Title: THE REGULATION AND RESTRUCTURING OF THE US POWER SECTOR
1THE REGULATION AND RESTRUCTURING OF THE US POWER
SECTOR
ROBERT W. GEE PRESIDENT GEE STRATEGIES GROUP LLC
- TSINGHUA UNIVERSITY LAW SCHOOL
- BEIJING, PRC
- 3 NOVEMBER 2006
2Overview
- Current projection for electricity demand in the
United States, and forecast of resources required - Steps taken to restructure U.S. electric sector
to introduce greater competition in wholesale and
retail markets, and outcomes - Gaps or issues created as markets evolved, and
how newly enacted federal legislation addresses
them - Lessons learned
3Basic Cornerstones of U.S. Energy Policy
- Secure supply generally maintained through
diversity of fuel types and source locations - Safe no threat to public health and welfare
- Reasonably affordable
- (For electricity) Always available (i.e.,
reliable and not subject to unintended
interruption) - Clean (non-polluting to air or water)
-
4Projection From 2004 Through 2025 The U.S.
Thirst for Energy Will Continue Unabated
- U.S. electricity demand expected to grow by 1.6
percent annually (from 3,729 billion Kwh to
5,208 billion Kwh) -
- Demand for natural gas expected to grow from 22.4
Tcf to 27.7 Tcf - Coal consumption will grow by 1,104 million short
tons to 1,592 million short tons
Source Energy Information Administration /
Annual Energy Outlook 2006
5U.S. Electricity generation by fuel,
1980-2030(billion kilowatthours)
- Coals share of electric generation escalates,
ramping up from 49 percent in 2020 to 57 percent
by 2030 - Natural gas share of electric generation peaks
at 22 percent before falling to 17 percent by
2030 when displaced by new coal-fired generation - This projection does not factor in US adoption
of carbon emission controls - Nuclear generation expected to grow from 100 Gw
in 2004 to 109 Gw in 2019 and remain static until
2030 - Renewable generation will grow at average annual
rate of 1.7 percent per year, from 358 billion
kwH to 559 kwH by 2030
Source Energy Information Administration /
Annual Energy Outlook 2006
6Key Milestones Over The Last Half Century
- For most of the last century, natural gas and
electric power have been highly regulated by
government as public utilities - These services were considered natural
monopolies, unable to draw competition because
of high costs of market entry - Both the infrastructure-related delivery service
and the commodity costs were regulated, based
primarily on historic acquisition cost - Natural gas prices subject to ceilings
- Electric wholesale retail power prices subject
to regulated tariffs - However, by the 1970s, natural gas shortages
occurred because of lack of financial incentives
for producers - Eventually, federal government chose to phase in
deregulation of interstate natural gas prices
gas pipelines became transporters, rather than
owners of gas volumes - Natural gas supplies grew and prices stayed level
for almost a decade
7Electricity Sector Market Reforms
- Until 1990s, electric utilities held monopolies
for transmission, distribution and generation
services in all markets - However, electric power generation technology
advances made generation of efficient, affordable
power from independent owners of power plants
feasible - Previously successful reforms of natural gas
sector influenced movement toward restructuring
and reforming power sector - Early 1990s Federal government allowed creation
of independent power producers, thereby creating
a competitive wholesale power market and
deregulating the generation sector transmission
and distribution remained regulated monopolies - Mid-1990s states began to require unbundling of
services or functional separation of services/
some generation was sold to independent power
producers
8Some States Opened Retail Power Markets To
Competition
- Retail Choice gave customers (industrial,
commercial, and residential) direct access to
power generators - Approach favored generally in states with
higher-than national-average power costs
9Status of State Retail Restructuring Efforts
(2003)
Source Energy Information Administration
10The Picture Today
- Steep escalation in natural gas prices
- Over reliance on natural gas as fuel for power
generation for peaking capacity - New baseload generation needed
- Underinvestment in transmission capacity
- Mixed record of success of retail experiments
11U.S. Natural Gas Markets Today Higher Prices
- Initially, experienced higher spot prices and
greater volatility than during the 1990s when
gas prices were around 2.00 3.00 per MMBtu - 6.50 8.00 per MMBtu in summer
- 10.00 per MMBtu in winter
- Although allegations of market manipulation were
claimed by some, and state and federal
investigations were triggered, reason was
attributed to economic forces of supply (which is
declining) and demand (which is increasing) - Current spot prices are within 7.00 8.00 per
