Title: Time Schedules and Project Management
1Time Schedules and Project Management
2Importance of Project Schedules
- Managers often cite delivering projects on time
as one of their biggest challenges - Average time overrun from 1995 CHAOS report was
222 improved to 63 in 2001 study - Time has the least amount of flexibility it
passes no matter what - Schedule issues are the main reason for conflicts
on projects, especially during the second half of
projects
3Conflict Intensity Over the Life of a Project
4Project Time Management Processes
- Project time management involves the processes
required to ensure timely completion of a
project. Processes include - Activity definition
- Activity sequencing
- Activity duration estimating
- Schedule development
- Schedule control
5Where Do Schedules Come From? Defining Activities
- Project schedules grow out of the basic document
that initiate a project - Project charter includes start and end dates and
budget information - Scope statement and WBS help define what will be
done - Activity definition involves developing a more
detailed WBS and supporting explanations to
understand all the work to be done
6Activity Sequencing
- Involves reviewing activities and determining
dependencies - Mandatory dependencies inherent in the nature of
the work hard logic - Discretionary dependencies defined by the
project team soft logic - External dependencies involve relationships
between project and non-project activities - You must determine dependencies in order to use
critical path analysis
7Project Network Diagrams
- Project network diagrams are the preferred
technique for showing activity sequencing - A project network diagram is a schematic display
of the logical relationships among, or sequencing
of, project activities
8Arrow Diagramming Method (ADM)
- Also called activity-on-arrow (AOA) project
network diagrams - Activities are represented by arrows
- Nodes or circles are the starting and ending
points of activities - Can only show finish-to-start dependencies
9Figure 5-2. Sample Activity-on-Arrow (AOA)
Network Diagram for Project X
10Precedence Diagramming Method (PDM)
- Activities are represented by boxes
- Arrows show relationships between activities
- More popular than ADM method and used by project
management software - Better at showing different types of dependencies
11Figure 5-3. Task Dependency Types
12Sample Precedence Diagramming Method (PDM)
Network Diagram for Project X
Project 98 file
13Activity Duration Estimating
- After defining activities and determining their
sequence, the next step in time management is
duration estimating - Duration includes the actual amount of time
worked on an activity plus elapsed time - People doing the work should help create
estimates, and an expert should review them
14Schedule Development
- Schedule development uses results of the other
time management processes to determine the start
and end date of the project and its activities - Ultimate goal is to create a realistic project
schedule that provides a basis for monitoring
project progress for the time dimension of the
project - Important tools and techniques include Gantt
charts, PERT analysis, critical path analysis,
and critical chain scheduling
15Gantt Charts
- Gantt charts provide a standard format for
displaying project schedule information by
listing project activities and their
corresponding start and finish dates in a
calendar format - Symbols include
- A black diamond milestones or significant events
on a project with zero duration - Thick black bars summary tasks
- Lighter horizontal bars tasks
- Arrows dependencies between tasks
16Gantt Chart for Project X
Project 98 file
17Sample Tracking Gantt Chart
white diamond slipped milestone two bars
planned and actual times
Project 98 file
18Project Management
Note Critical activities as percentage of total
activities in a project decrease with increase in
project size.
19Agenda
- PERT
- Introduction.
- Preliminary Setup.
- General Network Rules.
- Statistical Time Estimates.
- Determination of Critical Path.
20Critical Path Method (CPM)
- CPM is a project network analysis technique used
to predict total project duration - A critical path for a project is the series of
activities that determines the earliest time by
which the project can be completed - The critical path is the longest path through the
network diagram and has the least amount of slack
or float
21Finding the Critical Path
- First develop a good project network diagram
- Add the durations for all activities on each path
through the project network diagram - The longest path is the critical path
22Simple Example of Determining the Critical Path
- Consider the following project network diagram.
Assume all times are in days.
a. How many paths are on this network diagram?
b. How long is each path? c. Which is the
critical path? d. What is the shortest amount of
time needed to complete this project?
23Determining the Critical Path for Project X
24More on the Critical Path
- If one of more activities on the critical path
takes longer than planned, the whole project
schedule will slip unless corrective action is
taken - Misconceptions
- The critical path is not the one with all the
critical activities it only accounts for time - There can be more than one critical path if the
lengths of two or more paths are the same - The critical path can change as the project
progresses
25Program Evaluation and Review Technique (PERT)
- PERT is a network analysis technique used to
estimate project duration when there is a high
degree of uncertainty about the individual
activity duration estimates - PERT uses probabilistic time estimates based on
using optimistic, most likely, and pessimistic
estimates of activity durations
26PERT Formula and Example
- PERT weighted average formula
- optimistic time 4X most likely time
pessimistic time - 6
- Example
- PERT weighted average
- 8 workdays 4 X 10 workdays 24 workdays 12
days 6 - where 8 optimistic time, 10 most likely time,
and 24 pessimistic time
27Preliminary Setup
- Activity
- Event
- Activities in Series
- Parallel Activities
- Burst Events
- Merged Events
- Dummy Activity
28PERT
ACTIVITY
DEPENDS ON
A
NONE
B
A
C
A
D
B
E
C
F
D E
29NET WORK
3
D
B
A
F
1
2
5
6
C
E
4
30PERT
ACTIVITY
DEPENDS ON
A
NONE
B
A
C
A
D
BC
31NET WORK
3
B
A
1
2
C
D
4
5
32NET WORK
D
4
5
B
A
1
2
C
3
33PERTGENERAL NETWORK RULES
- Before the initiation of an activity, all
activities preceding it must be completed. - Arrows indicate the sequence in which activities
appear in the network. The length or compass
direction of an arrow is in no way related to the
duration of the activity which it represents.
