UGelectronics Update - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

UGelectronics Update

Description:

... for construction and qualification of QM and FM UG electronics February 2005 ... QM2 UG-electronics qualification scheduled at SERMS on feb 11th ... – PowerPoint PPT presentation

Number of Views:24
Avg rating:3.0/5.0
Slides: 23
Provided by: fran643
Category:

less

Transcript and Presenter's Notes

Title: UGelectronics Update


1
UG-electronics Update
  • Feb. 5th 2008
  • A.Bartoloni, B.Borgia, F.Spada

2
UG-electronics in the TRD Gas System
3
QM design
  • Design of control electronics from EM to QM
    updated after test session in August 2004
  • Contract issued to GA Engineering for
    construction and qualification of QM and FM UG
    electronics ? February 2005
  • Radiation test of few components performed at
    Karlsruhe, under the supervision of Andrei
    Kounine, May 2005
  • Further modifications were introduced because of
    gas circuit changes, e.g. 24V to 30V

4
EM ? QM
  • Change power supply 24V?30V (supply for Kulite,
    Marotta valves, pumps, heaters)
  • Pumps power supply 12V directly from DC-DC
    converter, 24V with step-down circuit 30V?24V.
  • Heaters x CO2, Xe vessels on/off switches
    identical to Marotta valves switches
  • Added Kulite gauges
  • Dallas T sensors replacing GP-50 T n. 2
    dedicated links to USCM
  • Safest valves operation in magnetic field
  • Pumps variable load
  • Need to control vessel temperature
  • Need pressure measurement reliability
  • Add temperature measurements

No basic circuit was modified, i.e. ADC,
switches, serial link QM FUNCTIONALITY TEST JULY
2006
5
Components
  • TIM January 2007 questioned several elements in
    components list
  • Kounine revised the components list and marked
    the following ones
  • TPS73xx on AMS component list marked as
    NON-FLIGHT
  • SUB85N10-10 not on AMS part list
  • HI-508 not on AMS part list
  • AD620BR not on AMS part list
  • GA provided documents on rad test. The only
    remaining non flight was TPS73xx
  • TPS73XX can be replaced by LP2989, latch free.
  • LP2989 is not pin to pin compatible, therefore
    needs a new layout and a new PCB

6
QM to QM2..
  • Following the change of linear regulators
    TPS73xx, of power distribution scheme and several
    changes required by safest operations (short
    circuits on cables or components),
  • we had to design new QM UGxx boards with
    following major modifications
  • replace the TPSxxxx regulators with SEL free
    LP2989 (UGBS, UGBC, UGFV)
  • put limiting resistor on Kulites and GP50 power
    supply lines (UGBS, UGBC)
  • separate 12V power supply for UGPS and flipper
    valve (UGFV)
  • introduce LP2953 regulator to generate 24V for
    pumps high speed (UGBP)
  • introduce LP2953 regulator to generate 21V for
    analog mux (UGBP)
  • eliminate 3.3V DC-DC converter ?generate 3.3V
    from 5V on backplane
  • introduce Solid State Fuses (SSF) for short
    circuit protection on 5V, on each module
  • introduce pull-down resistors on Mosfet gates
  • introduce differential amplifier on Kulite inputs
  • eliminate UHVG (?redesign of backplane)
  • eliminate 2 UGFV and reduce 8 multiple channels
    to 4 (?redesign of pcb)

7
UGxx specifications
  • First draft v 1.4 (26/02/02)
  • Draft after EM test v 3.6 (17/05/05)
  • Last draft v 4.2 (26/06/06)
  • In preparation v 5.0 (2008)

8
UG Backplane power connections
UGBS-A
UGSCM-A
UGSCM-B
UGBS-B
UGBC-A
UGBS-B
UGFV-A
UGFV-B
GND
5.6V-A
UGPD
5.6V-B
UGPD
UGPD
12.5V-A
12.5V-B
UGPD
29V-A
UGPD
UGPD
29V-B
3.4V-A
UGPD
3.4V-B
UGPD
9
UGxx 5V power supply
5.6V
5V
2.5V
SSF CAEN
LR
FPGA
LR
LP2989-2.5
3.3V
LR
LVDS
LP2989-3.3
RS232
ADC
GND
10
UG-crate Layout
  • 2 boards to control the BOX-S (UGBS)
  • 14 solenoid valves
  • 5 heater
  • 7 pressure sensors
  • 1 Dallas temperature sensors chain
  • 2 boards to control the BOX-C (UGBC)
  • 2 circulation pumps
  • 4 solenoid valves
  • 2 pressure. sensors
  • 1 CO2 analyzer (RS232)
  • 1 MCA (RS232)
  • 1 monitor tubes
  • 2 boards for Manifold control (UGFV)
  • 2 to control the 40 flipper valves located in the
    manifolds
  • logics for 20 pressure sensor signals
    multiplexing will be inserted in the UGFV boards