MMBtu range, and expectation is that prices will
continue to be high for foreseeable future
12Electricity Generations Growing Dependence on
Natural Gas
- Natural gas became the fuel of choice for new
power generation - Environmental advantages
- Shorter lead times of completion
- Improved efficiencies
- From 2000 to 2004, 200,000 Megawatts (MW) of new
power plant capacity was added to existing
capacity base of 903,000 MW - 94 percent of this new capacity was natural gas
fired - This has meant higher risks for power plant
developers - Exposure to higher fuel costs
- Exposure to price volatility
-
13Natural Gas The Fuel of Choice For Electric
Generation in late 1990s early 2000s
Annual Additions To Electricity Generation
Capacity By Fuel, 1950-2002 (Gigawatts)
Source Energy Information Administration /
Annual Energy Outlook 2004
14The Generation Outlook From Boom to Bust to
Boom Again
- Initially, markets were vastly oversupplied by
much as 25-40 excess and some by as much as 100 - Surplus plants were mothballed, and reserve
margins brought back into reasonable balance - However, current forecasts indicate new
generation needed - 130 GW over next 10 years
- Possibility of near-term shortages in certain
urban areas (i.e., New York City, Washington) and
subregions - Most will be new baseload
- High gas costs mean any new gas capacity will be
used for peaking only - 150 coal plants currently under development, but
will face environmental challenges - New nuclear capacity also being proposed
15An Electricity Delivery System In Need of New
Investment
Source E.Hirst, Transmission Crisis Looming?
Public Utilities Fortnightly, September 15, 2000
- Transmission investment declined in real dollar
terms for 23 years from 1975 to 1998, while load
has more than doubled - Estimated 25 percent increase in transmission
investment necessary to meet anticipated growth
in customer demand over next two decades
16Current Status of State Retail Power Market
Reforms
- Successful in providing commercial and industrial
customers choice of providers - Higher magnitude of volumes purchased conferred
bargaining leverage - Sophistication driven by desire to lower costs of
doing business - Less successful doing likewise for residential
customers - Smaller volumes purchased per customer
- Savings negligible for time expended to shop for
alternative providers - Some states designed markets poorly, unduly
exposing customers to price risk (i.e.,
California) - Some states erred in imposing 5 6 year price
caps or conferring discounts on rates provided by
incumbent utility, disincentiving customers from
switching to new provider, and discouraging new
market entrants - No additional states will embark on experiment
- In states where price caps are being lifted,
political controversy has ensued
17Energy Policy Act of 2005 (EPAct) Alteration of
the State-Federal Relationship
- Legislative thrust is remedial in areas where
issues have persisted or gaps have emerged - Transmission siting
- Responsibility for reliability
- Legislation clarifies responsibility between
states and federal government, creates new
decision-making mechanisms, and establishes
procedure for resolving conflicts -
18The Transmission Issue
- During previous decades, utility service was
primarily local, and transmission was built to
suit local needs - States and local entities held authority to site
transmission - Markets have now assumed, multi-state, regional
proportions - Concern is that states would behave parochially
in deciding whether to allow new transmission to
be built, if no immediately discernible benefit
for state - Past instances cited of state resistance to -- or
delay of -- siting of interstate transmission
lines ( Example 765-kV line proposed by American
Electric Power in Virginia and West Virginia
which took 16 years)
19The Energy Policy Act Remedy
- Grants Federal Energy Regulatory Commission
(FERC) authority to approve the siting of
electric transmission facilities located in
national interest electric transmission
corridors - if states lack authority to do so or they cannot
consider interstate benefits of a project - or when the applicant is essentially a
wholesale-only transmitter - or when states have withheld approval for more
than a year or have conditioned approval in such
a way that the project will not significantly
reduce congestion or would not be economically
feasible - The Department of Energy (DOE) must identify such
corridors, which may include any geographic area
experiencing electric transmission capacity
constraints or congestion, within one year of
enactment and every three years thereafter - Holders of a FERC siting permit may exercise
eminent domain authority in federal court,
allowing court to preempt state decision - DOE has identified critical congestion areas
