Title: ObjectionsSuggestions on ARRTariff filings by APTransco
1Objections/Suggestions onARR/Tariff filings by
APTransco DISCOMS
- Presentation by
- K. Raghu,
- Associate President,
- APSEB Engineers Association
2This presentation consists of
- Violations observed in the Merit Order Dispatch
- Factors which may affect actual revenue gap
- Need for review of Power Purchase Agreements.
- Investments by APTransco/ DISCOMS and growing
interest burden. - Gas allocation and avoidable burden.
- PPA with APGENCO
- Reform Program
- Prayer to the Commission
3Violations Observed in the Merit Order Operations
- Spectrum PPA- Section 3.10.2 (dealing with the
Incentives) states that - the Board shall pay for actual generation and
Notional generation above the threshold level of
a PLF of 68.49 an incentive in the nature of
increased ROE in accordance with the following
4Violations Observed in the Merit Order Operations
- PLF Level of Incentive
- PLFlt 68.5 None
- 68.5ltPLFlt 80.5 0.4 increase in ROE for every
- 1 increase in PLF above 68.5PLF
- 80.5ltPLFlt85.5 0.5 increase in ROE for every
- 1 increase in PLF above 68.5PLF
- gt85.5PLF 0.6 increase in ROE for every
- 1 increase in PLF above 68.5PLF
5Violations Observed in the Merit Order Operations
- It also states that provided , however , that
to the extent Notional generation contributes to
achieving a PLF above 85 shall not be
considered for the purpose of Payment of
incentives - Hence, incentive is part of Fixed cost upto the
level of 85 PLF and it should be part of
Variable Cost above 85 PLF. - However, APTRANSCO treats the entire incentive as
a part of Fixed cost. - This is a clear violation of Merit Order
Operations.
6Violations Observed in the Merit Order Operations
7Violations Observed in the Merit Order Operations
- Thus energy from IPPs has two tariffs for the
merit order operations - upto 85 PLF, where incentive has to be added to
the Fixed cost - above 85 PLF, where incentive has to be added to
the Variable cost. - It appears that the APTransco has not made this
distinction. - The same principle is applicable for the other
IPP projects.
8Violations Observed in the Merit Order Operations
- It is also not clear how Lanco project was paid
incentive for the operations using Naphtha. - APTransco has paid an amount of Rs 0.40 crore to
the Lanco Kondapally project during 2002-03 as an
incentive. - Why incentive is paid for the operations
involving alternate fuel?
9Factors which may affect the actual revenue gap
- The total revenue gap projected by the APTRANSCO
and DISCOMS is Rs 2882 Cr. - Several factors, such as, change in consumer mix,
fall in hydro generation are affecting actual
revenue gap at the end of the Year, than what is
projected at the beginning of the year. - This year also some more factors are likely to
increase the gap between the revenue and
expenditure. They are
10Factors which may affect the actual revenue gap
- 1. BST projected by APTRANSCO is Rs 2.07, where
as the average power purchase cost shown by the
DISCOMS is only Rs 1.961. - Additional power purchase expenditure to the
DISCOMs is 3802.7 X (2.07-1.961) Rs 414.49
Crore. - 2. Wheeling charges APTRANSCO claimed an amount
of Rs 215 Crore from the proposed wheeling charge
of Rs 1.00/ unit.
11Factors which may affect the actual revenue gap
- This may not be realised, Since APTRANSCO in its
proposal on wheeling charges has considered the
component of power purchase cost to be average
cost of its purchases from all the sources. - However, this should be taken as the higher of
the following two - 1. Cost of Power purchase from the MOD.
- 2. Actual revenue that is realised for the
additional units supplied to compensate for the
losses to the Consumers of wheeled energy under
the existing agreements.
12Factors which may affect the actual revenue gap
- Also, the income from wheeling projected by the
APTransco from the existing wheeling charges ( 13
paise/ unit) should be deducted from the total
revenue from wheeling charges, to arrive at
additional revenue from the revised wheeling
charges. - We would like to know from the Licensee
- what is the amount of energy consumed by the
wheeled consumers, above their allocated share? - And what is the amount realised from this
additional energy sold to these consumers at
present?
13Factors which may affect the actual revenue gap
- We feel APTRANSCO may not realise the amount
projected in the ARR, as the amount collected
would not be sufficient to meet the additional
liability due to the burden of loss compensation. - 3. No returns APTransco and DISCOMS have not
claimed any returns for its operations for the
current and ensuing years. - APTransco/DISCOMS have claimed that they would
forego returns with the intention to keep any
tariff increases required to bridge the gap to
minimum and unavoidable levels only. - It is not necessary for APTransco to play the
role of the Govt. and forego legitimate claims on
revenue requirements. - If govt. decides not to place any additional
burden on the Consumers, it should compensate for
the gap in the form of additional subsidy.
14Factors which may affect the actual revenue gap
- The purpose of Reforms is to run the Licensees on
commercial lines. - This is also against the ESA, 1948 , which
provides for the min. ROR of 3 on net fixed
assets. - This amount is approximately equal to Rs 200
crore. - 4. Dismantling of Administered Pricing Mechanism
- Govt. has decided to dismantle the APM for LNG
and petrolium products. - If APM is dismantled for Natural gas , the
additional burden on APTRANSCO is more than Rs
550 crore, as all the IPP projects are gas based
ones. - 5. 24 Hour supply to Rural consumers APTransco
has announced that it will supply electricity to
rural consumers 24 Hours a day from Aug 2002.
