Title: Lband Test Stand in Endstation B


1
L-band Test Stand in End-station B
Status update 06/09/05
  • Modulator Arrived at SLAC, installation
    started
  • Klystron 5 MW long pulse, bidding process
    finished, ready to order TH2104U and
    Solenoid arrived this Tuesday Boeing solenoid,
    donation process started
  • Circulator/WG Ready to order, we will buy 2
    from different vendors Layout of system
    ongoing, WG parts ordered
  • L-band structure Design under way in Juwens
    group
  • Controls/LLRF Design reviewed, Work started,
    Amplifier ordered

2
L-band Test Stand in End-station B
New coupler test stand planed
  • We plan now to include a warm coupler test area
    to
  • process couplers for SMTF at Fermi
  • conduct RD on alternative coupler concepts
  • study the limitations of couplers (major
    goal reduce processing time)

3
L-band Test Stand in End-station B
SNS modulator and controls
4
L-band Test Stand in End-station B
TH2104U arrived
5
L-band Test Stand in End-station B
Whats next ?
  • Install modulator and run into load as received
  • Modify modulator to match the klystron
  • Install klystron
  • Build interlock system, LLRF and control system