position
43MECH-7-A Supply Fan Variable Frequency Drive
- Construction inspection
- Factory calibrated pressure sensors with
certificate (dont lose these!) - Field calibration against a reference sensor
- Equipment testing
- Full flow all boxes calling for cooling
- Measured pressure within 10 of control pressure
- Reduced flow boxes not calling for cooling
- Measured pressure within 10 of control pressure
- Reduced flow pressure full flow pressure
44MECH-8-A Hydronic Tests
- Construction inspection
- Confirm piping, sensors and controls are located
as shown on plans - Sensors are factory calibrated or field
calibrated - Temperature for temperature reset
- Pressure for VFD control
45Summary
- Acceptance tests assure that your design intent
for energy savings is executed - Most automatic controls have an associated
acceptance test - The designer identifies which tests get applied
to which equipment on the MECH-1-C form - Construction bids need to account for the costs
of conducting and documenting the acceptance
tests - Specifying factory calibrated and factory
installed equipment can dramatically reduce
testing costs - Some designs reduce the amount of testing needed
- ducts run under an insulated roof
- factory installed economizers
46Resources 2005/2008 Standard
- Energy Efficiency Hotline
- Open 800 to 1200 and 1 to 430
- E-mail title24_at_energy.state.ca.us
- Phone 916-654-5106 or
- Phone 1-800-772-3300
- http//www.energy.ca.gov/title24/
- California Commissioning Collaborative
www.cacx.org
47Questions
Um Bob, I have a question.