Title: Scheduling and Budgeting
1Scheduling and Budgeting
- Engineers Without FrontiersCEE 402
2Basic Project Management Cycle
- Initiation Phase
- Team formation
- Goals
- Objectives
- Planning Phase
- Scheduling of tasks
- Budgeting (resource management)
- Control Phase
- Periodic adjustment of the PLAN
- Closeout Phase
3Basic Project Management Process
4Project Planning Tools
- Work Breakdown Structure (WBS)
- Hierarchy of tasks
- Estimated task durations
- Responsibility Chart
- Allocation of tasks to individuals
- Gantt or bar chart
- Schedule
- Budget
5Hierarchical Work Breakdown Structure (WBS)
6Microsoft Project WBS
7Building Renovation Example
- Design
- Pre-Renovation
- Renovation
- Furnish
- Post-Renovation
8Example of a WBS with Details
9Sample Responsibility Matrix
10Project Scheduling
- Critical path method
- Project network (arrow diagram)
- Gantt or bar chart
- Resource scheduling
- Program Evaluation Review Technique (PERT) (we
wont discuss)
11Blast Furnace Relining Example
- Reduction of iron oxide to molten iron to make
steel
Main reaction
1000o C
30 meters
7 meters in diameter
Molten Iron andimpurities
12Construction Planning
- Bosh and stack are lined with firebrick
- Lining needs to be replaced every 2-4 years
- Pipefitters, carpenters, bricklayers, etc. needed
- Expensive to have furnace offline
- Work typically carried out using three shifts
around the clock
13Objectives
- Installation of new coke screening and weighing
equipment - Replacement and rebricking of the hot blast main
- Rebricking of the bustle main
- Extensive repairs to the uptakes and downcomers
14Questions
- What is the expected project duration?
- How should the work tasks be scheduled so that
the project is completed in the minimum time
possible? - How do costs accumulate through the course of the
project? What are the financing needs?
? Use Critical Path Method to answer
15Project Network Example Build a House
1
Excavate
2
Foundation
Activitity
3
6
Roof
Event (usually point when activities leading to
that point are done)
Rough Wall
ExteriorSiding
4
8
Rough ExteriorPlumbing
Dummy
Exterior Painting
5
10
Dummy activity
Rough Interior Plumbing
Rough Electrical Work
7
- Rules
- 1 start node/1 end node
- 2 nodes can be directly connected by no more than
1 arc - No unnecessary arcs
- Flow to right (or down)
Wall Board
Exterior Fixtures
9
Flooring
Interior Plumbing
11
12
Dummy
13
Interior Fixtures
16How to Draw a Project Network
- List all tasks.
- Determine the precedence requirements.
- Draw diagram
- Draw node 1. All activities with no precedence
requirements emanate from it. - One by one add activities for which precedence
requirements have been satisfied. - Renumber nodes.
17List Tasks for Blast Furnace and Precedence
Requirements
Duration (Hrs.)
ID
Task Description
Predecessors
A
Cool furnace
none
128.0 18.0 6.0 14.7 56.0 22.7 37.3 46.0 96.0 56.0
169.3 300.0 41.3 82.7 160.0 633.3 586.7 126.7 36.0
128.0 98.7
B
Remove top
A
C
Rake out
A
D
Remove pipes
A
E
Wreck stack
B, C
F
Install safety platform
E
G
Fit brick platform
F
H
Wreck hearth
F
I
Renew bosh
F
J
Renew coolers
H
K
Brick hearth
I, J
L
Brick stack
G, K
M
Fit top
L
N
Fit pipes
D, E
O
Rebrick bustle main
A
P
Renew hot blast main
A
Q
Repair uptakes downcomers
A
R
Install coke screen weigh
none
S
Complete top
M, N, O, P, Q
T
Dry
M, N, O, P, Q
U
Fill and heat
R, S, T
2843.4
18Critical Path for Blast Furnace
- Sequence of activities through project network
that determines project duration - Since all activities must be completed, critical
path is path with maximum duration
3
G, 37.3
13
S,36
F 22.7
B,18
J 56
M 41.3
A 128
L 300
H,46
K 169.3
2
11
1
C,6
T,128
E,56
4
17
16
I, 96
U 98.7
N, 82.7
D,14.7
10
O, 160
14
P, 633.3
Expected Duration 1064 hrs.
