Procurement and Selection of DesignBuild Entities - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

Procurement and Selection of DesignBuild Entities

Description:

Source Selection with formal review ( No Discussion) ... dedicated to the project; and (6) financial solidity and management skills. ... – PowerPoint PPT presentation

Number of Views:88
Avg rating:3.0/5.0
Slides: 34
Provided by: itc125
Category:

less

Transcript and Presenter's Notes

Title: Procurement and Selection of DesignBuild Entities


1
Procurement and Selection of Design-Build
Entities
CEM 525 PROJECT DELIVERY SYSTEMS By
MOHAMMED JALALUDDIN LECTURER CONSTRUCTION
ENGINEERING MANAGEMENT DEPT
2
Presentation Outline
  • The Difference between Project Delivery and
    Procurement
  • Procurement Options for Implementing Project
    Delivery
  • Sole-Source Selection
  • Qualification Based Selection (QBS)
  • Negotiated Source Selection with Discussions
  • Source Selection with formal review ( No
    Discussion)
  • Fixed Budget /best technical response or design
  • Weighted Criteria
  • Adjusted Low Bid
  • Low First cost
  • Other Variations
  • Equivalent Design/low bid
  • Meets criteria/ low bid

3
Objectives of Class
  • To differentiate between project delivery system
    and procurement options and recognize the key
    terms in design- build delivery system
  • To describe the various options in
    procurement/selection of design-build
    contractors/design builders

4
Alphabet Soup of Design Build
Technical Leveling
Procurement
D/B
DATA CENTER TOTAL 240 X 400 105,000GSF
LOBBY
SECURITY
DATA FLOOR AREA 40 X 60 BAYS TYPICAL BAYS
MEN
Two step
WOMEN
Best Value
MAIL PRINT AREA
QBS
NOC
DBOF
Sole Source
Design Criteria
OFFICE AREA
Performance specifications
UPS/ BATTERY ROOMS
Negotiated
STAGING
STORAGE
UTILITY SUPPORT AREA 15,000SF
Meets Criteria/Low Bid
RFP
MAINTENANCE
LOADING DOCK
ELECTRICAL
SWITCHGEAR
CHILLER PLANT
GENERATORS
Low Bid
RFQ
One Step
PRECAST SREEN WALL
COOLING TOWERS
UTILITY TRANSFORMERS/ SWITCHING CUBICLES
Adjusted Low Bid
Weighted Bid
Fixed Budget/Best Design
5
Procurement/Selection Options
6
Project Delivery System versus Procurement
  • Project Delivery system is defined as an approach
    to select project team.
  • Project Delivery method is an organizational
    concept which assigns specific responsibilities
    and authorities to people and organizations and
    which defines relationship of the various
    elements in construction of a project.
  • It is the first allocation of base
    responsibilities between the owner, design
    professional and contractor. Thus, the project
    delivery system is the foundation on which all
    subsequent negotiations will be based.
  • Procurement represents the purchasing steps that
    the owner or its representative must take to gain
    the services required under the chosen project
    delivery system.

7
Project Delivery System versus Procurement
  • For example, the Ministry of Education wants to
    build a new University in Riyadh, and the
    Ministry board considers three project delivery
    methodologies design-bid-build, CM (construction
    management) at risk, and design-build.
  • For the project, the officials decide to use
    traditional design-bid-build as a project
    delivery system.
  • To implement the delivery system, officials must
    purchase design services separately and
    construction services separately.
  • Under most state law, for contracts that are
    primarily professional design services in nature,
    the state uses a qualifications-based selection
    procedure Note that qualifications-based
    selection (QBS using an RFQ) is not a project
    delivery methodology, but a procurement/purchasing
    methodology
  • To obtain construction services under traditional
    design-bid-build, the Ministry is then required
    to purchase construction services via
    low-first-cost bids from construction contractors
    who meet the bonding requirements.