UG-Crate
UGBP
UGBS-A
UGSCM-A
UGSCM-B
UGBS-B
UGBC-B
UGBC-A
UGFV-B
UGFV-A
LESS COMPONENTS BETTER RELIABILITY
11
UG-electronics Status
  • UGPS FM ready, tested, installed
  • QM1 UG-electronics currently used for Gas System
    tests
  • UG slow-control software and user interface used
    successfully on QM1 and QM2 UG-electronics
  • QM2 UG-electronics under functionality test
  • QM2 UG-electronics qualification scheduled at
    SERMS on feb 11th
  • UGPD (A. Koulemzine) crate integration with QM2
    boards done
  • UGPD QM2 waits for test window

12
Qualification and acceptance tests
Guidelines for the qualification and acceptance
tests of the AMS-02 electronics (Notes compiled
by G. Ambrosi for the AMS-02 Sub Detector
Electronic group, September 28th 2005. Feedback,
comments and corrections are welcome.) In this
short report are summarized the guidelines for
the definition of the qualification and
acceptance procedure to be implemented for all
the box electronics of the AMS--02 experiment.
The information and specifications reported are
derived from the discussions within the
Sub-Detector Electronics group, from the
indications of the CSIST people and from the
experience gained with the test of J/JT/JPD
crate. The guidelines reported here do apply to
the following hardware (for the detailed
nomenclature and list look in the Flight Design
) U- , T- , S- , E- ,J- , JT- ,TT- , UG- , M-
crate UPD, TPD, TSPD, ERPD, JPD, UGPD, TMPD,SHV,
RHV, EHV As a general rule no design
modifications are allowed between the QM and
FM/FS.
13
UG-electronics test set-up
  • UGTS
  • PC with CAN-bus interface to UGSCM
  • power supply
  • 29V A B
  • 12V A B
  • 5V A B
  • test station
  • gas system simulator GSS
  • PC ADC/DAC National Instrument

14
UG-electronics test set-up
TV CHAMBER
UG CRATE
GAS SYSTEM SIMULATOR
TEST STATION
29V 12V 5V
15
Modifying Gas System Simulator
16
Test Station Computers
Command Computer TRDGAS SlowControl Soft
Test Station Computer LabView
17
WINCAN command list
Configuration file
Time needed to perform all commands 15 minutes
18
TRD GAS SlowControl output
Command
Parameter/ Reply
Time
Date
  • Mon Jan 21 2008 154744 USCM boot  0x1A1 Mon
    Jan 21 2008 154812 P2a  read  2003 Mon Jan 21
    2008 154902 V1a  open  10.00 Mon Jan 21 2008
    154942 V2a  open  10.00 Mon Jan 21 2008
    155012 V3a  open  10.00 Mon Jan 21 2008
    155046 H2   start 3.00 Mon Jan 21 2008
    155051 Pk2c read  2101 Mon Jan 21 2008
    155123 CP1  start F Mon Jan 21 2008 155146
    CP1  read  A F Mon Jan 21 2008 155221 CP1  stop

Initialize USCM
Read sensor P2a, reply in mV
Open V1a for 10 s
Open V2a for 10 s
Open V3a for 10 s
Start heater H2 for 3 mins
Read sensor Pk2c, reply in mV
Start pump CP1, Full speed
Read pump CP1 status (Active, Full)
Stop pump CP1
19
Q A tests
  • The tests will be performed at Terni, SERMS
    facility
  • Conduction of tests by Alessandro Bartoloni,
    Bruno Borgia, Francesca Spada GA engineers (R.
    Bellarosa, M. Tucceri) Perugia?

20
UG-electronics schedule / QM2
  • 21/01/08 QM2 boards ready
  • functional tests
  • 11/02/08 ready to start qualification tests
    (SERMS)
  • 29/02/08 end of qualification tests
  • ready to start tests at CERN
  • 14/03/08 end of tests at CERN ?
  • Go ahead FM

21
UG-electronics schedule / FM
  • 04/04/08 FM boards delivered by GA
  • Start acceptance tests _at_ SERMS
  • 21/04/08 end of FM boards acceptance tests

22
Acknowledgements
  • I wish to acknowledge GA Engineering not
    wearing out their patience for a contract
    protracted by almost
  • 3 years
Write a Comment
User Comments (0)
About PowerShow.com