Q, 586.7
15
R, 126.7
19Numbering Nodes on Project Network
- Number start node 1, then erase all arrows coming
out of it. - Find all nodes that have only outward-pointing
arrows. - Number all such nodes consecutively (in any
order), then erase all arrows emanating from
these nodes. - Repeat steps 2 and 3 until final node is numbered.
G
13
3
B
S
A
F
H
J
K
L
M
2
11
E
C
T
I
4
U
17
16
N
D
10
O
P
14
Q
15
R
20Time Definitions
- dIJ duration of activity IJ
- ESTIJ earliest time activity IJ can start
- EFTIJ earliest time activity IJ can finish
- LSTIJ latest time activity IJ can start without
increasing project duration - LFTIJ latest time activity IJ can finish without
increasing project duration - EFTIJ ESTIJ dIJ
- LFTIJ LSTIJ dIJ
21Float
- Total float of activity IJ
- Max. time activity IJ can be delayed without
increasing project duration, assuming predecessor
activities started at EST
TFIJ LSTIJ - ESTIJ
22Calculating Times
- Forward pass to calculate ESTIJ
- Max. of EFT of activities coming into node
- Backward pass to calculate LSTIJ
- Min.(LSTJK) - dIJ
- EFTIJ ESTIJ dIJ
- LFTIJ LSTIJ dIJ
- TFIJ LSTIJ ESTIJ
- If ESTIJLSTIJ, then IJ is on critical path.
- Minimum project duration Critical path duration
23Activity Table
24Completed Activity Table
25Gantt Chart for Blast Furnace
200
400
600
800
1000
1200
hours
Activity
Critical
A
B
Scheduled duration
C
D
Float
E
F
G
Expected duration 1,064 hours
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
26Gantt Chart Variation
7/03
8/03
9/03
10/03
11/03
12/02
mth.
Duration (days)
Activity
40
A
Progress to date September 2003
B
10
C
5
D
25
Milestone
E
0
F
45
90
G
H
0
27Costs for Blast Furnace Tasks
Duration (Hrs.)
Cost (1000)
ID
Task Description
Imm. Pred.
A
Cool furnace
none
60
128.0 18.0 6.0 14.7 56.0 22.7 37.3 46.0 96.0 56.0
169.3 300.0 41.3 82.7 160.0 633.3 586.7 126.7 36.0
128.0 98.7
B
Remove top
A
25
C
Rake out
A
65
D
Remove pipes
A
100
E
Wreck stack
B, C
125
F
Install safety platform
E
70
G
Fit brick platform
F
70
H
Wreck hearth
F
75
I
Renew bosh
F
50
J
Renew coolers
H
60
K
Brick hearth
I, J
190
L
Brick stack
G, K
230
M
Fit top
L
50
N
Fit pipes
D, E
50
O
Rebrick bustle main
A
220
P
Renew hot blast main
A
170
Q
Repair uptakes downcomers
A
120
R
Install coke screen weigh
none
80
S
Complete top
M, N, O, P, Q
60
T
Dry
M, N, O, P, Q
55
U
Fill and heat
R, S, T
75
2000
2843.4
28Accumulated Project Cost for Blast Furnace (1000)
2,000
1,800
1,600
1,400
1,200
Project Cost (1000)
1,000
800
600
400
200
0
0
100
200
300
400
500
600
700
800
900
1000
1100
Time (hours)
29Microsoft Project Gantt
30Questions
- What is the expected project duration?
- How should the work tasks be scheduled so that
the project is completed in the minimum time
possible? - How do costs accumulate through the course of the
project? What are the financing needs?
31Costs and Budgets
- Major concern of every project is to control
- Time
- Costs
- Issues affecting costs
- Amount of time charged by workers
- Duration from start to finish
- Time lost due to
- Factors within control of management
- Factors beyond control of management
- Resources required to perform project
32Cost Classification
- Recurring vs. nonrecurring
- Fixed vs. variable
- Direct vs. indirect
33Budgets
- A budget is a plan that describes expenses for a
specified period of time. - Budgets often include
- Start-up costs (fixed)
- Resources needed, e.g., labor, materials (direct)
- Unit cost for resources (direct)
- Indirect costs
- Total project cost
- Cost sharing