Chapter 4 Inventory Control Subject to Deterministic Demand

1 / 45
About This Presentation
Title:

Chapter 4 Inventory Control Subject to Deterministic Demand

Description:

finished inventory held in anticipation of a rise in their ... c) Breakage Spoilage and Deterioration (1 %) d) Opportunity Cost of alternative investment (18 ... – PowerPoint PPT presentation

Number of Views:654
Avg rating:5.0/5.0

less

Transcript and Presenter's Notes

Title: Chapter 4 Inventory Control Subject to Deterministic Demand


1
Chapter 4Inventory Control Subject to
Deterministic Demand
2
Operations Management
  • Inventory control
  • Scheduling
  • Capacity planning
  • Forecasting
  • Quality control
  • Equipment maintenance
  • Finished product
  • Work-In-Progress
  • Components
  • Rough materials

3
Reasons for Holding Inventories
  • Economies of Scale
  • cheaper to produce/order in large batches
  • Uncertainties
  • demand lead times delivery of supply
  • Speculation
  • finished inventory held in anticipation of a rise
    in their value or costs
  • Smoothing
  • irregularities of demand pattern
  • Transportation
  • inventory in transit from one location to other
  • Costs of Maintaining Control System
  • can be cheaper to order once a year, than
    continuously monitor orders and deliveries

4
Relevant Costs
  • Holding Costs - Costs proportional to the
    quantity of inventory held. Includes, for
    example
  • a) Physical Cost of Space (3 )
  • b) Taxes and Insurance (2
    )
  • c) Breakage Spoilage and Deterioration
    (1 )
  • d) Opportunity Cost of alternative investment
    (18 )
  • (Total 24 )

5
Relevant Costs (continued)
  • Penalty or Shortage Costs. Including
  • Loss of revenue for lost demand
  • Costs of book keeping for backordered demands
  • Loss of goodwill for being unable to satisfy
    demands when they occur.
  • Generally assume cost is proportional to number
    of units of excess demand.

6
Relevant Costs (continued)
  • Ordering Cost (or Production Cost)
  • Includes both fixed and variable components
  • K

7
Example MedEquip dilemma Harris 1913
  • Small manufacturer of operating-room monitoring
    and diagnostic equipment
  • Production process mounting electronic
    components in standard metal racks
  • The racks are purchased from a local metalworking
    shop, which must set up its equipment (presses,
    machining stations, welding stations) every time
    it produces run of racks ? setup cost
  • As result , the metalworking shop does not want
    to produce small batches each time, but MedEquip
    does not want to buy in excessive quantities ?
    inventory cost
  • How many parts to make/order at once?

8
Inventory Levels for the EOQ Model
9
The EOQ Model Assumptions
  • Production is instantaneous
  • There is no capacity constraint, and entire lot
    is produced simultaneously
  • Delivery is immediate
  • There is no time lag between production and
    availability to satisfy demand
  • Demand is deterministic
  • There is no uncertainty about the quantity or
    timing of demand
  • Demand is constant over time
  • It can be presented as a straight line, so that
    if annual demand is 365 units, this translates to
    a daily demand of one unit
  • A production run incurs a fixed setup cost
  • Regardless of the size of the lot or the status
    of the factory, the setup cost is the same
  • Products can be analyzed individually
  • Either there is only a single product or there
    are no interactions (e.g. shared equipment)
    between products

10
Inventory Levels for the EOQ Model
11
The EOQ Model Notation
  • D ? is the demand rate (in units per year)
  • c unit production cost, not counting setup or
    inventory costs (in dollars per unit)
  • K setup costs (per placed order) in dollars
  • h holding cost (in dollars per unit per year),
    if the holding cost consists entirely of interest
    on money tied up in inventory,
  • h ic, where i is an annual interest rate
  • Q lot size (order size) in units
  • T time between orders (cycle length)
  • G(Q) average annual cost

12
Relationships
  • Ordering Costs (Order amount Q)
  • C(Q) K cQ
  • Holding Cost
  • h Ic (Interest Rate)(Cost of Inv.)
  • Average Inventory Size?
  • Under constant demand Q/2
  • Time Between Orders
  • l Q/T
  • T Q/l

