White topping highways for life - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

White topping highways for life

Description:

Project started out as a mine & blend with widening. ... With flashing beacons raised pavement markers. Similar to the DOT standards D-704-43 and 44. ... – PowerPoint PPT presentation

Number of Views:2818
Avg rating:3.0/5.0
Slides: 29
Provided by: leck
Category:

less

Transcript and Presenter's Notes

Title: White topping highways for life


1
White topping/highways for life
Leon Eckroth , Design
2
White Topping /Highways for life
  • Project Team
  • Design
  • Planning
  • Devils Lake District
  • Construction
  • FHWA
  • ND Ready Mix Concrete Products Association
  • And many others

3
White topping / highways for life
  • Westbound portion of Hwy 2 from Rugby to Berwick.
  • 8.25 miles in length.
  • Project started out as a mine blend with
    widening.
  • During the design phase upper management looked
    at a number of projects and this one was tagged
    for White Topping.
  • Planning Division then applied for HFL funds.
  • ND did receive 1 million to help fund this
    project.
  • The winning bid for this project was 6.793
    million.

4
highways for life Commitments
  • Mill existing surface.
  • Use the milled asphalt to widen and overlay the
    shoulders.
  • Overlay the milled surface with concrete.
  • Incorporate White Topping Specifications.
  • Implement a full lane closure and route EB and WB
    traffic head to head.
  • Use leave outs for cross traffic at all
    intersections throughout the project limits.

5
Highways for life commitments
  • Widen the median and outside shoulders.
  • Upgrade safety features to meet current standards
    (lane widths and shoulder widths, turn lanes).
  • Milling, paving, and installation of turn lanes
    should last approximately 9 weeks.
  • Reduce speed to 60 mph in construction zone.
  • Hold a public information meeting before
    construction begins.
  • Develop news releases for newspapers and radio
    and TV during and after construction.
  • Distribute surveys to nearby residents and
    businesses during and after construction.

6
Highways for life commitments
  • Have a goal of 4 on the Likert scale for the
    following 2 questions on the surveys.
  • How satisfied are you with the approach used to
    construct the new facility in terms of minimizing
    disruption.
  • How satisfied are you with the new facility
    compared to its previous condition.
  • Have a goal of zero worker injury rates for this
    project and require the contractor to submit a
    plan identifying how this will be accomplished.
  • Use an IRI specification for the PCC pavement.
  • Create a traffic control plan with the use of
    precast concrete median barriers in the crossover
    areas. With flashing beacons raised pavement
    markers. Similar to the DOT standards D-704-43
    and 44.
  • All HFL Commitments were met

7
Designing the white topping
  • Needed a concrete depth for a 20 year design life
    .
  • 7 was determined to be used, remaining
    decisions were based on that 7.
  • Bonded White Topping
  • Traffic control was one of the first issues that
    had to be addressed.
  • Cross traffic at intersections needed to be
    addressed.
  • Design showed 7 Leave outs in the whole project.
  • The contractor and the DL District reduced this
    number to 1 during the paving operation.
  • What type of surfacing should be used in the
    areas of culvert replacement.
  • First idea was full depth concrete of 9 with
    dowel bars and 15 spacing on the saw cuts.
  • Final design called for 12 of aggregate base and
    3 of HBP then the 7 of White Topping (uniform
    section).

8
Designing the white topping
9
Designing the white topping
  • First job of this type in the state.
  • Met with representatives of the concrete pavement
    industry.
  • Calls to the ND Ready Mix Concrete Products
    Association.
  • Calls to Wisconsin, Minnesota, Michigan and
    Colorado.
  • Materials made more calls during the process.

10
Special provisions
  • 6 special provisions used for this project.
  • First three covered the basic PCC conditions.
  • 1. Testing the strength of PCC using the
    maturity method .
  • 2. PCC pavement well-graded aggregate.
  • 3. Surface tolerance/grinding.
  • Next three covered payment methods, joint
    cutting, lay down, etc.
  • 4. PCC pavement longitudinal tining.
  • 5. PCC pavement - uncontrolled cracking.
  • 6. White Topping covered method of payment,
    milling, surface prep, placing and finishing.

11
Method of payment
  • 2 special pay items for the white topping
  • Concrete Pavement White Topping by the CY
  • Concrete Placement White Topping by the Square
    Yard

12
White topping quantities
  • Square yards of pavement (Included the placement,
    joint sawing)
  • Concrete by the CY (Measured amount)
  • Plans called for 7 of concrete.
  • Additional 10 for irregularities in the profile
    and repairing the cross slope.

13
joints
  • Joints were required every 7 for transverse and
    longitudinal.
  • The joint width was 1/8 and not sealed.
  • 36,200 LF of joints per mile .
  • Contractor used 4 to 5 saws to keep up with the
    lay down operation.
  • Eliminate any uncontrolled cracking. 
  • Total width of the concrete slab was 27 wide.
  • Outside part of the slab was 14 with a joint cut
    at 7 from center.
  • Inside part of the slab was 13 with a joint cut
    at 6.5 from center.

14
Joint detail
15
Construction issues
  • Grade line control.
  • Advised not to set a grade line in the plans. Do
    it in the field.
  • Used a string line on this project.
  • Field personnel would really like some guidance.
  • Better guidance on the grade line should be
    included in future plans.
  • May be more beneficial to cut the inside slab
    joint at 6 from center as it would put the joint
    more in the middle of the driving lane.

16
Project numbers
  • Contractor for this project was PCI (Progressive
    Contractors Inc.)
  • Total cost 6.94 million to date.
  • 1 million coming from HFL.
  • Slightly higher than mine and blend even with the
    current oil costs.
  • White topping portion of this project was
    completed in 8 days.
  • 1.5 days delay due to rain.
  • Total construction time was set at 90 days.
  • Plan quantity was 28,311 CY.
  • Actual field quantity was 28,248 CY.
  • Plan quantity for placement was 130,500 SY.
  • Total length of joints were 298,200 ft. 56.47
    miles

17
(No Transcript)
18
(No Transcript)
19
(No Transcript)
20
(No Transcript)
21
(No Transcript)
22
(No Transcript)
23
(No Transcript)
24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
  • Any questions
  • Leon Eckroth, Design
  • Clayton Schumaker, Materials
  • Greg Semenko, Devils Lake District
  • Darrin Lindblom, Devils Lake District
  • Jack Smith, Technical Services
  • Dave Sethre, ND Ready Mix Concrete Products
    Association
Write a Comment
User Comments (0)
About PowerShow.com