Title: Small Scale Projects


1
Small Scale Projects Learning from the CDM
Paul Soffe
2
Small-scale Facility Concept
  • A dedicated facility providing buyers with CERs
    from small-scale projects
  • Facility participants structure their
    requirements, specifying
  • Project type / Countries / Fixed price
  • Current buy orders from Government of Austria and
    Japan Carbon Finance
  • EcoSecurities sources all projects
  • Direct sourcing global network
  • eg. ECo joint venture (2E Carbon Access)
  • EcoSecurities prepares all project documentation
  • PDD, MV plan etc.
  • Arranges validation with a DOE
  • Coordinates and oversees monitoring, verification
    and issuance
  • All project developer costs are covered by the
    facility
  • PDD, Validation, Registration
  • Only cost to developer is verification and annual
    Share of Proceeds after CERs are produced
  • Track-record Small-scale Facility has
    registered 5 projects under CDM. One has issued
    CERs.

3
Facility Structure
Project 1
Master ERPA
Buyer Govt of Austria and JCF
EcoSecurities
Project 2
Project 3
Project 4
Individual ERPAs
Project 5
4
Key issues for SSc Project Success under carbon
mechanisms
  • Minimise costs all costs related with CDM
    project development, including third party costs
    for validation and registration have to be
    minimised
  • Simplicity - all documentation standardized
  • Speed entire process process cannot be too
    long, SSc developers have limited budgets (time
    and cost)
  • Expertise SSc need access to assistance with
    process
  • Financial value-added prices for ERUs (CERs)
    for smallest project may need to be higher
  • Track-record Demonstrating that JI SSc can work
    with the rapid approval and development of the
    first projects is very important

5
Advantages for Buyers
  • Small-scale projects with high sustainable
    development benefits
  • High-quality projects that have received business
    development services, thorough due diligence and
    assistance reaching financial closure more
    likely to reach CER delivery targets
  • Projects that have advanced through the CDM
    Development Process PDD completed, validated,
    or registered
  • Low transaction costs and high efficiency and
  • Optimum equilibrium between high quality project
    assessment and low transaction costs.
  • Track-record Small-scale Facility has registered
    5 projects and 2 pending. One has received CERs.

6
Case Study La Esperanza Hydroelectric Project
  • Location Western Honduras
  • Project type Hydroelectric
  • Installed Capacity 12.73 MW
  • CO2e per year 37,031 tons
  • CER buyer World Bank
  • Current Status Issued CERs
  • Lessons learned
  • Partnerships
  • Engage with DNA early in the process
  • Additionality include early
  • Start Early

7
Case Study Pig projects in the Philippines
  • Case Study Small-scale pig projects
  • Location Philippines
  • Project type Anaerobic
    Digestion
  • Installed Capacity 150 kW each
  • CO2e per year 1,500 to 10,000 tons
  • CER buyer Austria, JCF, and
    EcoSecurities
  • Current Status Final validation
  • Lessons learned
  • Difficult to keep transaction costs low
  • Economies of scale possible over time
  • Methodologies data availability
  • Validation costs high

8
Case Study Hydro in Honduras
  • Case Study Cuyamapa Hydroelectric Project
  • Location Western
    Honduras
  • Project type Hydroelectric
  • Installed Capacity 12.20 MW
  • CO2e per year 38,552 tons
  • CER buyer EcoSecurities through
    Austrian Facility
  • Current Status 1st Registered Unilateral
    Project
  • Lessons learned
  • Engage with DNA early in the process
  • Unilateral Project

9
Lessons Learned
  • Bundles of SSc projects an attractive option for
    buyers to secure a number of projects
  • Under CDM rules it was possible to develop a
    large pipeline of projects for the Facilities
  • Uncertain what problems may be encountered during
    moniotirng, certification, and issuance stages
  • Other problems unrelated to CDM Executive Board
  • price expectations and forecast for CERs
  • host country approval can take a long time

10
Conclusions
  • Make system for SSc projects as simple as
    possible to reduce transaction costs associated
    with carbon related aspects of project
    development
  • Any charges for by JISC must be kept low
  • Specify as much of JI cycle in detail ASAP.
    Clarity is important in building confidence that
    JI is workable
  • Do not re-invent the wheel
  • Utilise CDM baseline meths additionality tools
    of SSc
  • Are any specific meths needed for JI SSc in
    addition to CDM meths (I do not know). If so
    develop them SSc developers will not and cannot
    (they are by default relatively poor)