Scheduling and Budgeting - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

Scheduling and Budgeting

Description:

Program Evaluation & Review Technique (PERT) (we won't discuss) Blast Furnace Relining Example ... B. Remove top. A. 25. C. Rake out. A. 65. D. Remove pipes. A ... – PowerPoint PPT presentation

Number of Views:70
Avg rating:3.0/5.0
Slides: 33
Provided by: reginac8
Category:

less

Transcript and Presenter's Notes

Title: Scheduling and Budgeting


1
Scheduling and Budgeting
  • Engineers Without FrontiersCEE 402

2
Basic Project Management Cycle
  • Initiation Phase
  • Team formation
  • Goals
  • Objectives
  • Planning Phase
  • Scheduling of tasks
  • Budgeting (resource management)
  • Control Phase
  • Periodic adjustment of the PLAN
  • Closeout Phase

3
Basic Project Management Process
4
Project Planning Tools
  • Work Breakdown Structure (WBS)
  • Hierarchy of tasks
  • Estimated task durations
  • Responsibility Chart
  • Allocation of tasks to individuals
  • Gantt or bar chart
  • Schedule
  • Budget

5
Hierarchical Work Breakdown Structure (WBS)
6
Microsoft Project WBS
7
Building Renovation Example
  • Design
  • Pre-Renovation
  • Renovation
  • Furnish
  • Post-Renovation

8
Example of a WBS with Details
9
Sample Responsibility Matrix
10
Project Scheduling
  • Critical path method
  • Project network (arrow diagram)
  • Gantt or bar chart
  • Resource scheduling
  • Program Evaluation Review Technique (PERT) (we
    wont discuss)

11
Blast Furnace Relining Example
  • Reduction of iron oxide to molten iron to make
    steel

Main reaction
1000o C
30 meters
7 meters in diameter
Molten Iron andimpurities
12
Construction Planning
  • Bosh and stack are lined with firebrick
  • Lining needs to be replaced every 2-4 years
  • Pipefitters, carpenters, bricklayers, etc. needed
  • Expensive to have furnace offline
  • Work typically carried out using three shifts
    around the clock

13
Objectives
  • Installation of new coke screening and weighing
    equipment
  • Replacement and rebricking of the hot blast main
  • Rebricking of the bustle main
  • Extensive repairs to the uptakes and downcomers

14
Questions
  • What is the expected project duration?
  • How should the work tasks be scheduled so that
    the project is completed in the minimum time
    possible?
  • How do costs accumulate through the course of the
    project? What are the financing needs?

? Use Critical Path Method to answer
15
Project Network Example Build a House
1
Excavate
2
Foundation
Activitity
3
6
Roof
Event (usually point when activities leading to
that point are done)
Rough Wall
ExteriorSiding
4
8
Rough ExteriorPlumbing
Dummy
Exterior Painting
5
10
Dummy activity
Rough Interior Plumbing
Rough Electrical Work
7
  • Rules
  • 1 start node/1 end node
  • 2 nodes can be directly connected by no more than
    1 arc
  • No unnecessary arcs
  • Flow to right (or down)

Wall Board
Exterior Fixtures
9
Flooring
Interior Plumbing
11
12
Dummy
13
Interior Fixtures
16
How to Draw a Project Network
  • List all tasks.
  • Determine the precedence requirements.
  • Draw diagram
  • Draw node 1. All activities with no precedence
    requirements emanate from it.
  • One by one add activities for which precedence
    requirements have been satisfied.
  • Renumber nodes.

17
List Tasks for Blast Furnace and Precedence
Requirements
Duration (Hrs.)







ID
Task Description
Predecessors




A

Cool furnace




none

128.0 18.0 6.0 14.7 56.0 22.7 37.3 46.0 96.0 56.0
169.3 300.0 41.3 82.7 160.0 633.3 586.7 126.7 36.0
128.0 98.7
B

Remove top




A

C

Rake out




A

D

Remove pipes




A



E

Wreck stack




B, C



F

Install safety platform



E



G

Fit brick platform



F



H

Wreck hearth




F



I

Renew bosh




F



J

Renew coolers




H



K

Brick hearth




I, J



L

Brick stack




G, K



M

Fit top





L



N

Fit pipes




D, E



O

Rebrick bustle main



A



P

Renew hot blast main



A



Q

Repair uptakes downcomers


A



R

Install coke screen weigh


none



S

Complete top




M, N, O, P, Q



T

Dry





M, N, O, P, Q



U

Fill and heat




R, S, T





2843.4
18
Critical Path for Blast Furnace
  • Sequence of activities through project network
    that determines project duration
  • Since all activities must be completed, critical
    path is path with maximum duration

3
G, 37.3
13
S,36
F 22.7
B,18
J 56
M 41.3
A 128
L 300
H,46
K 169.3
2
11
1
C,6
T,128
E,56
4
17
16
I, 96
U 98.7
N, 82.7
D,14.7
10
O, 160
14
P, 633.3
Expected Duration 1064 hrs.
Q, 586.7
15
R, 126.7
19
Numbering Nodes on Project Network
  • Number start node 1, then erase all arrows coming
    out of it.
  • Find all nodes that have only outward-pointing
    arrows.
  • Number all such nodes consecutively (in any
    order), then erase all arrows emanating from
    these nodes.
  • Repeat steps 2 and 3 until final node is numbered.

