Ralph Program Overview - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

Ralph Program Overview

Description:

The Ralph Design & Program Status Is The Focus For The ... packaging lab in FM-1. Electronics test lab ... Is A Challenge; The Team Is Up To The Task ... – PowerPoint PPT presentation

Number of Views:48
Avg rating:3.0/5.0
Slides: 18
Provided by: stevej1
Category:
Tags: fm | overview | program | ralph | task

less

Transcript and Presenter's Notes

Title: Ralph Program Overview


1
Ralph Program Overview Schedule
New HorizonsShedding Light On Frontier Worlds
Ralph Instrument Critical Design ReviewAug 5
6, 2003
  • Bob Parizek
  • Ralph Program Manager, Ball Aerospace
  • 303 939-4853
  • rparizek_at_ball.com

2
The Ralph Design Program Status Is The Focus
For The Next Two Days
  • Brief Overview Of The Ralph Instrument
  • Introduce Partners Producing The Ralph Instrument
  • Resources Are Available
  • Schedule Approach and Status
  • Limited Engineering Model Hardware Planned
  • Longevity Approach
  • Summary

3
The Ralph Instrument Contains Two Detectors MVIC
and LEISA
Cold Radiator
Warm Radiator
Thermal Straps
Purge Assy
Alignment Cube (Allocated space)
Thermal Strap
Aperture Baffle
Ralph Electronics
3X S/C Flexures
MVIC Detector Package
LEISA Detector Package
LEISA Detector Cabling
4
The Ralph Instrument Contains Two Components TDA
Electronics
Cold Radiator
Warm Radiator
Tertiary Mirror
Aperture Baffle
TDA Telescope Detector Assy
Primary Mirror
Electronics
3X S/C Flexures
5
The TDA Design Is Simple, Effective and Is
Designed To Last
Detector Packages
Aperture Baffle
Solar Illumination Lyot Stop Assy
Aperture Door Pin-Pull Actuator
Purge Asy
Aperture Door Assy (Open configuration)
Tertiary Mirror
3X S/C Flexure
Primary Mirror
6
Ball, GSFC and SwRI Are Partners In Developing
The Ralph Instrument
7
No Staffing Issues Resources Are Available And
Scheduled When Needed
  • Personnel resources are currently adequate the
    magnitude of the Ralph effort is well within
    capabilities and availability
  • Facilities are operational and available
    scheduled when needed
  • CCD test lab in CO-5
  • Production facilities in various locations
  • Machine shop
  • Metal treatment and painting
  • Electronics assembly both in-house and vendors
  • Detector packaging lab in FM-1
  • Electronics test lab in FA-2
  • Vibration tables and thermal vacuum chambers in
    FT-1
  • Performance verification test equipment mostly
    available from other projects
  • Ralph-specific GSE is planned and some items in
    work no significant issues

8
No Schedule Management Reserve Dictates
Success-Oriented Scheduling Approach
  • Several month Phase C/D delay since PDR and Delta
    PDR
  • Schedule compression results in several, parallel
    critical paths
  • Almost everything is near the critical pathby
    plan
  • One month internal management reserve extracted
    by applying nearly equal compression to parallel
    paths
  • Reserve reluctantly doled out as immovable issues
    occur
  • Only if work arounds exhausted
  • Initial one month reserve still intact

9
Some Engineering Model (EM) Hardware Built To
Reduce Technical and Schedule Risk
  • EM MVIC - Multi-spectral Visible Imaging Camera
  • Packaging path finder and assembly process
    verification
  • Early MVIC performance and detector-level
    environmental testing
  • EM LEISA Linear Etalon Imaging Spectral Array
  • Assembly process verification
  • Early performance testing
  • EM Electronics
  • Prove electronics design including detector
    interfaces
  • Enables simultaneous flight PWA testing at SwRI
    and Ball
  • Becomes integral to Ralph test set to support EM
    MVIC, EM LEISA and flight TDA functional and
    environmental testing

10
Success-Oriented Schedule Is Monitored and
Adjusted Continuously
11
The TDA and Electronics Follow Separate Paths
Until Final Integration and Performance Testing
Insert Simplified Summary Version of IT Flow
Chart
12
MVIC and LEISA Detector Schedules
13
Optics, TDA Housing, MLI Schedules
14
(No Transcript)
15
Electronics and TDA IT
16
Ralph Instrument IT
17
The Ralph Program Is A Challenge The Team Is Up
To The Task
  • The Ralph Team Is Fully Staffed and Working Well
    Together
  • Other Resources Are Available
  • The Design Is Maturing NicelyAs You Will Hear
    Today
  • The Schedule Is Very Tight But Achievable
Write a Comment
User Comments (0)
About PowerShow.com