8
Sole Source Selection
  • Private owners who have established long-term
    relationships with services providers often use
    sole-source or direct selection in the
    procurement of design and construction services.
  • Using selection factors such as past performance,
    reputation, technical and managerial
    qualifications, and long-standing or prior
    association, a private owner has the latitude to
    bestow contracts on the firm or individual of
    choice.
  • Public owners may also employ sole-source
    selection when there are no other potential
    offerors or bidders
  • or when an emergency (such as an earthquake,
    hurricane, or civil disturbance that may endanger
    the health and safety of the public) allows the
    waiver of strict procurement rules.
  • The purchasing vehicle or format used for
    sole-source selection is a direct purchase
    request or sole-source contract agreement.

9
Qualification Based Selection (QBS)
  • In response to the owner's RFQ, entities or
    individuals submit their qualifications
    statements for review.
  • The owner will review the qualifications
    statements and rank the firms on the basis of
    their past performance, technical competence,
    capacity to accomplish the work, and geographic
    location (if applicable).
  • Usually, previous experience or specialized
    experience in the type of project named in the
    solicitation is critical to being ranked as one
    of the top three "most qualified."
  • During the review, the owner will rank the firms
    according to their qualifications and will then
    begin negotiations with the number 1 (most
    qualified) ranked offeror to reach a "fair and
    reasonable" price for the services required.

10
Qualification Based Selection (QBS) Contd
  • If the owner is unable to reach a satisfactory
    agreement with the most qualified offeror, it
    will cease discussions with number 1 and begin
    negotiating with the second most qualified firm.
  • In public projects, agencies normally identify a
    set of criteria in the project announcement
    against which each qualifications statement will
    be evaluated.
  • For design-build projects, a selection scoring
    matrix may include (1) past experience with
    integrated services delivery (2) past experience
    with other members of the team (3) approach to
    problem solving, creative strategies, and
    innovation (4) quality assurance planning and
    management (5) key personnel dedicated to the
    project and (6) financial solidity and
    management skills.
  • The purchasing vehicles or formats used for
    qualifications-based selection are RFQ and
    qualifications statements. Firms or individuals
    who respond to an RFQ are called offerors.

11
(No Transcript)
12

13
Negotiated Source Selection with Discussions
  • Generally, negotiated source selection with
    bilateral discussions involves a procedure of
    inviting proposals from design build contractors,
    permits "bargaining," and usually affords an
    opportunity to revise offers before the award of
    a contract.
  • Bargaining (in the sense of discussion,
    persuasion, alteration of initial assumptions and
    positions, and give-and-take) may apply to
    technical requirements, schedule, price, type of
    contract and its provisions, and other
    project-related issues.
  • Discussions with proposers deemed to be within
    "the competitive range" are held, and those
    within the competitive range may submit best and
    final offers.
  • The final proposal packages are considered, and
    award is made to the proposer who is providing
    the "best value" to the government.
  • Owners who procure design and construction
    services via negotiated source selection would
    use a request for proposals (RFPs). Respondents
    to an RFP are known as offerors or proposers.

14
Source selection with formal review (no
discussions)
  • Owners may award contracts on the basis of the
    most favorable initial proposal without
    discussions.
  • The use of discussions is advantageous for
    projects that have little definition however,
    the owner may not have the time or inclination to
    conduct protracted negotiations about the scope
    and terms of the contract.
  • In these situations, the owner will solicit
    proposals on the basis of information that is
    contained within or appended to the RFP Relying
    on the guidance contained within the RFP, plus
    the factors for evaluation of the proposals, the
    team will generate their response documents.
  • Award is made (without discussions) to the
    proposer submitting what is deemed to be the most
    advantageous offer to the owner.
  • Implementation of negotiated source selection
    with unilateral evaluation and selection of the
    successful proposal by the owner requires the use
    of an RFP

15
Fixed Budget/ Best Design
  • Adoption of the fixed-price/best-design approach
    to procuring integrated design and construction
    services is growing rapidly.
  • This procurement method relies on a contract
    price that is fixed by the owner and stated
    within the RFP Since the budget is set prior to
    the RFP announcement, proposers work to develop
    qualitative and technical proposals only, under
    the stipulation that all price offers are equal.
  • Fixed budget/best design is regarded as a
    competitive procedure wherein the proposers are
    competing in terms of scope and quality, rather
    than cost.
  • The proposer that can fill the owner's shopping
    bag with the most value through their technical
    submission or concept design will become the
    awardee.
  • Fixed-budget/best-design procurement is
    implemented through an RFP