G
13
3
B
S
A
F
H
J
K
L
M
2
11
E
C
T
I
4
U
17
16
N
D
10
O
P
14
Q
15
R
20
Time Definitions
  • dIJ duration of activity IJ
  • ESTIJ earliest time activity IJ can start
  • EFTIJ earliest time activity IJ can finish
  • LSTIJ latest time activity IJ can start without
    increasing project duration
  • LFTIJ latest time activity IJ can finish without
    increasing project duration
  • EFTIJ ESTIJ dIJ
  • LFTIJ LSTIJ dIJ

21
Float
  • Total float of activity IJ
  • Max. time activity IJ can be delayed without
    increasing project duration, assuming predecessor
    activities started at EST

TFIJ LSTIJ - ESTIJ
22
Calculating Times
  • Forward pass to calculate ESTIJ
  • Max. of EFT of activities coming into node
  • Backward pass to calculate LSTIJ
  • Min.(LSTJK) - dIJ
  • EFTIJ ESTIJ dIJ
  • LFTIJ LSTIJ dIJ
  • TFIJ LSTIJ ESTIJ
  • If ESTIJLSTIJ, then IJ is on critical path.
  • Minimum project duration Critical path duration

23
Activity Table
24
Completed Activity Table
25
Gantt Chart for Blast Furnace
200
400
600
800
1000
1200
hours
Activity
Critical

A


B

Scheduled duration
C

D

Float

E


F

G

Expected duration 1,064 hours

H

I


J


K


L


M

N

O

P

Q

R

S


T


U

26
Gantt Chart Variation
7/03
8/03
9/03
10/03
11/03
12/02
mth.
Duration (days)
Activity
40

A

Progress to date September 2003
B

10

C

5

D

25

Milestone
E

0
F

45

90

G

H
0
27
Costs for Blast Furnace Tasks
Duration (Hrs.)
Cost (1000)









ID
Task Description
Imm. Pred.









A

Cool furnace


none


60
128.0 18.0 6.0 14.7 56.0 22.7 37.3 46.0 96.0 56.0
169.3 300.0 41.3 82.7 160.0 633.3 586.7 126.7 36.0
128.0 98.7
B

Remove top




A



25

C

Rake out




A



65

D

Remove pipes




A



100

E

Wreck stack




B, C



125

F

Install safety platform



E



70

G

Fit brick platform



F



70

H

Wreck hearth




F



75

I

Renew bosh




F



50

J

Renew coolers




H



60

K

Brick hearth




I, J



190

L

Brick stack




G, K



230

M

Fit top





L



50

N

Fit pipes




D, E



50

O

Rebrick bustle main



A



220

P

Renew hot blast main



A



170

Q

Repair uptakes downcomers


A



120

R

Install coke screen weigh


none



80

S

Complete top




M, N, O, P, Q



60

T

Dry





M, N, O, P, Q



55

U

Fill and heat




R, S, T




75


2000
2843.4
28
Accumulated Project Cost for Blast Furnace (1000)
2,000
1,800
1,600
1,400
1,200
Project Cost (1000)
1,000
800
600
400
200
0
0
100
200
300
400
500
600
700
800
900
1000
1100
Time (hours)
29
Microsoft Project Gantt
30
Questions
  • What is the expected project duration?
  • How should the work tasks be scheduled so that
    the project is completed in the minimum time
    possible?
  • How do costs accumulate through the course of the
    project? What are the financing needs?

31
Costs and Budgets
  • Major concern of every project is to control
  • Time
  • Costs
  • Issues affecting costs
  • Amount of time charged by workers
  • Duration from start to finish
  • Time lost due to
  • Factors within control of management
  • Factors beyond control of management
  • Resources required to perform project

32
Cost Classification
  • Recurring vs. nonrecurring
  • Fixed vs. variable
  • Direct vs. indirect

33
Budgets
  • A budget is a plan that describes expenses for a
    specified period of time.
  • Budgets often include
  • Start-up costs (fixed)
  • Resources needed, e.g., labor, materials (direct)
  • Unit cost for resources (direct)
  • Indirect costs
  • Total project cost
  • Cost sharing
Write a Comment
User Comments (0)
About PowerShow.com