Title: High Intensity Neutrino Source HINS Linac FrontEnd R
1High Intensity Neutrino SourceHINS Linac
Front-End RD ---Systems Integration, Beam
Diagnostics Needs, and Meson Lab Setup
2Motivation and Timeline
- Motivation
- Test key un-proven technologies important to the
low-energy front-end (ßlt0.4) section of the
proposed 8 GeV Superconducting H- Linac - Timeline
- Accomplish the RD necessary to establish
technical credibility and cost basis for the
Linac front-end by 2010 - Funding Resources
- 10M in FY06 (FNAL and collaborators SWF and
MS) - similar funding projected for FY07 and 08 until
recent rumblings from DOE (within the last 4
weeks)
3RD Objectives
- Demonstrate high power RF distribution and 4.5
millisecond pulse operation of multiple cavities
from a single klystron - Demonstrate device and system performance of high
power vector (IQM) modulators for amplitude and
phase control of multiple cavities - Measure axially-symmetric beam performance with
RT-CH (room temperature, crossbar H-type) spoke
resonator cavities and SC solenoid focusing in
the RT Linac - Demonstrate low transition energy (10 MeV) to and
application of superconducting spoke resonator
accelerating structures - Demonstrate high-speed (nanosecond) beam
chopping at 2.5 MeV - Demonstrate performance of this Linac concept and
resulting beam quality to 90 MeV
4RD Plan
- Install and commission 2.5 MW, 325 MHz klystron
system - Equip and operate a 325 MHz high power RF
component test facility - Fabricate, install, and operate a test cryostat
for 325 MHz SC spoke cavities - Construct and test key components of the
low-energy Linac concept - Assemble the 10 MeV RT Linac, operate with beam,
and verify performance - Install 325 MHz SC spoke resonator cryomodules
and operate with beam up to 90 MeV - This all adds up to building a first-of-its-kind
superconducting 90 MeV H- linac
5Major Activity Areas in Meson
- 325 MHz Klystron and Modulator Area
- 325 MHz RF Component Test Facility
- Cavity Test Cave (RT-CH and superconducting
cavities) - Ion Source, RFQ, and 2.5 MeV Absorber Area
- 90 MeV Accelerator and Beam Absorber Cave
6Meson Building Floor Plan
Cavity Test Cave
RF Component Test Facility
Klystron and Modulator Area
90 MeV Linac
Ion Source and RFQ Area
200 ft.
7View Into Klystron/Modulator Area (early May)
8325 MHz 2.5MW Klystron (early May)
94.5 msec Klystron Pulse Transformer (early May)
10325 MHz Waveguide Circulator (early May)
11View Into Klystron/Modulator Area (June 9)
12View Into Klystron/Modulator Area (June 9)
13Klystron and Waveguide (June 16)
14Modulator Capacitor Cabinet (front) (June 28)
15Modulator Switch Cabinet (back) (June 28)
16Modulator Switch Cabinet (front) (June 28)
17View Down (Future) Linac Beam Line
18Layout Through Second ß.4 Cryostat
Ion Source
RFQ
MEBT
Room Temperature 16-Cavity, 16 SC Solenoid Section
2.5 MeV
50 KeV
10 MeV
Two ?0.2 SSR 9-Cavity, 9-Solenoid Cryostats
20 MeV
30 MeV
Two ?0.4 SSR 11-Cavity, 6-Solenoid Cryostats
90 MeV
60 MeV
19Meson Linac Cave Cross-section
20Beam Diagnostics - Minimum on-line (P. Ostroumov)
- Current transformers (CT)
- Beam phase pick-up necessary to control energy
stability during the operation - Initial tune-up of the cavity field and phase
- Beam profile wire scanners (or/and laser
scanners) - Beam loss monitors about 20 distribute along
the linac - Inter-cryostat space should include
- CT
- BPM, includes phase pick-up
- Wire scanner
21Off-line (temporary installation)
- The temporary diagnostics station is desirable to
use at the end of the following linac sections - RFQMEBT, RT section, SSR1, SSR2 - will be
permanent place - Diagnostics station includes (minimum set)
- 1 solenoid (or 3 quads, triplet)
- 2 steering magnets
- 2 BPMs, includes phase pick-up
- 3 profile monitors
- 2 current transformers
- Beam dump water cooled
- Energy degrader