34PERTGENERAL NETWORK RULES
- Any two events cannot be connected by more than
one activity. - Event numbers cannot be duplicated.
- Networks must have only one initial event and
only one terminal event.
35PERTGENERAL NETWORK RULES
- The number at the head of an arrow should be
greater than that at the tail. - No looping is allowed in a network.
36Class Activity
- For your case draw the network diagram and
compare it with those of your classmates. - Make a ham and cheese omelet with three eggs
37PERT Statistical Time Estimates
- Optimistic Time (a)
- the minimum time in which an activity may be
expected to be completed if everything goes right
the first time. - Most Likely Time (m)
- the time taken most frequently by an activity for
its completion. - Pessimistic Time (b)
- the maximum time an activity takes for its
completion when every thing goes wrong.
38PERT Statistical Time Estimates
- Expected Duration (te) a4mb
- 6
- Standard Deviation (b-a)/6
39PERT Determination of Critical Path
- Activity Times
- ES Early Start of an Activity
- EF Early Finish of an Activity
- LS Late Start of an Activity
- LF Late Finish of an Activity
40PERT Determination of Critical Path
Lj
Li
Ej
Ei
i
j
ES Ei and LF Lj and EFEj ESD and LSLi
LF-D where D is the duration of the activity
41PERT Determination of Critical Path
- Slack
- corresponds to the extra time available for the
completion of an activity without affecting the
completion time of the project. - Slack LF-ES-D Lj-Ei-D
42Critical Path
- What is the critical Path?
C 3
4
2
G 4
A 8
1
I 6
D 7
6
7
F 13
B 10
H 2
E 2
3
5
43Critical Path
44Class Activity
- Changing a tire or Barbecue two stakes (with
barbecue sauce) and 4 ears of corn. - For your case, compute the total slack and free
slack for each activity. Determine the critical
path. Compare it with those of your classmates.
45Outputs from Schedule Development
- Project schedule.
- Bar charts, also called Gantt charts
46Gantt Chart
- Start with the calendar.
- Note all holidays, vacations, shutdown and any
business event or milestone that may effect the
project. - Set the project start date and work forward.
- Use data from your CPM table to position the
boxes. - Color critical activities.
47Outputs from Schedule Development
- Project schedule.
- Milestone charts
48SCHEDULE MANAGEMENT
49Inputs to Schedule Control
- Project schedule.
- Performance reports.
- Change requests.
- Schedule management plan.
50Tools and Techniques for Schedule Control
- Schedule change control system.
- Performance measurement.
- Additional planning.
- Project management software.
- Variance analysis.
51Outputs from Schedule Control
- Schedule updates.
- Corrective action.
- Lessons learned.
52Using Software to Assist in Time Management
- Software for facilitating communications helps
people exchange schedule-related information - Decision support models help analyze trade-offs
that can be made - Project management software can help in various
time management areas
53Project 98 Features Related to Project Time
Management
54Words of Caution on Using Project Management
Software
- Many people misuse project management software
because they dont understand important concepts
and have not had good training - You must enter dependencies to have dates adjust
automatically and to determine the critical path - You must enter actual schedule information to
compare planned and actual progress
55Barriers to Effective Time Management
There are many barriers to effective time
management, but they can be overcome. Here is a
list of the most common barriers
- Distractions
- Disorganization
- Perfectionism
- Procrastination
- Rigidity
56Distractions
Distractions come in many forms, but we must
learn to avoid distractions if we are to get work
done. Here are a few ideas
- Tell people when you are busy and cannot be
disturbed. - Work in areas where you are less likely to be
disturbed. - Do your work at times when you are most alert.
It is easier to get distracted when you are
tired.
57Disorganization
People often waste much time because of
disorganization. Here are some tips for staying
organized
- Keep things that you need in a specific place.
- Eliminate clutter.
- Before starting on a task, make sure that you
have all of the materials or information that you
need. - Follow your schedule.
58Perfectionism
It is a virtue to want to do a good job, but some
people become so anxious about getting a job done
perfectly that they never complete it.
- Examine whether your efforts to get the job done
perfectly are really improving things or
preventing you from getting the job done. - Think about the cost-benefit ratio of the extra
effort. - Remember that nothing is perfect.
59Procrastination
It is easy to put off tasks if they are not due
right away. The trouble is, tasks pile up and
you can run into a time crunch later. Remember
to work ahead whenever possible. If you can do
it today, do it!
60Rigidity
It is important to develop a habit of following
your schedule, but some people become too rigid.
Unexpected things come up and activities
sometimes take more time than planned. It is
important to have some flexibility in your
schedule. Allow extra time and avoid becoming
too frustrated if things dont work out as
planned just re-evaluate the plan and make
adjustments.
61The Next Step
You have learned about evaluating your time,
developing a weekly schedule, keeping a to-do
list, and identified distractions that should be
avoided. Now it is time for the next step Put
your time management skills into practice!