Title: AGU presentation


1
9th International Conference on Space Operations,
Rome June 2006
SMART-1 EP OPERATIONAL EXPERIENCE
Presented by David Milligan, Spacecraft
Operations Engineer European Space Operations
Centre, Robert-Bosch Straße 5, 64293, Darmstadt,
Germany e-mail David.Milligan_at_esa.int
2
PRESENTATION
  • Spacecraft, Mission Ground Segment
  • Smart-1 EPS description (Hardware Software)
  • Post launch mission optimisation
  • EP Re-boost Phase (Mission Extension)
  • Operational Considerations of EP
  • EP shutdowns Performance changes
  • Power Throttling
  • Interactions
  • Conclusions and Remarks

3
Spacecraft Platform Design
4
Electrical Propulsion Hardware - Main Elements
  • Xenon Tank
  • PPS1350 Thruster
  • PPU
  • EPIRTU
  • BPRU
  • XFC
  • FU
  • HPSSPC
  • PPIM

5
Electric Propulsion Hardware - Thruster
  • Stationary plasma thruster PPS-1350-G developed
    by SNECMA
  • Input power range 649-1418 W
  • At maximum nominal power set, Thrust 70.1mN,
    Isp 1609s

6
Electric Propulsion Hardware - Thruster
Operating Principle
Ions
B
7
Electric Propulsion Hardware - EPMEC
  • Gimbals the EP thruster
  • 2 axis /- 8deg
  • Counteract disturbance torques

8
EPS Subsystem Software
PREcard Software
  • PREcard is responsible for Propellant Management
  • Dedicated TCs can program variables
  • Used in Venting and Automatic modes
  • Controls Valve opening and closing times
    dedicated health checks
  • Essentially regulates LPT pressure i.e. pressure
    in the plenum tank..

9
EPS Subsystem Software
PPU - Variable Power and Inrush Limitation
  • Executes in PPU Automatic mode
  • Commands EPS power supplies (1 of 117 nominal
    power sets)
  • Initiates controls ignition sequence
  • Operates closed loop control of EPS
  • Many monitoring checks..

10
Ground Facilities
  • Ground segment facilities are based on
    (extensions of) existing infrastructure
  • ESA ground stations shared between ESA missions
    and external customers.
  • Dedicated Control Room, incl. MCS workstations.
  • Dedicated areas for FD, Network, etc.

11
Operations Concept
  • Mission operations team kept at a minimum
  • Reduction of planned passes to reduce operations
    cost (originally planned to have 2x8hrs passes
    per week)
  • Support during normal working hours only during
    the routine phase
  • Sequences uplnked to cover 10 days
  • No spacecraft controllers (low level of
    operations).
  • Approach was adapted after launch (e.g. improved
    Lunar orbit doppler and ranging data for EP)
  • Some lights-out operations

12
Mission Description 7 Phases
  • Launch and Early Orbit Phase. Launch on
    2003/09/27, initial orbit 7029 x 42263 km.
    Platform Commissioning - 4days (24hrs/day)
  • Van Allen Belt Escape. Escape phase completed by
    Dec-2003 Jan-2004, orbit 20000 x 63427 km.
    Continuous thrust.
  • Earth Escape Cruise. Mainly perigee thrusting to
    raise apogee.
  • Moon resonance and Capture. Moon capture on
    2004/11/11, 310,000 km from the Earth and 90,000
    km from the Moon.
  • Lunar descent. Target orbit of 2,200 x 4,600 km.
  • Lunar Science (before and after re-boost phase).
    Until the end of lifetime around 2006/07, excl.
    one-month re-boost phase.
  • Re-boost phase. 207 revolutions of about 5 hours
    each with 68 minutes thrust during both
    ascending, and descending arcs of the orbit.
    02/08/05 to 17/09/05

13
In Flight Use SMART-1 Mission Evolved with
Experience
  • Removal of 3 Swing-bys
  • Earlier arrival Improved orbit (300x10000km ?
    300x3000km)
  • Mission Extension (1yr)
  • EPS excellent performance
  • Power budget
  • FD transfer optimisation / season

14
MISSION EXTENSIONEP Re-boost Phase - Orbital
Perturbations
  • With nominal mission approaching end S1 in good
    health mission extension foreseen
  • Orbit unstable - main disturbance 3rd body
    Earth and Sun
  • Retrograde argument of perilune drift
  • Eccentricity also effected
  • Decreases initially (up until line of apsides
    alignment with Lunar axis, at 270deg)
  • Increases afterwards - perilune altitude affected
    (until perilune lt Lunar radius impact!)

