Title: Petroleum Engineering 406
1Petroleum Engineering 406
2Read
- Well Control Manual
- Chapter 4-6
- Homework 1 Due Jan. 1/28/04
3Causes of Kicks - Tripping
- Failure to keep the hole full
4Causes of Kicks - Tripping
5Causes of Kicks
6Causes of Kicks - Drilling
- Insufficient density of drilling fluid
- Drilling into Abnormal pressure
7Causes of Kicks - Other
- Annular flow after cement job
- Lost control during DST
- Drilling into adjacent wells
- Drilling through (shallow) gas zones at excessive
rates
8Kick Warnings - Drilling
- Drilling break
- Increase in flow rate
9Kick Warnings - Drilling
10Kick Warnings - Drilling
- Decrease in circulating pressure
- Increase in pump rate
- Well flows with pumps off
11(No Transcript)
12(No Transcript)
13Kick Warnings - Tripping
- Improper hole fill
- DO NOT WAIT FOR PIT GAIN OR FOR THE WELL TO FLOW
- What should you do if the well is not taking the
proper fill on a trip?
14Shut In Procedures - Drilling
- Soft Shut In
- Pick up the kelly until the tool joint clears the
floor. - Shut down the pumps.
- Check for flow.
- If flowing, open the HCR valve.
- Close BOP.
- Close choke.
- Hard Shut In
- Pick up the kelly until the tool joint clears the
floor. - Shut down the pumps.
- Check for flow.
- If flowing, Close BOP.
- Open HCR valve.
- Close choke.
15Shut In Procedures - Drilling
- Soft Shut In
- Notify supervisors
- Read record SIDPP, SICP, Pit Gain, Time, Date
- Prepare to implement kill.
- Hard Shut In
- Notify supervisors
- Read record SIDPP, SICP, Pit Gain, Time, Date
- Prepare to implement kill.
16Shut In Procedures - Tripping
- 1. Set slips below top tool joint
- 2. Stab a full opening safety valve and close
it. - 3. Open the HCR and close the BOP, and choke
- 4. Pick up and stab the kelly or a pump-in line
17Shut In Procedures - Tripping
- 5. Open the safety valve.
- 6. Notify the supervisors.
- 7. Read and record SIDPP, SICP, Pit gain, TVD of
Well, TVD of bit, time, and date. - 8. Prepare to implement kill.
18Shut In Procedures - Diverters
- With diverters in use (prior to setting surface
casing) - DO NOT SHUT IN WELL - DIVERT.
19Shut In Procedures - Casing
- 1. Lower casing until a swage and valve can be
stabbed. - 2. Close the casing rams or annular preventer.
- 3. Stab the swage and valve.
- 4. Notify supervisor
- 5. Read and record pressures
- 6. Prepare to kill well
20Well Kill Methods
- Wait Weight method
- Drillers method
- Circulate weight
- Concurrent method
21Well Kill Methods
- Reverse circulation
- Dynamic kill
- Bullheading
- Lubricate and bleed
- Volumetric
22Constant BHP Well Control
23Wait Weight Method
- Weight up mud to KWM and complete kill sheet
- Circulate KWM to bit following decline schedule
- Circulate KWM back to surface maintaining FCP on
drillpipe pressure
24Wait Weight Method
7000
25Wait Weight Method
- When well is full of KWM, Shut in well
- Check for remaining pressures
- If surface pressures are zero, check for flow by
cracking choke - If no flow, carefully open BOPs
- Circulate around again
26Wait Weight - Advantages
- Kill well in one circulation
- Least amount of maximum casing pressures
27Drillers Method
- Shut in well long enough to measured stabilized
SI pressures - Circulate kick fluids from wellbore with original
weight mud maintaining ICP on drillpipe - When kick fluids are circulated out, shut in well
28Drillers Method
- Weight up mud to KWM
- Circulate KWM to bit following pressure decline
schedule - Continue circulating KWM around maintaining FCP
until KWM reaches surface - Shut well in, check for pressures, flow etc.
29Drillers Method
30Drillers Method - Advantages
31Circulate Weight
- Shut in long enough to measure stabilized SI
pressures - Begin circulating kick from wellbore with OWM at
ICP - While circulating, isolate one pit and begin to
weight up to KWM - When mud is weighted up, switch pump suction to
weighted pit, and follow WW
32Circulate Weight - Advantages
33Concurrent method
- Weight up and circulate in increments
- Takes one complete circulation for each increment
34Reverse Circulation
- Circulate down annulus and up the drillpipe or
tubing. - Used extensively in workovers and completions
35Dynamic Kill
- For blowout control
- Use high pump speeds and viscosities to generate
high annular friction pressures - Annular friction used instead of surface choke
- For shallow gas
- Circulate as fast as rig pumps will allow through
diverters - DO NOT HOLD ANY BACK PRESSURE
36Bullheading
- Pump kill fluid down wellbore, usually at
relatively high speeds to force formation fluids
back into formation - Used predominantly in
- Workover and completion operations
- Austin Chalk flow drilling
- When danger of H2S
37Lubricate Bleed
- Only applicable with gas at the surface
- Pump in KWM into wellbore
- Let KWM fall for some time
- Bleed off gas
- Repeat
38Volumetric Method
- Used when circulation is not possible or when gas
is migrating in closed in well - As surface pressures increase due to gas
migration, bleed off excessive pressure and allow
bubble to expand. - Continue until circulation can be resumed or
until gas reaches surface
39Use of Kill Sheet
- Pre-recorded information
- SPP
- Pump output
- Drillstring capacity
- Annular capacity
- Pressure limitations
- Circulation times
- Number of strokes
40Use of Kill Sheet
- Post kick information
- SIDPP
- SICP
- Pit gain
- Time
- Date
41Use of Kill Sheet
- Calculate
- KWM SIDPP/0.052/TVD OWM
- ICP SPP SIDPP
- FCP SPPKWM/OWM
- Plot Pressure Decline Schedule
42Kill Sheet
43Kill Sheet
Plot ICP
Plot FCP