Operations Planning (Alberta/BC) Outage Contacts. George Phillips Manager 920-6825 ... Refer to STOP for actual capability prior to outage ... – PowerPoint PPT presentation

Number of Views:132
Avg rating:3.0/5.0
Slides: 13
Provided by: Holl68
Category:
Tags: customer | sales | outage | seg

less

Transcript and Presenter's Notes

Title: CUSTOMER SALES


1
CUSTOMER SALES SERVICE
October 2005 OUTAGE FORECAST
2
Operations Planning (Alberta/BC) Outage Contacts
George Phillips Manager 920-6825 NORTH AND EAST
AREA Rahim Ruda 920-6360 Perry Krebes 920-6267
North and East Area
CENTRAL AREA Bruce Huynh 920-6282 Phil
Hanoski 920-5320 Kim Prusky 920-8118
OUTAGE PLANNING Glen Mohan 920-6802 Mike
Wylie 920-7346 Paula Jacobsen 920-6384 Jeff
Stoffregen 920-6337
Central Area
3
CONTENTS
  • Receipt Outlook - Upper and Central Peace River

    - Upstream of James River
  • Delivery Outlook - Empress/McNeill
  • - Alberta/BC
  • Central, Eastern and Northern Area Outage Maps

4

EASTERN CONSOLE
10. LIEG
6. MRTN
Paul Lake C/S
12. SMHI



Field Lake C/S
11. KIRB
14. COLD
13. REDL
Bens Lake C/S
Dusty C/S
23. WAIN
Gadsby C/S
16. ELAT
15. NLAT
Farrell Lake C/S
Oakland C/S
Cavendish C/S
Princess C/S
5
3. NWML
NORTHERN CONSOLE
Thunder Creek C/S
1. UPRM
Dryden CK C/S

Hidden Lk C/S
Meikle Rvr C/S
2. PRLL
Alces C/S
4. GRDL
27. LPRM
26. WRSY
Alces B C/S
6. MRTN
2. PRLL
4. GRDL
Saddle Hills C/S
27. LPRM
Gold Creek C/S
5. WAEX
Latornell C/S
Knight C/S
7. GPML
Berland River C/S
24. JUDY

9. LPOL
Swartz Creek C/S
8. CENT
Clearwater C/S
6
CENTRAL CONSOLE
17. ALEG
Schrader Creek C/S
Torrington C/S
Beiseker C/S
Hussar C/S
Winchell Lk C/S
Crawling Valley C/S
Red Deer R. C/S
21. WGAT
18. BLEG
Acme C/S
De/Re C/S
Richmound C/S
19. EGAT
Turner Valley C/S
Jenner C/S
Piapot C/S
22. SLAT
Foothills Sask.
Burton Creek C/S
Princess C/S
20. MLAT
Frenchmen Rvr C/S
Crowsnest A,B C/S
Elko C/S
Monchy C/S
Drywood C/S
Moyie C/S
25. TCBC
7
Upper Peace River Mainline Outlook
Facility Name Timing Capability Impact
Assessment (segments) Capability and impact
assessment depends on several factors and is
subject to change at any time, potential for
FT/IT cuts. denotes capability in restricted
area only see attached spreadsheet and map for
details. Refer to TCPLs Short Term Operating
Plan (STOP) for the latest information on
upcoming outages (1 - 2 month timeframe)
8
Upstream of James River Outlook
Facility Name Timing Capability Impact
Assessment (segments) Capability and impact
assessment depends on several factors and is
subject to change at any time, potential for
FT/IT cuts. Denotes capability upstream of
restricted area only see attached spreadsheet for
details Refer to TCPLs Short Term Operating
Plan (STOP) for the latest information on
upcoming outages (1 - 2 month timeframe)
9
Empress / McNeill Border Outlook

8 9 10
1,2
7
6
3 5
Facility Name Timing Capability 1.
Schrader Creek 3 C/S Unit Inspection (3
days) Dec 12 14 234 E6 2. Schrader Creek 1
C/S Unit Inspection (2 days) Dec 15 16 230
E6 3. Schrader Creek 1 C/S Unit Inspection (11
days) Jan 9 19 227 E6 5. Crawling Valley C/S
Unit Inspection (5 days) Jan 23 27 224 E6
6. Schrader Creek C/S Stn Inspection (5
days) Feb 6 10 220 E6 7. Schrader Creek 3
C/S Unit Inspection (3 days) Feb 27 Mar
3 231 E6 8. Clearwater 1 C/S Unit
Maintenance (5 days) Mar 6 10 227 E6 9.
Clearwater C/S Stn Inspections (5 days) Mar 13
17 223 E6 10. Clearwater 5 C/S Unit
Maintenance (5 days) Mar 6 10 229
E6 Capability and impact assessment depends on
several factors and is subject to change at any
time, potential for FT/IT cuts. Refer to TCPLs
Short Term Operating Plan (STOP) for the latest
information on upcoming outages (1 - 2 month
timeframe) Denotes capability upstream of
restricted area only see attached spreadsheet for
details
10
Alberta B.C. Border Outlook

Facility Name Timing ALTBC Cap Impact
Assessment /shipper Capability and impact
assessment depends on several factors and is
subject to change at any time, potential for
IT/FT cuts. Refer to TCPLs Short Term
Operating Plan (STOP) for the latest information
on upcoming outages (1- 2 month timeframe)
Higher capability may be achievable depending on
PGT ability to reduce Kingt pressure below
typical. Refer to STOP for actual capability
prior to outage
11
TransCanada West Outage Forecast October 2005
as of October 31, 2005
C/S Compressor Station M/S Meter Station (Shade
indicates new or changed) Inquiries? Contact
Glen Mohan at 920-6802.
EGAT Eastern Gate (Empress/McNeill
Borders ALTBC Alberta/BC Border FSCD Firm
Service Contract Demand
12
TransCanada West Outage Forecast October 2005
as of October 31, 2005
C/S Compressor Station M/S Meter Station (Shade
indicates new or changed) Inquiries? Contact
Glen Mohan at 920-6802.
EGAT Eastern Gate (Empress/McNeill
Borders ALTBC Alberta/BC Border FSCD Firm
Service Contract Demand
Write a Comment
User Comments (0)
About PowerShow.com