High Intensity Neutrino Source HINS Linac FrontEnd R - PowerPoint PPT Presentation

1 / 36
About This Presentation
Title:

High Intensity Neutrino Source HINS Linac FrontEnd R

Description:

Accomplish the R&D necessary to establish technical credibility and cost basis ... Demonstrate high-speed (nanosecond) beam chopping at 2.5 MeV ... – PowerPoint PPT presentation

Number of Views:51
Avg rating:3.0/5.0
Slides: 37
Provided by: Keph
Category:

less

Transcript and Presenter's Notes

Title: High Intensity Neutrino Source HINS Linac FrontEnd R


1
High Intensity Neutrino SourceHINS Linac
Front-End RD ---Systems Integration, Beam
Diagnostics Needs, and Meson Lab Setup
  • Bob Webber

2
Motivation and Timeline
  • Motivation
  • Test key un-proven technologies important to the
    low-energy front-end (ßlt0.4) section of the
    proposed 8 GeV Superconducting H- Linac
  • Timeline
  • Accomplish the RD necessary to establish
    technical credibility and cost basis for the
    Linac front-end by 2010
  • Funding Resources
  • 10M in FY06 (FNAL and collaborators SWF and
    MS)
  • similar funding projected for FY07 and 08 until
    recent rumblings from DOE (within the last 4
    weeks)

3
RD Objectives
  • Demonstrate high power RF distribution and 4.5
    millisecond pulse operation of multiple cavities
    from a single klystron
  • Demonstrate device and system performance of high
    power vector (IQM) modulators for amplitude and
    phase control of multiple cavities
  • Measure axially-symmetric beam performance with
    RT-CH (room temperature, crossbar H-type) spoke
    resonator cavities and SC solenoid focusing in
    the RT Linac
  • Demonstrate low transition energy (10 MeV) to and
    application of superconducting spoke resonator
    accelerating structures
  • Demonstrate high-speed (nanosecond) beam
    chopping at 2.5 MeV
  • Demonstrate performance of this Linac concept and
    resulting beam quality to 90 MeV

4
RD Plan
  • Install and commission 2.5 MW, 325 MHz klystron
    system
  • Equip and operate a 325 MHz high power RF
    component test facility
  • Fabricate, install, and operate a test cryostat
    for 325 MHz SC spoke cavities
  • Construct and test key components of the
    low-energy Linac concept
  • Assemble the 10 MeV RT Linac, operate with beam,
    and verify performance
  • Install 325 MHz SC spoke resonator cryomodules
    and operate with beam up to 90 MeV
  • This all adds up to building a first-of-its-kind
    superconducting 90 MeV H- linac

5
Major Activity Areas in Meson
  • 325 MHz Klystron and Modulator Area
  • 325 MHz RF Component Test Facility
  • Cavity Test Cave (RT-CH and superconducting
    cavities)
  • Ion Source, RFQ, and 2.5 MeV Absorber Area
  • 90 MeV Accelerator and Beam Absorber Cave

6
Meson Building Floor Plan
Cavity Test Cave
RF Component Test Facility
Klystron and Modulator Area
90 MeV Linac
Ion Source and RFQ Area
200 ft.
7
View Into Klystron/Modulator Area (early May)
8
325 MHz 2.5MW Klystron (early May)
9
4.5 msec Klystron Pulse Transformer (early May)
10
325 MHz Waveguide Circulator (early May)
11
View Into Klystron/Modulator Area (June 9)
12
View Into Klystron/Modulator Area (June 9)
13
Klystron and Waveguide (June 16)
14
Modulator Capacitor Cabinet (front) (June 28)
15
Modulator Switch Cabinet (back) (June 28)
16
Modulator Switch Cabinet (front) (June 28)
17
View Down (Future) Linac Beam Line
18
Layout Through Second ß.4 Cryostat
Ion Source
RFQ
MEBT
Room Temperature 16-Cavity, 16 SC Solenoid Section
2.5 MeV
50 KeV
10 MeV
Two ?0.2 SSR 9-Cavity, 9-Solenoid Cryostats
20 MeV
30 MeV
Two ?0.4 SSR 11-Cavity, 6-Solenoid Cryostats
90 MeV
60 MeV
19
Meson Linac Cave Cross-section
20
Beam Diagnostics - Minimum on-line (P. Ostroumov)
  • Current transformers (CT)
  • Beam phase pick-up necessary to control energy
    stability during the operation
  • Initial tune-up of the cavity field and phase
  • Beam profile wire scanners (or/and laser
    scanners)
  • Beam loss monitors about 20 distribute along
    the linac
  • Inter-cryostat space should include
  • CT
  • BPM, includes phase pick-up
  • Wire scanner