15
EP Re-boost Phase Maximise use of xenon
  • Residual xenon was 1.8kg (cant be used) of
    original 82kg
  • But after analysis - innovative new procedures
    developed to push system beyond its original
    design (down to last 280g)
  • Ultimate limit at very low pressure
  • Propellant flow system

16
EP Re-boost PhaseMission Extension Implementation
  • Studies and sims gave good confidence ? the most
    ambitious re-boost strategy was selected (of
    possible 3)
  • Re-boost August 2nd -September 17th, 2005.
  • Included 3 pauses (total 10 days) - double
    star-tracker blinding
  • The thrust arcs outside the perilune and apolune
    rotate as well as raise the orbit
  • Some FDIR disabled
  • Other operational tricks
  • Insertion of filling procedures at perilune and
    apolune

Operational Orbit selected for Mission extension
Distance from the Moon Centre
17
EP Re-boost Phase Operations and Results
  • Ultimate limit when the Anode current falls below
    1.35A, the PPU software turns off the thruster
    power supplies and flags a FLAME OUT in
    telemetry.
  • BB valves push well beyond qualification for
    mission extension performed very well

18
Orbit at end of EP re-boost 1
  • Orbit largely reset to initial conditions ?
    most favourable trade-off for lunar science
  • First Science phase, argument pericentre 286.2
    ? 243.8
  • Re-boost, 243.8 ? 292.9
  • Residual xenon mass reduced from 1.8kg to only
    280g
  • Second (much smaller re-boost phase foreseen).

From October 1st 2005 the Science Activities were
resumed and they will finish just before the Moon
impact scheduled on August 17th 2006 ? now
September 3rd 2006
19
General EP Ops experience - EPS Unplanned
Shutdowns
  • Initial orbit raising
  • Unplanned shutdowns out of coverage
  • Mainly radiation induced
  • SEUs in software etc
  • EP not primary source
  • Less than half were OSETs
  • All solved after launch
  • e.g by patching various software on board

20
General Ops Experience - Unplanned EP shutdown
effect
  • Antenna pointing errors
  • Infrequent passes
  • Missing impulse ? early AOS

GS pointing error
S1 Thrust arcs
Expected position
Actual position
21
Orbital Uncertainties
Variable Thruster performance and switch OFF out
of coverage
  • Infrequent passes on orbit raising missions is
    challenging
  • Unplanned shutdowns can create very large TOVs.
    Need to be able to deal with them (impact search
    routines - scheduling)
  • Small thrust variations create small TOVs
    increases required frequency of orbit
    determination
  • SMART-1 GS developed new search routines and
    demonstrated tolerance to performance uncertainty

S1 thrust performance
PPS1350 Anode rms Current
22
EP Thrust Performance
  • Thrust levels from ranging Doppler cf Nominal
    Power Set

Drawing provided by ESOC Flight Dynamics
23
PPS1350 Anode rms Current
24
Ops Experience - OSETs
  • Unexpected EP shutdowns occurred, with the PPU
    software bit Flame Out triggered in TM
  • Strongly correlated with the Halloween solar
    flare 10/2003
  • Sensitivity identified in an optocoupler in the
    PPU (single events)
  • Recovery action is after status check of power
    supplies to restart the thruster OBSW patched
    developed to automate process

25
Ops Experience - OSETs
  • OBSW patch developed that detected and
    automatically restarts EP

26
General EP OPS experience - Power Dependency 2
  • Generated Solar Array Power with the seasonal
    effect removed
  • Distance affects available W/m2
  • Drop caused by Van Allen Belt Crossing ? 8
    (7.5)..

Radiation exposure
27
EP Power Throttling
  • Goal safely maximize power into EP
  • SA output and platform consumption predicted
  • EP power levels (?thrust/Isp) given to FD for
    Orbit Propagation..

28
EPS Performance Summary
From October 1st 2005 the Science Activities were
resumed and they will finish just before the Moon
impact scheduled on August 17th 2006 ? now
September 3rd 2006 see S1 impact presentation
on friday
29
CONCLUSIONS AND REMARKS
  • SMART-1 Mission performance - a great success..
  • First EP use to escape Earth centred orbit (weak
    stability crossing)
  • The orbital strategy, the performance operation
    of thruster and power subsystems, allowed
  • Shorter transfer
  • Improved Science orbit
  • 1 Year mission extension
  • Ground segment for EP orbit raising demonstrated
    (tolerant to switch offs performance changes)
  • Low pressure ops demonstrated Tank residual
    1.8kg ? 280g
  • SA degradation due to VA belts 8 (with X-class
    solar flare)
  • Plasma of EP caused no operational impact

30
QUESTIONS
  • ?
  • Further questions david.milligan_at_esa.int