Queuing - PowerPoint PPT Presentation

About This Presentation
Title:

Queuing

Description:

At one of these locations, customers arrive at a Poisson rate of 150 per hour. ... to find the 'best' number of tellers, given that tellers are paid $8 per hour. ... – PowerPoint PPT presentation

Number of Views:38
Avg rating:3.0/5.0
Slides: 15
Provided by: LisaV
Learn more at: http://www.csun.edu
Category:
Tags: per | queuing

less

Transcript and Presenter's Notes

Title: Queuing


1
Example 14.3
  • Queuing

2
Background Information
  • County Bank has several branch locations
  • At one of these locations, customers arrive at a
    Poisson rate of 150 per hour.
  • The branch employs 6 tellers.
  • Each teller takes, on average, 2 minutes to serve
    a customer, and service times are exponentially
    distributed.
  • Also, all tellers perform all takes, so that
    customers can go to any of the 6 tellers.

3
Background Information -- continued
  • Customers who arrive and find all 6 servers busy
    join a single queue and are then served in FCFS
    fashion.
  • As a first step, the bank manager wants to
    develop a queuing model of the current system.
  • Then he wants to find the best number of
    tellers, given that tellers are paid 8 per hour.

4
MMS_TEMPLATE.XLS
  • As in the M / M / 1 system, there are formulas
    for the steady state probabilities, and these can
    be used to find summary measures such as L and W.
  • However, the details are fairly complex and will
    not be given here.
  • Instead, we provide a template in this file for
    performing the calculations.
  • The template can be seen on the next slide.

5
(No Transcript)
6
Solution
  • All you need to do is enter the inputs in cells
    B4 through B7 and then click on the button.
  • This button runs a macro that calculates all of
    the necessary outputs and places them in the
    appropriate cells.
  • From the template, we see that when there are 6
    tellers and the server utilization is 0.833, the
    expected number of customers in the system is
    7.94 and the expected time a typical customer
    spends in the system if 0.053 hour.

7
Solution -- continued
  • We can find the expected fraction of time each
    teller is busy as Lserv/s.
  • Then the expected fraction of time each teller is
    busy is Lserv/s 5/6 0.833. If this number
    doesnt ring a bell, it should it is the server
    utilization in cell B13. This is no coincidence.
  • The server utilization in an M / M / 1 system,
    calculated as the arrival rate divided by the
    maximum service rate, is always the expected
    fraction of time a typical server is busy.
  • We now turn to the economic analysis.

8
Economic Analysis
  • There is a cost and benefit from adding a teller.
  • The cost is the wage rate paid to the extra
    teller, 8 per hour.
  • The benefit is that customers wait less time in
    the bank.
  • The problem is evaluating the cost of waiting in
    line.
  • This is not an out-of-pocket cost for the bank,
    but the back realizes that it is an indirect cost
    in that customers who experience long waits might
    take their business elsewhere.

9
Economic Analysis -- continued
  • In any case, the key to the trade-off is
    assessing a unit cost, cQ, per customer per hour
    of waiting in the queue.
  • If the manager can assess this unit cost, then
    the total expected cost per hour and each waits
    waiting is cQ?WQ.
  • Then we can trade off this waiting cost against
    the cost of hiring extra tellers.

10
MMS_OPT_TEMPLATE.XLS
  • We provide another template in this file that
    helps solve the problem.
  • You now need to provide the arrival rate, the
    service rate per server, the wage rate per
    server, and the unit waiting cost per customer
    per unit time in line.
  • You should not enter the numbers of servers as an
    input.
  • Instead, the macro calculates selected summary
    measures of the system for several choices of the
    number of servers.

11
(No Transcript)
12
Solution -- continued
  • Specifically, it begins by using the smallest
    umber of servers required to keep the system
    stable.
  • This procedure requires a value for cQ in cell
    B8.
  • Because this value is probably very difficult for
    a bank manager to assess, we can instead use an
    indirect approach.
  • We will find ranges for cQ where a specific
    number of servers is economically optimal.

13
Solution -- continued
  • The output form the template can be seen on the
    next slide.
  • The results imply that it is best to use 6
    tellers when cQ lt 3.76.
  • Otherwise, if cQ lt 15.24, it is best to use 7
    tellers.
  • Finally, for cQ between 15.24 and 20, it is
    best to use 8 tellers.

14
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com