Title: Dalian Water Supply Project
1Dalian Water Supply Project
- February 26, 2004
- Alyona Dubrovina
- Jim Horiuchi
- Henning Hummervoll
2Context
Background Project Description Analysis
Conclusion
- China, 1994
- Asian Development Bank considers 160 M
investment in a water supply project
317 Infant mortality rate Cambodia
4Aids spreading in Africa
575 million living below poverty line in China
6Problem definition
- Which project should be financed?
7Agenda
- Background
- Project description
- Analysis
- Conclusion
8China
Background Project Description Analysis
Conclusion
- 1.17 billion people (1994)
- Steady reforms since 1978
- GDP growth of 9 per annum
- Infrastructure bottlenecks
- Tight political controls
- Pressures for reforms
- Increased trade
- WTO
9Dalian Municipality
Background Project Description Analysis
Conclusion
- Important seaport
- Technology Development Area
- Growing population
- 4.7 million in 1997 growing at 3 pa
- Water supply shortage
- Lowest average supply
- Static water tariff level 1952-1992
10Project description
Background Project Description Analysis
Conclusion
11Scope of Project
Background Project Description Analysis
Conclusion
- Increase water supply
- 220 lpcd per person
- 2.2 million residents, farming and industry
- Project goals
- Alleviate water shortage
- Improve public health
- Support regional growth
- Increase water treatment capacity
12Project Mechanism
Background Project Description Analysis
Conclusion
- Transport water
- Biliuhe Reservoir ? Dalian (160 km or 100 miles)
- Total project cost 379.7 million
- Project components
- Water conveyor (68 km)
- Two pipelines (94 km and 79 km)
- Two new pumping stations
- Water treatment plant near Dalian
- Distribution lines storage tanks
- Project completion by September of 1998
13Project Location
Background Project Description Analysis
Conclusion
14Stakeholders
Background Project Description Analysis
Conclusion
- Executing Agencies
- Dalian Water Supply Company
- Northern Water Supply Company
- Debt holders
- Dalian Municipality Government
- Asian Development Bank
- China Construction Bank and other commercial
banks - Other stakeholders
- Dalian population, farming community and
industries
15Financial Structure Use of Cash
Background Project Description Analysis
Conclusionv
- Total project cost 379.9 million
16Financial Structure
Background Project Description Analysis
Conclusion
- Sources of Cash
- Loans
- ADB
- Local commercial banks
- (China Construction Bank)
- PRC government
- Ministry of Water Resources
- State Planning Commission
- Gant from PRC government
- Dalian municipalitys own resources
17Financial Structure (continued)
Background Project Description Analysis
Conclusion
- Effectively all-PRC funding other than ADB Loan
- Enhancement of credibility
Local Commercial Banks
ADB
Debt Service
- Execution Agents
- Dalian Water Supply Company
- Northern Water Supply Company
Disbursement
Debt Service
- Ministry of Water Resources
- State Planning Commission
Disbursement
Loan relent under separate loan agreements
Dalian Municipal Government
Grant
Debt Service
Central Government
Project Execution Management
18ADB Loan Terms Conditions
Background Project Description Analysis
Conclusion
- Summary of terms and conditions
19Analysis
20Investment Criteria
Background Project Description Analysis
Conclusion
21Project cost of capital
Background Project Description Analysis
Conclusion
- Cost of debt 8.51
- US 30-year treasury 7.37
- 1994 Chinese government bonds spread 1.14
- Risk mitigation factors (discussed later)
- Cost of equity 15.82
- Market risk premium 3.5
- Sovereign risk premium 8.51
- Equity beta 0.3
- Risk mitigation factors (discussed later)
- WACC 10.5
- Capital structure 53 equity, 47 debt
22Project risk analysis
Background Project Description Analysis
Conclusion
- Dependence on completion of environmental
protection and wastewater programs - Agency risks associated with large project and no
direct foreign involvement - Availability of inputs
- Size and sustainability of reservoir
- Stability and cost of power supply
- Dependence on tariff increases for profitability
- Currency risk
- Possible floating of Yuan could result in
devaluation and difficulties in repayment of
loans in USD as income is in Yuan
23Results of financial analysis
Background Project Description Analysis
Conclusion
- Negative NPV (474.9)M
- IRR 8.9
- Growth rate and discount rate sensitivity
- Base case Growth rate 9, discount rate 10.5
Project most likely not attractive to private
investors
24Sensitivity Analysis Key Variables
Background Project Description Analysis
Conclusion
- Key variables
- Water Sales
- Water Tariff
- Raw water expense
- Power expense
25Sensitivity analysis NPV
Background Project Description Analysis
Conclusion
- Expected NPV (723)
- Less than 2 probability of positive NPV
26Sensitivity analysis IRR
Background Project Description Analysis
Conclusion
Expected IRR 7.93
27ADBs perspective
- Returns to ADB equal interest rate
- Variable interest rate exceeding cost of capital
- High probability of default on debt payments 83
- ADBs debt is expected to be honored at the
expense of other debt holders
28Alternative sources of financing
Background Project Description Analysis
Conclusion
- Corporate finance
- Municipality owned operating agencies
inefficiencies and agency problems - Illiquid assets
- Private sources Highly unlikely
- Limited recourse project finance
- Elimination of agency problem
- Local and state government resistance
- Not a Greenfield development
- More expensive
- Private sources Highly unlikely
29Economic analysis
Background Project Description Analysis
Conclusion
- Benefits High
- Increase GDP, productivity, foreign investment
- Improve public health
- Eliminate inefficiencies in water sector
- Costs Low
- Wastewater treatment
- Additional subsidy
- Opportunity costs
- Risks Low
- In case of operational success economic benefits
will be achieved
30Conclusion
Background Project Description Analysis
Conclusion
- Financial analysis should be enhanced by economic
analysis - Unconvincing financial projections
- Strong economic benefits and low risks
- We recommend to invest in the project
31What happened
Background Project Description Analysis
Conclusion
- Loan approved for 160 million
- Reappraisal in 1997 extended scope
- 2 subprojects implemented to utilize northern
conveyor - Economic internal rate of return estimated at
13.4 - Projected completed on time
- Knowledge and project skill transfer deemed
successful - Opened up for 8 more water supply and wastewater
management projects including BOT and
international investments
32