Title: NovaChip
1NovaChip
2What is NovaChip
- Ultra-thin polymer modified asphalt
- surface treatment.
- Combines open graded hot mix asphalt
- with emulsified asphalt polymer-modified
- membrane.
3Features Benefits
- Superior bond to the existing surface
- Increases skid resistance, reduces noise
- Ultra-thin application eliminates the need for
utility adjustments. - Minimal traffic disruption, requires a single
lane closure - Expected life cycle of up to ten years with crack
sealing.
4Features Benefits (cont..)
- Does not affect overhead clearances on bridges,
overpasses, signs, and other structures. - Reduces hydroplaning and reduces spray on wet
roadways.
5Equipment
- Specialized NovaChip paver
- Rollers
- Water truck
6Materials
- Open graded hot mix asphalt
- NovaBond, a polymer modified asphalt
- emulsion.
7History of NovaChip
- 1988 - First trial in France
- 1992 - Introduced in the United States
- 1992-93 - Projects in TX, AL, PA, and NJ.
8Application Rates
- Novabond(TM) emulsion membrane 0.13 - 0.25
gal/sy - Ultra-thin hot mix asphalt overlay
- Minimum application rates Type A - 45-55
lbs./sy Type B - 50-65 lbs./sy Type C -
55-70 lbs./sy - Total Thickness 3/8 to 3/4
- Maximum recommended thickness 1-1/4
9Road Preparation for NovaChip
- Pavement should be in reasonably good
- condition.
- Pavement should be swept clean
- Pavement should be dry before lay-down.
- Crack seal all cracks ¼ wide or more
- Repair all failed areas with full depth
- Patching.
- Cover all utilities
10Applications for NovaChip
- Asphalt pavements
- Concrete pavements
- Airports
- Interstate highways
- Turnpikes
-
11NovaChip The Process
PHASE 1 during application (3/8 nominal size)
The Novabond Emulsion Wicks Up Around the HMA
Aggregates
Surface of Mix
7.5-10 mm coating on mix
Existing Pavement
12 Skid resistance test - PA
SR 422 Chester Montgomery Counties
NovaChip applied to existing PCC surface
Aug. 93 before - Dec. 93 after
13 NovaChip Paver
14 Receiving hopper. 4 screw augers help stop
segregation
15NovaBond is sprayed onto road surface inches in
front of the hot mix
16 Muhlenberg Township, PA
17Full depth patching crack sealing before
NovaChip
18 Paving Of NovaChip
19Rolling in static mode to seat aggregate material
20Care is taken when rolling along curb lines
21NovaChips open gradation allows water to
penetrate and disperse faster
22East Hanover Township, Lebanon County,
Pennsylvania Old Rt 22 before NovaChip
23Only very bad sections had full depth removal
repair
24Tack coat applied before leveling course of HMA
25Loaded trucks wait their turn to go into the paver
26Hot mix asphalt leveling course placed on Rt 22
27Leveling course before compaction
28Steel drum roller compacting hot mix asphalt
leveling
29Liquid NovaBond placed directly in front of
NovaChip hot mix screed
30NovaChip Lay-down on Rt.22
31Open graded NovaChip placed on hot mix asphalt
32NovaChip open graded mix
33NovaChip laid down ¾ inch compacted
34Roller only seats the aggregate in the NovaChip
35Hand work is sometimes necessary with NovaChip
36Center joint hardly noticeable
37Alatchua County, FL
38 Back of tamping screed
39 NovaChip
40 5 Minutes after lay down loaded trucks cross
pavement
41No material deterioration or displacement
42Traffic can be returned to the pavement quicker
43Orange County, Florida Rt 440
44Concrete two lane highway, pavement joints 2
inches wide.
45Expansion joints routed filled with flexible
hot mix asphalt.
46South lane NovaChip complete
47Traffic flow was uninterrupted
48Joint maker on NovaChip paver
49 NovaChip pavement mat
50Evaporating steam from the NovaBond
51 Finished pavement center
joint
52 Reduces spray hydroplaning
53 Traffic moves down Rt. 440
54 THANK YOU
- E.J. Breneman LP.
- 1117 Snyder Road
- West Lawn, PA 19609
- Phone 610-678-1913 or 610-636-0121
- e-mail mpolak_at_ejbreneman.com