Rate of consumption l
Q
T
13
Total Costs
  • What is the average annual cost?
  • G(Q) average order cost average holding cost

14
Total Costs
  • What is the average annual cost?

15
The Average Annual Cost Function G(Q)
16
Minimize Annual Costs
  • Take the derivative of G(Q)
  • Is this a minimum?
  • EOQ

YES!
17
Properties of the EOQ Solution
  • This formula is well-known economic order
    quantity, is also known as economic lot size
  • This is a tradeoff between lot size and inventory
  • Garbage in, garbage out - usefulness of the
    EOQ formula for computational purposes depends on
    the realism of input data
  • Estimating setup cost is not easily reduced to a
    single invariant cost K

18
Example
  • Uvic requires 3600 gallons of paint annually for
    scheduled maintenance of buildings. Cost of
    placing an order is 16 and the interest rate
    (annual) is 25. Price of paint is 8 per
    gallon.
  • How much paint should be ordered, and how often?

240
Q




days/year)

working
(250



years

07
.
T
l
3600
days

18



days

working
17.5


19
Order Point for the EOQ Model
  • Does it matter if
  • t lt T or t gt T ?
  • Keep track of
  • time left to zero inventory or set
    automatic reorder at a particular
  • inventory level, R.
  • R ?t, if t lt T
  • R ?MOD(t/T),
  • if t gt T

Assumption Delivery is immediate There is no
time lag between production and availability to
satisfy demand Relax this assumption! Let the
order lead time to be equal to t
20
Sensitivity Analysis
  • Let G(Q) be the average annual holding and set-up
    cost function given by

and let G be the optimal average annual holding
and setup cost. Then it can be shown that
Cost penalties are quite small
21
Finite Replenishment Rate Economic
Production Quantity (EPQ)
  • Assumptions for EOQ
  • Production is instantaneous
  • There is no capacity constraint, and entire lot
    is produced simultaneously
  • Delivery is immediate
  • There is no time lag between production and
    availability to satisfy demand
  • Example
  • Parts produced at the same factory
  • production rate is P (P gt ?),
  • arriving continuously.

22
Inventory Levels for Finite Production Rate Model
23
The EPQ Model Notation
  • D ? is the demand rate (in units per year)
  • c unit production cost, not counting setup or
    inventory costs (in dollars per unit)
  • K setup costs (per placed order) in dollars
  • h holding cost (in dollars per unit per year),
    if the holding cost consists entirely of
    interest on money tied up in inventory, hic,
    where i is an annual interest rate
  • Q size of each production run (order) in units
  • T time between initiation of orders arrival
    (cycle length)
  • T1 production (replenishment) time
  • T2 downtime
  • H maximum on-hand inventory
  • G(Q) average annual setup holding cost

24
The EPQ Model Formula
25
Quantity Discount Models
  • One of the most severe assumptions the unit
    variable cost c did not depend on the
    replenishment quantity
  • In practice quantity discounts exist based on
    the purchase price or transportation costs take
    advantage of these can result in substantial
    savings
  • All Units Discounts the discount is applied to
    ALL of the units in the order. Gives rise to an
    order cost function such as that pictured in
    Figure 4-9 in Ch. 4.7
  • Incremental Discounts the discount is applied
    only to the number of units above the breakpoint.
    Gives rise to an order cost function such as that
    pictured in Figure 4-10

26
All-Units Discount Order Cost Function
27
The Average Annual Cost Function G(Q)
28
All-Units Discount Average Annual Cost Function
G0(Q)
G1(Q)
G2(Q)
29
Incremental Discount Order Cost Function
30
Average Annual Cost Function for Incremental
Discount Schedule
31
Properties of the Optimal Solutions
  • For all units discounts, the optimal will occur
    at the minimum point of one of the cost curves or
    at a discontinuity point
  • One compares the cost at the largest realizable
    EOQ and all of the breakpoints succeeding it
  • For incremental discounts, the optimal will
    always occur at a realizable EOQ value.
  • Compare costs at all realizable EOQs.

32
Example
  • Supplier of paint to the maintenance department
    has announced new pricing
  • 8 per gallon if order is lt 300 gallons
  • 6 per gallon if order is 300 gallons
  • Data remains as before
  • K 16, I 25, l 3600
  • Is this a case of all units or incremental
    discount?

