Title: TRENCHLESS TECHNOLOGY HOW TO ACHIEVE THE DESIRED RESULT
1TRENCHLESS TECHNOLOGY - HOW TO ACHIEVE THE
DESIRED RESULT
- Presenter
- Philip McFarlane
2Sewer Rehabilitation Survey 2001
- Average Council Expenditure
- 670k per year
- Spending more than 1mil per year
- 5 Councils
- Mostly maintenance of individual assets
- Some major upgrade projects
- Most expected expenditure to increase
3LEVEL OF SATISACTION
4REASONS
- Unreasonable expectations of what could be
achieved - No-one told us that would be a problem
- We did not think that was there
- Not sure if contractor delivered what we wanted
5TYPICAL PROJECT MANAGEMENT APPROACH
6MORE UNCERTAINTIES WITH TRENCHLESS
- Ground conditions
- Existing pipe
- Performance of the existing system
- Performance of installation techniques
7TRENCHLESS TECNOLOGY APPROACH
Project Definition
Determine performance of existing network
Investigate condition of existing system
Investigate subsoil conditions
Design
Implementation
Evaluation
8PROJECT DEFINITION
- Feasibility of project is investigated
- Project budget determined
- Project programme is determined
- Roles and responsibilities allocated
- Clear quantifiable objects set
9TYPICAL OBJECTIVES
- Increased capacity
- I/I Reduction
- Reduction in frequency of sewer overflows
- Reduction in frequency of blockages
- Less risk of collapse
10DETERMINATION OF PERFORMANCE OF CURRENT SYSTEM
- Sewer gauging and modeling
- Spot gauging
- Location of blockages
- Location and frequency of overflows
- Location of surcharging manholes
- Locations where exfiltration occurs
11SUBSOIL INVESTIGATIONS
- Purpose to Identify
- Hard/Softness of ground
- Variable ground
- Position of Interfaces
- Services
12SUBSOIL INVESTIGATIONS
- Types of Investigations
- History of area
- Local knowledge
- Boreholes
- Test Pits
13DETERMINATION OF THE CONDITION OF THE EXISTING
SYSTEM
- Smoke and dye testing
- CCTV inspection
- Inspect/test manholes
- Inspect/testing private drainage
14SMOKE TESTING
15CCTV INSPECTIONS
16SEE THE PIPE
17(No Transcript)
18Profiler
19Profiler Outputs
20Identify Other Constraints
- Areas where excavations not desirable
- Permitted working times
- Permitted working areas
- Bypass pumping requirements
- Environmental considerations
21DESIGN -
FACTORS TO CONSIDER
- Project objectives
- Hydraulic requirements
- Subsoil conditions
- Existing conditions
- Construction considerations
- Required performance of new works
22ITEMS TO BE ADDRESSED IN PERFORMANCE SPECIFIATION
- Contractors responsibilities
- Minimum performance requirements
- Risks
- Constraints
- Existing conditions
- Health Safety and Environmental Issues
- Quality assurance procedures
- How will performance be evaluated
- What factors will the client consider in their
evaluation
23IMPLEMENTATION
24CONTRACTORS QUALITY ASSURANCE DOCUMENTATION
Quality Manual
Project Plan
Process Plans
Inspection and Test Plans
25QUALITY ASSURANCE AUDITS
Check contractors QA documentation
Check actual work processes
Check quality records
Compliance Audits
26TYPICAL COMPLIANCE AUDITS
- Samples of liner tested for strength
- Hydrostatic test
- CCTV inspection
27Evaluation
- Sewer gauging and modeling
- Has frequency of blockages reduced
- Long-term monitoring of performance
28TRENCHLESS TECNOLOGY APPROACH
Project Definition
Determine performance of existing network
Investigate condition of existing system
Investigate subsoil conditions
Design
Implementation
Evaluation