Title: Ralph Program Overview
1Ralph Program Overview Schedule
New HorizonsShedding Light On Frontier Worlds
Ralph Instrument Critical Design ReviewAug 5
6, 2003
- Bob Parizek
- Ralph Program Manager, Ball Aerospace
- 303 939-4853
- rparizek_at_ball.com
2The Ralph Design Program Status Is The Focus
For The Next Two Days
- Brief Overview Of The Ralph Instrument
- Introduce Partners Producing The Ralph Instrument
- Resources Are Available
- Schedule Approach and Status
- Limited Engineering Model Hardware Planned
- Longevity Approach
- Summary
3The Ralph Instrument Contains Two Detectors MVIC
and LEISA
Cold Radiator
Warm Radiator
Thermal Straps
Purge Assy
Alignment Cube (Allocated space)
Thermal Strap
Aperture Baffle
Ralph Electronics
3X S/C Flexures
MVIC Detector Package
LEISA Detector Package
LEISA Detector Cabling
4The Ralph Instrument Contains Two Components TDA
Electronics
Cold Radiator
Warm Radiator
Tertiary Mirror
Aperture Baffle
TDA Telescope Detector Assy
Primary Mirror
Electronics
3X S/C Flexures
5The TDA Design Is Simple, Effective and Is
Designed To Last
Detector Packages
Aperture Baffle
Solar Illumination Lyot Stop Assy
Aperture Door Pin-Pull Actuator
Purge Asy
Aperture Door Assy (Open configuration)
Tertiary Mirror
3X S/C Flexure
Primary Mirror
6Ball, GSFC and SwRI Are Partners In Developing
The Ralph Instrument
7No Staffing Issues Resources Are Available And
Scheduled When Needed
- Personnel resources are currently adequate the
magnitude of the Ralph effort is well within
capabilities and availability - Facilities are operational and available
scheduled when needed - CCD test lab in CO-5
- Production facilities in various locations
- Machine shop
- Metal treatment and painting
- Electronics assembly both in-house and vendors
- Detector packaging lab in FM-1
- Electronics test lab in FA-2
- Vibration tables and thermal vacuum chambers in
FT-1 - Performance verification test equipment mostly
available from other projects - Ralph-specific GSE is planned and some items in
work no significant issues
8No Schedule Management Reserve Dictates
Success-Oriented Scheduling Approach
- Several month Phase C/D delay since PDR and Delta
PDR - Schedule compression results in several, parallel
critical paths - Almost everything is near the critical pathby
plan - One month internal management reserve extracted
by applying nearly equal compression to parallel
paths - Reserve reluctantly doled out as immovable issues
occur - Only if work arounds exhausted
- Initial one month reserve still intact
9Some Engineering Model (EM) Hardware Built To
Reduce Technical and Schedule Risk
- EM MVIC - Multi-spectral Visible Imaging Camera
- Packaging path finder and assembly process
verification - Early MVIC performance and detector-level
environmental testing - EM LEISA Linear Etalon Imaging Spectral Array
- Assembly process verification
- Early performance testing
- EM Electronics
- Prove electronics design including detector
interfaces - Enables simultaneous flight PWA testing at SwRI
and Ball - Becomes integral to Ralph test set to support EM
MVIC, EM LEISA and flight TDA functional and
environmental testing
10Success-Oriented Schedule Is Monitored and
Adjusted Continuously
11The TDA and Electronics Follow Separate Paths
Until Final Integration and Performance Testing
Insert Simplified Summary Version of IT Flow
Chart
12MVIC and LEISA Detector Schedules
13Optics, TDA Housing, MLI Schedules
14(No Transcript)
15Electronics and TDA IT
16Ralph Instrument IT
17The Ralph Program Is A Challenge The Team Is Up
To The Task
- The Ralph Team Is Fully Staffed and Working Well
Together - Other Resources Are Available
- The Design Is Maturing NicelyAs You Will Hear
Today - The Schedule Is Very Tight But Achievable