- Faraday cup
- Fast Faraday cup
- CCD camera with the quartz foil
- Maximum set, extend for
- Emittance station slit-collector copy from
SNS - Bunch length custom design
22Machine and Beam Parameters
- Two operating modes providing 1.56E14 ppp
- 3 millisecond 8.6 mAaverage beam pulse at 2.5
Hz - 1 millisecond 26 mAaverage beam pulse at 10 Hz
- Bunch Frequency 325 MHz
- (1/4 of ILC 1.3 GHz)
- Chopped in MEBT (2.5MeV) at 53 MHz ( 2 of 6
bunches missing) and at 89 KHz (1.6 microsecond
gap) therefore peak beam current is 1.5 times
average current stated above - Beam tube aperture
- 20mm bore radius through focusing solenoids
15mm? through warm RF cavities
23Baseline - 05/15/06 Trans. envelopes
24MEBT June 12, 2006 Dimensions OK
Increase this space and use it for the steering
magnet
25CH-SSR1
Strip-line BPM
This space can be increased up to 204 mm
26So What is Needed Now?
- Beam current transformer electromechanical
designs - BPM pick-up electromechanical design(s) for RT
and SSR Linac sections - Scanning wire electromechanical designs
- Laser wire design
- Beam phase monitor system design
- Beam energy analysis system
- Beam bunch length monitor?
- Electronics for all above
27SNS Diagnostics plate
28BPM (SNS)
29Meson Schedule 2006
- Short mock Linac cave section available
- May 2006 ?
- Klystron modulator completion
- July 2006 (late July)
- 325 MHz RF power system commissioning
- July 2006 (early August)
- 325 MHz component testing in RF test area
- Starting August 2006
- 325 MHz RT cavity power testing in cavity test
cave - September 2006
- Superconducting cavity test cryostat installation
- October 2006
- Ion Source installation in Meson
- November 2006
30Meson Schedule 2007
- RFQ (now in procurement) delivery and power
testing - January 2007
- RT cavity and coupler testing
- Starting February 2007
- 2.5 MeV beam tests
- Beginning February 2007
- First SC spoke resonator power tests in test
cryostat - April 2007
- Linac cave construction and utilities
installation - May 2007
- Demonstration of multiple cavity RF distribution
and independent amplitude phase control - July 2007
- Beam accelerated through first N RT cavities
- September 2007 (optimistic)
31Meson Schedule 2008
- Full 10 MeV RT linac installed
- April 2008
- RD beam operations at 10 MeV
- Starting May 2008
- First SC spoke resonator cryomodule installation
- October 2008
- Tests of RT SC cavity RF distribution and
independent amplitude phase control - November 2008
- Beam through first SC spoke cryomodule
- December 2008 (optimistic)
32Manpower Resources
- A Lab-Wide effort is required and now being
applied - Beam line components are designed and procured by
Technical Division - RF and conventional power source components and
systems integration and operation are the
responsibility of the Accelerator Division - Particle Physics Division is supplying manpower
for utilities and infrastructure installation in
the Meson building - Laboratory Safety Section and Accelerator
Division Safety Department are already at this
early stage actively involved - Key technical systems now lacking required
attention - RF power distribution system (tightly coupled
with cavity design status and power requirements) - Low level RF systems system design, modeling,
hardware (partially mitigated via LBNL MoU) - Cryogenics delivery system engineering for the
Meson Linac cave - Beam instrumentation design (partially mitigated
by BNL MoU)
33Summary
- Considerable activity is now underway on
component design, procurement, and facilities to
support planned RD - It will be an exciting next 12 months to bring
325 MHz klystron and RFQ on-line and to
accelerate beam in the Meson Building - Key areas, presently lacking effort necessary to
maintaining desired schedule, are identified
34Backup Slides
35Meson Building Floor Plan
36Modified, 05/25, Trans. envelopes