Time Out For Safety - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Time Out For Safety

Description:

Chain block and jack were removed after welding of 2 flanges. ... The A-Frame, chain block and 5 Tons jack used earlier for alignment purposes ... – PowerPoint PPT presentation

Number of Views:758
Avg rating:3.0/5.0
Slides: 16
Provided by: SEK3
Category:
Tags: jackblock | out | safety | time

less

Transcript and Presenter's Notes

Title: Time Out For Safety


1
Time Out For Safety
  • BSP/BLNG
  • 25th August 2004
  • BSRC Ball room

2
This gentleman would have celebrated his 31st
birthday on 25th August BUT..
3
Fatality Incident on 18 Aug 2004
4
SEQUENCE OF EVENT


CG

2


12/08/04

13/08/04

1

32 T SPOOL


11/08/04
Primary Support


(WEDNESDAY)


4

3

16/08/04 UNTIL
16/08/04 UNTIL
1600HRS

1600HRS




5
PICTORIAL REPRESENTATION
6
Tee-Piece Fabrication Fatality Time Out25 Aug
2004
  • Purpose
  • To share preliminary findings of the
    investigation.
  • Cascade immediately the preliminary findings to
    all BSP staff and contractors within the next 48
    hours
  • Implement immediate actions recommended by the
    investigation team to prevent recurrence
  • Note that this is only the beginning and there
    are many more areas that we need to work on in
    more detail.

7
Fatality Incident on 18 Aug 2004
  • Incident Details
  • At Zainal Daud (ZD) Fabrication Yard (G25) at
    7.30 a.m.
  • Victim Mr. Lee, 31 years old Malaysian working
    for Chin Wui Heng Welder Enterprise
  • Occupation Senior Marker, 8 yrs experience
  • Injury Death from severe head injuries.
  • Survived by Spouse 4 years old son.
  • Project Single Buoy Mooring (SBM) Metering
    (Phase 2)
  • Main Contractor Warner Company Sdn. Bhd.
  • Sub-contractor Zainal Daud Sdn. Bhd.
  • Sub sub-contractor Chin Wui Heng Welder
    Enterprise

8
Fatality Incident on 18 Aug 2004
  • Facts Findings (1)
  • Fabrication Yard Work delayed whilst waiting for
    Tool Box Talk
  • 32 pipe Tee piece 300 (1.3 tons) partially
    completed (2 flanges welded on). Suspended,
    awaiting material.
  • Was supported by 2 primary ground supports.
  • Chain block and 5 tons jack were used whilst
    fabrication was in progress for alignment
    purposes.
  • Chain block and jack were removed after welding
    of 2 flanges.
  • No further adjustments of the primary supports
    were made to improve stability.
  • Deceased was assigned the role of supervisor of
    the above fabrication activities.

9
Fatality Incident on 18 Aug 2004
  • Facts Findings (2)
  • Initial calculations indicate Tee-piece Centre of
    Gravity shifted significantly effectively on
    the verge of tilting.
  • Since materials were not available, no further
    work was carried out. Two days later, the
    deceased (ca. 70 Kg wt) attempted to sit on outer
    rim of Tee-piece flange.
  • Tee piece slipped toppled over crushing victim
    on the head

10
Findings
  • Direct Causes
  • The Tee piece became unstable after the
    installation of the two flanges. The centre of
    gravity had shifted but the primary supports were
    not adjusted.
  • For unknown reasons, the deceased attempted to
    sit on the vertical flange of the Tee piece
  • This action caused the unstable Tee piece to slip
    and topple over.
  • The deceased suffered severe head injuries after
    being crushed by the Tee piece.

11
Findings
  • Indirect Causes (1)
  • The A-Frame, chain block and 5 Tons jack used
    earlier for alignment purposes were removed
    leaving the Tee piece on the two unadjusted
    ground supports.
  • Although a co-worker, recognising a hazard,
    re-secured the Tee piece on a chain block, this
    was subsequently removed.
  • The instability of the Tee piece had not been
    communicated to the others. Enforcement of Duty
    to Stop was inadequate.
  • General lack of hazard awareness of the
    workforce.
  • Hazard Identification Plan (HIP) for the
    contractor fabrication yard was not developed.
  • Lack of barricades and warning signs around
    hazardous areas.
  • No designated rest area

12
Findings
  • Indirect Causes (2)
  • Lack of effective supervision.
  • Lack of planning Work started on the Tee piece
    before all the materials had arrived.
  • Contract HSE Management
  • Lack of clarity between contractor,
    sub-contractor sub-sub-contractor on
    responsibility for HSE management
  • The main contractor was required under its
    contract with BSP to play a leading role in HSE
    implementation, not just the subcontractor
  • There were early warning signs of a lack of
    commitment to safety such as not following up on
    repeated violations identified during site
    visits.

13
Immediate Action (1)
  • Please undertake the following
  • Survey work supports at all worksites
    immediately. Rectify where work supports are
    unsafe or inadequate. Communicate any unsafe
    conditions found.
  • Ensure you have a HIP for every stage of your
    project, including the fabrication stage, both at
    BSP and the contractor worksites.
  • Include HIP in Tool Box Talk. Address safety of
    worksites, even when unattended.
  • Ensure provision and enforce use of designated
    rest areas at worksites.

14
Immediate Action (2)
  • Please undertake the following
  • Supervisors contract holders/managers
    accountability for safety
  • Do you know the full extent of your role?
  • Do you know what you are accountable for?
  • Are you discharging your responsibility?
  • Confirm who is responsible for sub-contractor HSE
    management.

15
Areas requiring further work
  • We will need to strengthen the culture of
    intervention (e.g. PAKAT, House Rules,
    Consequence Management).
  • We will require senior management of all
    contractors, all direct and indirect
    sub-contractors to demonstrate commitment to HSE
    by, for example, site visits and mandatory joint
    HSE meetings.
  • We will require contract holders to include all
    direct and indirect sub contractors in HSE
    performance reviews.
  • Review appropriateness of contracting strategy to
    ensure HSE responsibilities can be effectively
    exercised.
Write a Comment
User Comments (0)
About PowerShow.com