Title: US 36 Steering Committee


1
US 36 Steering Committee April 14, 2009 Karen
Morales FasTracks Public Information
2
U.S. 36 Corridor
18 miles Bus Rapid Transit (BRT)
service Connects downtown Denver to
Boulder Complete in 2016
Pending funding for managed lanes.
3
U.S. 36 Current Status
  • Phase I Transit Improvements begun to be
    complete in 2010
  • Opened new bus pullouts and new park-n-Ride at
    Church Ranch Boulevard, and new pullouts and
    pedestrian bridge at McCaslin Boulevard
  • Completed Draft Environmental Impact Statement in
    2007
  • Communities have identified combined alternative
  • Top priority managed lanes
  • Public meetings held April 1, 8 9

4
(No Transcript)
5
Components of Phase I
  • Improvements at
  • McCaslin
  • Church Ranch
  • 116th/Broomfield
  • Table Mesa
  • Combined travel time savings of 13 15 minutes
    between Boulder and Denver
  • Better pedestrian access with bridge additions
  • Expanded parking

6
  • US 36/116th Avenue

7
  • US 36/116th Avenue
  • Serving Broomfield
  • New parking structure complete 940 of 1,500
    spaces, shared with Broomfield Events Center
  • park-n-Ride with new slip-ramp stops estimated to
    open in May 2010
  • Estimated travel time savings 6-8 minutes each
    direction

8
Broomfield Improvements
9
Bridge Improvement Specifics
  • 3-span bridge length 400 ft
  • 4-span bridge length (planned for the future)
    500 ft
  • Bridge width 12-ft pedestrian pass and 20-ft
    overall width
  • The bridge has 18 clearance from the existing
    US-36 pavement to the bridge deck
  • The slip on- and off-ramps are 3,200 ft in length
    in each direction

10
Arista Development Site Plan
11
Broomfield Improvements
  • City Council just approved plan for these
    improvements
  • Design for the new bus transfer facility is
    approximately 90 complete
  • Parking on the east side of US 36 will include
    715 spaces to be added to the existing 940 spaces
    in the new parking facility for the Broomfield
    Event Center

12
Master Plan
13
  • For FasTracks Information
  • Surf FasTracks at
  • www.RTD-FasTracks.com
  • FasTracks Information Line
  • 303.299.2000
  • Questions?