21
Off-line (temporary installation)
  • The temporary diagnostics station is desirable to
    use at the end of the following linac sections
  • RFQMEBT, RT section, SSR1, SSR2 - will be
    permanent place
  • Diagnostics station includes (minimum set)
  • 1 solenoid (or 3 quads, triplet)
  • 2 steering magnets
  • 2 BPMs, includes phase pick-up
  • 3 profile monitors
  • 2 current transformers
  • Beam dump water cooled
  • Energy degrader
  • Faraday cup
  • Fast Faraday cup
  • CCD camera with the quartz foil
  • Maximum set, extend for
  • Emittance station slit-collector copy from
    SNS
  • Bunch length custom design

22
Machine and Beam Parameters
  • Two operating modes providing 1.56E14 ppp
  • 3 millisecond 8.6 mAaverage beam pulse at 2.5
    Hz
  • 1 millisecond 26 mAaverage beam pulse at 10 Hz
  • Bunch Frequency 325 MHz
  • (1/4 of ILC 1.3 GHz)
  • Chopped in MEBT (2.5MeV) at 53 MHz ( 2 of 6
    bunches missing) and at 89 KHz (1.6 microsecond
    gap) therefore peak beam current is 1.5 times
    average current stated above
  • Beam tube aperture
  • 20mm bore radius through focusing solenoids
    15mm? through warm RF cavities

23
Baseline - 05/15/06 Trans. envelopes
24
MEBT June 12, 2006 Dimensions OK
Increase this space and use it for the steering
magnet
25
CH-SSR1
Strip-line BPM
This space can be increased up to 204 mm
26
So What is Needed Now?
  • Beam current transformer electromechanical
    designs
  • BPM pick-up electromechanical design(s) for RT
    and SSR Linac sections
  • Scanning wire electromechanical designs
  • Laser wire design
  • Beam phase monitor system design
  • Beam energy analysis system
  • Beam bunch length monitor?
  • Electronics for all above

27
SNS Diagnostics plate
28
BPM (SNS)
29
Meson Schedule 2006
  • Short mock Linac cave section available
  • May 2006 ?
  • Klystron modulator completion
  • July 2006 (late July)
  • 325 MHz RF power system commissioning
  • July 2006 (early August)
  • 325 MHz component testing in RF test area
  • Starting August 2006
  • 325 MHz RT cavity power testing in cavity test
    cave
  • September 2006
  • Superconducting cavity test cryostat installation
  • October 2006
  • Ion Source installation in Meson
  • November 2006

30
Meson Schedule 2007
  • RFQ (now in procurement) delivery and power
    testing
  • January 2007
  • RT cavity and coupler testing
  • Starting February 2007
  • 2.5 MeV beam tests
  • Beginning February 2007
  • First SC spoke resonator power tests in test
    cryostat
  • April 2007
  • Linac cave construction and utilities
    installation
  • May 2007
  • Demonstration of multiple cavity RF distribution
    and independent amplitude phase control
  • July 2007
  • Beam accelerated through first N RT cavities
  • September 2007 (optimistic)

31
Meson Schedule 2008
  • Full 10 MeV RT linac installed
  • April 2008
  • RD beam operations at 10 MeV
  • Starting May 2008
  • First SC spoke resonator cryomodule installation
  • October 2008
  • Tests of RT SC cavity RF distribution and
    independent amplitude phase control
  • November 2008
  • Beam through first SC spoke cryomodule
  • December 2008 (optimistic)

32
Manpower Resources
  • A Lab-Wide effort is required and now being
    applied
  • Beam line components are designed and procured by
    Technical Division
  • RF and conventional power source components and
    systems integration and operation are the
    responsibility of the Accelerator Division
  • Particle Physics Division is supplying manpower
    for utilities and infrastructure installation in
    the Meson building
  • Laboratory Safety Section and Accelerator
    Division Safety Department are already at this
    early stage actively involved
  • Key technical systems now lacking required
    attention
  • RF power distribution system (tightly coupled
    with cavity design status and power requirements)
  • Low level RF systems system design, modeling,
    hardware (partially mitigated via LBNL MoU)
  • Cryogenics delivery system engineering for the
    Meson Linac cave
  • Beam instrumentation design (partially mitigated
    by BNL MoU)

33
Summary
  • Considerable activity is now underway on
    component design, procurement, and facilities to
    support planned RD
  • It will be an exciting next 12 months to bring
    325 MHz klystron and RFQ on-line and to
    accelerate beam in the Meson Building
  • Key areas, presently lacking effort necessary to
    maintaining desired schedule, are identified

34
Backup Slides
35
Meson Building Floor Plan
36
Modified, 05/25, Trans. envelopes
Write a Comment
User Comments (0)
About PowerShow.com