16
Weighted Criteria
  • The solicitation for proposals will include a
    requirement for the submission of a separate
    qualitative proposal and a price proposal from
    each offeror.
  • The qualitative proposal contains technical
    information from the design-build team that will
    be rated on the basis of points, frequently with
    the use of a matrix that scores each proposer's
    response to each of the evaluation factors.
  • After consideration of each of the qualitative
    proposals (a process that may include oral
    presentations by the teams), the price proposals
    will be opened
  • Maximum price points are assigned to the lowest
    dollar bid, and all others are scaled inversely
    proportional to that amount. The firm with the
    highest total points will gain the award.
  • Weighted-criteria procurement is usually
    implemented using an RFP

17
(No Transcript)
18
Adjusted Low Bid
  • Purchasing of design-build services through the
    use of adjusted low bid is similar to the
    approach used under weighted criteria.
  • Following the receipt of qualitative proposals
    and fixed-price envelopes, the qualitative
    portion is scored and totaled on a scale of 1 to
    100, which is expressed as a decimal (e.g., a
    score of 92 is shown as 0.92).
  • Price submissions are then opened, and each price
    is divided by its respective qualitative score to
    yield an adjusted price.
  • The adjusted low-bid amount is used to determine
    the successful proposer however, the actual
    price submitted in the original proposal is used
    on the contract.
  • Because the adjusted low-bid process includes
    submission of a technical portion along with a
    price, the procedure relies on an RFP format for
    implementation.

19
(No Transcript)
20
Equivalent design/ low bid
  • Under equivalent design/ low bid, the proposer
    responds to the owner's RFP with a technical
    submission and price submission.
  • After review and critique by the owner and its
    consultant, the proposer is given a deadline to
    respond with specified design changes and
    corresponding price amendments (either additive
    or deductive) in order to arrive at a group of
    proposals that are technically equivalent (this
    is sometimes referred to as technical leveling).
  • Revised designs and pricing are then evaluated
    by the owner using both base cost and amendments.
    Award is normally made with overwhelming emphasis
    on costs, because the initial review process
    should have created nearly equivalent designs.

21
Meets criteria/ low bid
  • A related purchasing variation is known as meets
    criteria/ low bid.
  • This method of evaluation most closely resembles
    the traditional bid process except that the
    drawings and specifications are not absolutely
    complete
  • Very specific outline or conceptual designs are
    issued as a part of the design criteria package.
  • Proposals are solicited from qualified firms. The
    proposals are evaluated, deemed to meet the base
    criteria, and award is made to the low bidder.
  • The proposals from design build teams are
    evaluated and deemed to meet the base criteria,
    and award is made to the low-cost bidder.

22
Low First Cost
  • This method of purchasing, using the single
    attribute of price, is applicable
  • Owners who employ low first-cost bidding to
    purchase design-build services are sending a
    signal to the marketplace that cost is their
    overriding criterion, and that the creative value
    of a unique proposal (solution to their facility
    problem) is not wanted or desired.
  • The bidder's role amounts to completing the
    partial design and constructing the facility.
  • Many design-build practitioners are uncomfortable
    with bidding under these conditions, because the
    low-bid process eliminates the creativity and
    innovation of the team
  • Low first-cost procurement is usually applied by
    state or local governmental agencies who, under
    anachronistic procurement laws, must use bidding
    for contracts with a majority of the dollars
    destined for construction costs.
  • The format or vehicle used to implement low
    first-cost procurement is the invitation for bids
    (IFBs)..