for comment and is expected to designate
national interest electric transmission
corridors by end of year
20Reliability Responsibility Now Federalized
- Pre-Energy Policy Act Enactment
- Reliability responsibility rested primarily with
states at local distribution level (regulating
outage frequency, continuity of service) - Industry reliability requirements for planning
and operation of bulk power system were voluntary
- Northeast-Midwest power outage was a watershed
- Energy Policy Act Federalizes Reliability
- Congress directed development of mandatory,
federally (FERC) approved, enforceable
reliability standards - FERC will certify a single Electric Reliability
Organization (ERO) to oversee reliability of US
portion of interconnected North American
Bulk-Power System, subject to FERC oversight - The ERO may delegate enforcement responsibilities
to a Regional Entity, but only after the FERC
approval of delegation agreement - Either ERO or Regional Entity may propose
reliability standards, monitor compliance, or
impose a penalty on user, owner or operator for
standard violation, subject to review by, and
appeal to, FERC -
21FERCs Reliability Standards Balancing National
Vs. Regional Interests
- FERC seeks standards uniformity as much as
possible across interconnected North American
bulk power system - Will permit regional differences to extent more
stringent than continent-wide or necessitated by
physical system - Will not defer to ERO or Regional Entity with
respect to the effect on competition of proposed
reliability standard - North American Electric Reliability Council
applied for, and has been designated by, FERC to
be the ERO
22The States Authority No Preemption, But FERC
Resolves Alleged Conflicts
- Energy Policy Act savings clause State action to
ensure the safety, adequacy, and reliability of
electric service within that state not preempted
as long as such action is not inconsistent with
any federal reliability standard -
- FERC rule sets out procedure for resolving
before FERC all federal/state conflicts upon
petition by ERO, Regional Entity, or other
affected person
23State Authority to Form Regional Advisory Bodies
- Upon petition of at least two-thirds of the
states within region with more than one-half of
their electric load served within the region - Requires member from each participating state in
the region, appointed by governor of each state - May include representatives of agencies, states
and provinces outside of US - Regional Advisory Body may provide advice to ERO,
Regional Entity, or FERC concerning - Governance of an existing or proposed Regional
Entity within the same region - Whether reliability standard proposed to apply
within the region is just, reasonable, not unduly
discriminatory or preferential, and in the public
interest - Whether fees for all activities proposed to be
assessed within the region are just, reasonable,
not unduly discriminatory or preferential, and in
the public interest and - Any other responsibilities requested by the FERC
- FERC may give deference to Regional Advisory Body
that is organized on an Interconnection-wide
basis - Regional Advisory Body comprised of 10 Western
states has been formed -
24What does the Power Sector Look Like Today?
- The power sector is no longer a declining cost
industry - Cost of fuel for electricity (coal natural gas)
will continue to rise, and for natural gas could
be volatile - Lack of transmission investment in prior years
will require significant upgrades to meet demand
expectations, further boosting consumer energy
costs - The need for higher rates will place
extraordinary pressure on state utility
commissions charged with regulating electric
utility companies - Rate increases will likely be politicized,
heightening risk for investors
25Lessons Learned
- Power sector reform has had mixed outcomes
- Induced utilities to operate more efficiently and
to focus on core capabilities (good) - Created boom/bust generation cycles in the
absence of long-term planning (bad) - We will likely be thrust into more robust
long-term resource portfolio management - Reforms have spawned a variety of utility
business models - Traditional vertically integrated
- Distribution companies with competitive wholesale
but closed retail markets - Distribution companies with competitive wholesale
and open retail markets - Generation-only companies
- Transmission-only companies
- These various business models could pave the way
for learning which are optimum from a consumer
and investor standpoint - We learn from our mistakes since we have made
many, we must be learning!
26Thank You For Your Attention
Xie Xie
27Robert W. Gee President Gee Strategies Group
LLC 7609 Brittany Parc Court Falls Church, VA
22304 U.S.A. 703.593.0116 703.698.2033
(fax) rwgee_at_geestrategies.com www.geestrategies.co
m