33
Solution
  • Step 1 For Price 1
  • Step 2 As Q(1) lt 300, EOQ is realizable.
  • Step 3 Price 2
  • Step 4 As Q(2) lt 300, EOQ is not realizable.

34
Cost Function
Realizable
G(Qp1)
C(Q)
G(Qp2)
Not Realizable
240
277
Q
300
35
Cost Function
Only possible solutions
G(Qp1)
C(Q)
G(Qp2)
240
277
Q
300
36
Solution
  • Step 5 Compare costs of possible solutions.
  • For 8 price, Q240
  • For 6 price, Q300
  • Q300 is the optimal quantity.

37
Resource Constrained Multi-Product Systems
  • Classic EOQ model is for a single item. Setup
    plan for n items.
  • Option A Treat one system with multiple items
    as multiple systems with one item
  • Works if There are no interactions among items,
    such as sharing common resources budget,
    storage capacity, or both
  • Option B Modify classic EOQ to insure no
    violation of the resource constraints
  • Works if Have not made any mistakes and know how
    to use Lagrange multipliers ?

38
Resource Constrained Multi-Product Systems
  • Consider an inventory system of n items in which
    the total amount available to spend is C and
    items cost respectively c1, c2, . . ., cn. Then
    this imposes the following budget constraint on
    the system
  • , where Qi is the order size for product i
  • , where wi is the volume occupied by product
    i
  • Minimize
  • s.t. and

For EOQ
39
Resource Constrained Multi-Product Systems
  • Minimize
  • s.t.

Budget constraint Space constraint
Lagrange multipliers method relax one or more
constraints Minimize by solving necessary
conditions
40
Resource Constrained Multi-Product Systems Steps
to Find Optimal Solution
  • Single constraint
  • Solve the unconstrained problem. If constraint is
    satisfied, this solution is the optimal one.
  • If the constraint is violated, rewrite objective
    function using Lagrange multipliers
  • Obtain optimal Qi by solving (n1) equations

41
Resource Constrained Multi-Product Systems Steps
to Find Optimal Solution
  • Double constraints
  • Solve the unconstrained problem. If both
    constraints are satisfied, this solution is the
    optimal one.
  • Otherwise rewrite objective function using
    Lagrange multipliers by including one of the
    constraints, say budget, and solve one-constraint
    problem to find optimal solution. If the space
    constraint is satisfied, this solution is the
    optimal one.
  • Otherwise repeat the process for the only space
    constraint.
  • If both single-constraint solutions do not yield
    the optimal solution, then both constraints are
    active, and the Lagrange equation with both
    constraints must be solved.
  • Obtain optimal Qi by solving (n2) equations

42
EOQ Models for Production Planning
  • Problem determine optimal procedure for
    producing n products on a single machine
  • Consider n items with known demand rates ,
    production rates , holding costs , and
    set-up costs . The objective is to minimize
    the cost of holding and setups, and to have no
    stock-outs. For the problem to be feasible we
    must have that
  • Assumption rotation cycle policy exactly one
    setup for each product in each cycle production
    sequence stays the same in each next cycle

43
The method of solution is to express the average
annual cost function in terms of the cycle time,
T to assure no stock-outs. The optimal cycle time
has the following mathematical form, where sj is
a setup time And the optimal production
quantities are given by where T max T,
Tmin, see pp.216-217
44
Recommended problems
  • Look over Ch. 4.1 4.4
  • Read Ch. 4.5 4.9
  • Problems
  • 4.5, 4.12, 4.15, 4.16
  • 4.17, 4.18, 4.22, 4.24, 4.25
  • 4.26, 4.27, 4.28, 4.30

45
References
  • Presentations by McGraw-Hill/Irwin and by
    Wilson,G.R.
  • Production Operations Analysis by S.Nahmias
  • Factory Physics by W.J.Hopp, M.L.Spearman
  • Inventory Management and Production Planning and
    Scheduling by E.A. Silver, D.F. Pyke, R.
    Peterson
  • Production Planning, Control, and Integration
    by D. Sipper and R.L. Bulfin Jr.
Write a Comment
User Comments (0)