23
Alphabet Soup of Design Build
Technical Leveling
Procurement
D/B
DATA CENTER TOTAL 240 X 400 105,000GSF
LOBBY
SECURITY
DATA FLOOR AREA 40 X 60 BAYS TYPICAL BAYS
MEN
Two step
WOMEN
Best Value
MAIL PRINT AREA
QBS
NOC
DBOF
Sole Source
Design Criteria
OFFICE AREA
Performance specifications
UPS/ BATTERY ROOMS
Negotiated
STAGING
STORAGE
UTILITY SUPPORT AREA 15,000SF
Meets Criteria/Low Bid
RFP
MAINTENANCE
LOADING DOCK
ELECTRICAL
SWITCHGEAR
CHILLER PLANT
GENERATORS
Low Bid
RFQ
One Step
PRECAST SREEN WALL
COOLING TOWERS
UTILITY TRANSFORMERS/ SWITCHING CUBICLES
Adjusted Low Bid
Weighted Bid
Fixed Budget/Best Design
24
BEST VALUE
  • Also known as Greatest Value,
  • A selection process in which proposals contain
    both price and qualitative components,
  • Award is based upon a combination of price and
    qualitative considerations. Qualitative can be
    further subdivided as to technical design
    and/or Management plan. etc

25
TWO PHASE SELECTIONPROCESS
  • The most popular method of design-build
    procurement is Two phase selection
  • AIA, AGC, DBIA all recommend Two-phase process
  • Two-phase selection refers to a design-builder
    selection process where the first
  • phase involves shortlisting of candidates on the
    basis of the qualification statements they supply
    ( 3-5 )
  • And the second phase involves final selection on
    the basis of technical and price proposals, etc.
    from the shortlisted offerors.

26
Stipend
  • Stipend (or Honorarium) A stated amount
    sometimes paid to offerors in consideration for
    the cost of preparing a Design-Build proposal.
    The stipend or honorarium would be paid to
    unsuccessful offerors.

27
Request for Qualifications (RFQ)
  • Request for Qualifications (RFQ) The document
    issued by the Owner prior to an RFP that
    typically
  • intended to procure Qualification Statements from
    potential design-builder offerors that are then
    evaluated and ranked based on the qualifications.
  • It also describes the project in enough detail to
    let potential proposers determine if they wish to
    compete and forms the basis for requesting
    Qualifications Submissions in a two phase or
    prequalification process.

28
Request for Proposal (RFP)
  • Request for proposal (RFP) the document that
    totally describes the procurement process, forms
    the basis for proposals, and ultimately becomes a
    potential element in the contract.
  • Requests for proposals contain information about
    the size, scope, and complexity of the project,
    the clients requirements and budgetary
    considerations,
  • selection criteria, and the desired form and
    content of the proposals

29
TECHINCAL LEVELLING
  • Technical leveling a part of the Equivalent
    Design Low bid selection process
  • In which the technical aspects of competing
    design-build proposals are critiqued and
  • Offerors respond with adjustments to create
    technical equivalency across all proposals.

30
Adjusted Low Bid
  • Adjusted Low Bid
  • A form of best value selection in which
    qualitative aspects are scored on a 0 to 100
    scale expressed as a decimal
  • bid price is then divided by qualitative score
    to yield an adjusted bid or cost per quality
    point.
  • Award is made to offeror with the lowest
    adjusted bid.

31
Fixed Price/Best Design
  • A form of best value selection in which contract
    price is established by the Owner and stated in
    the RFP.
  • Design proposals and management plan are
    evaluated and scored, with award going to the
    firm offering the best qualitative proposal for
    the established price.

32
Design competition
  • Design competition a method of procuring
    design-build services in which design-build teams
    submit detailed design proposals to the client,
  • who then selects a team based on the ability of
    their proposal to meet the requirements of the
    project.
  • The "winner" of the competition is awarded the
    contract to complete the design and construct the
    project.

33
Design Criteria Professional
  • Design Criteria Professional An individual
    (typically a registered professional Architect or
    Engineer) who develops the facility program,
    design criteria, outline performance
    specification and other project specific material
    to provide to potential design-build offerors.
    The design criteria professional may be in-house
    or may be an outside consultant (see Owners
    Consultant).
  • A consultant or consulting firm that may be
    employed by an Owner (e.g. an Owner who may not
    have sufficient in-house expertise to acquire
    design-builder services) to assist in organizing
    and administering the design-build selection
    process, and for other consulting services such
    as review of submissions for compliance with the
    RFP. Is often the design criteria professional
    who develops the facility program, performance
    specifications and other RFP components.
Write a Comment
User Comments (0)
About PowerShow.com