15Factors which may affect the actual revenue gap
- This will increase the burden of power purchase
to APTransco without commensurate returns from
these consumer categories. - The loss due to supply of electricity to the
subsidized sections is of the order of Rs 100
Crore.( Assuming the cost to serve to be Rs
4.50/unit and realisation of Rs 1.50 / unit, and
total additional supply to rural consumers is
about 300 MU) - 6. Revenue from inter-state sales
- APTransco has claimed that it may realise Rs 350
Crore from inter-state sales. - This may not be realised, considering the fact
that already many states are facing the problem
of surplus energy.
16Factors which may affect the actual revenue gap
- We request the Licensee to declare the plans of
Inter state sales. - In this connection, We also request the Licensee
to study the impact of third party sales out side
the state as allowed in the MOAs for the some
short gestation projects, on its future marketing
plans. - The shortfall from inter state sales will be of
the order Rs 100 Cr.
17Factors which may affect the actual revenue gap
- Thus the total short fall in revenue
- Projected by LicenseesRs 2882 Cr
- Under estimation of BSTRs 414 Cr.
- Additional burden due to
- new wheeling proposal..Rs 250 Cr.
- RoR..Rs 200 Cr.
- Dismantling of APM..Rs 550 Cr.
- 24 Hrs supply to rural consumer..Rs 100 Cr.
- Short fall from inter state salesRs 100 Cr.
-
---------------------- - Total Revenue gap.. Rs Rs
4496 Cr -
----------------------
18Factors which may affect the actual revenue gap
- Other factors which are affecting(increasing )
the expenditure and revenue of The Licensees
every year - Fall in revenue due to
- Change in consumer mix.Rs 150 Cr
- Shortfall in Hydel generationRs 150 Cr
- There are several Other factors( Say impact of
ABT regime, consumer resistance to tariff hike),
which may adversely affect the Licensees
revenues. - Thus, the revenue gap for the Licensee for the
FY 2003 may vary between Rs 4000 Crore to Rs 5000
Crore.
19Factors which may affect the actual revenue gap
- APTRANSCO/ DISCOMS propose to bridge the above
gap through tariff hike and subsidy from the
govt. - The additional revenue from the tariff hike is
about Rs 481 Crore. This can only meet 16.6 of
the total gap projected by the APTRANSCO and if
all other factors mentioned above are also
considered, this amounts to only 10. - Thus the substantial amount should come from the
Govt in the form of subsidy.
20Factors which may affect the actual revenue gap
- It is very clear from the above that tariff hike
can not be the solution for the present crises
faced by the Licensees, and we should identify
the causes for the present situation and try to
address them. - Blind pursuance of the reform program, without
understanding the nature and working of the power
sector and ignoring the social realities will
only land us in a Orissa like situation.
21Need for review of PPAs
- There is a need for review of all Power Purchase
Agreements with the IPPs for the following
reasons - 1. Violation of GOI norms For ex while the GOI
guidelines provide for 16 return on equity for
the entire year, the IPPs are being paid the
above amount in 12 equal parts on monthly basis .
This is resulting in additional payment to the
IPPs. - 2. Harmful provisions in the PPA
- Comptroller and Auditor General in its reports
on GVK and Spectrum projects has identified
several provisions which are harmful to the
consumers, and recommended for the review of
these PPAs.
22Need for review of PPAs
- The Commission has also agreed with some of the
above issues raised in its order on PPA between
APTRANSCO and BPL Project. - Godbole committee also had identified several
issues which burden the consumers. For ex Fuel
arbitrage I.e. difference between the cost of
fuel actually consumed and as provided in the PPA
based on calorific value. - Inflated Capital costsFor similar capacity of
projects, there is abnormal difference with
regard to the capital cost. - For Ex BSES 220MWRs 700 Crore.
- GVK 216MWRs 870
crore. -
Spectrum.208MW748 Crore.
23Need for review of PPAs
- The BSES project is a new project and GVK and
Spectrum projects are completed long ago, still
having higher capital cost. The above figures may
further go up if revised capital cost proposals
are approved by the CEA. - Even the purchase of energy based on uniform
fixed cost / unit , as provided in PPAs with
short gestation projects appear to be on higher
side. - 3. Interest rates offered by the financial
institutions have drastically reduced. Hence this
may be taken into consideration to restructure
the debt portion of the capital cost of IPPs to
minimise the Forex risk and lessen the debt
repayment obligation. - In view of the above, we request the Commission
to review all the PPAs with IPPs.
24Why APTransco is sympathetic to IPPs?
- 1. Wheeling charges
- APTRANSCO has requested the Commission to
approve a wheeling charge of Rs 1.00/ unit. - This is based on its expenditure for the year
2001-02. - The actual expenditure for the year 2001-02 is
more than approved by the Commission, and the
expenditure for the year 2002-03 has further gone
up. - It is not clear why APTRANSCO has preferred not
to claim revised wheeling charge based on the
revised expenditure. - Moreover, in the original proposals on wheeling
charges APTRANSCO has not taken burden of cross
subsidy into consideration.
25Why APTransco is sympathetic to IPPs?
- 2. Fixed charge for GVK and Spectrum projects
- APTRANSCO has stated that it is adopting the
existing fixed cost level of Rs 195 crore for GVK
project and Rs 183 crore for the Spectrum project
for the ensuing year also. - This is in view of the revised proposals
submitted by the IPPs to the CEA for the fixed
cost revision. - If the revised fixed cost is not approved by the
CEA, this will result in higher payments to
theIPPs in the form of interest on these
additional amounts paid. - 3. Incentive payments to the Lanco project
- APTransco has paid an amount of Rs 0.40 crore as
incentive to the Lanco for the units produced
with fuel Naphtha. - What is the need to pay incentives when energy is
produced with alternate fuel?
26Investments and Growing interest Burden
- Interest payments approved by
APERC for the year 2001-02 Rs 470 crore. - Revised estimate of interest
payments for the year
2001-02 Rs 495 Crore. - Interest payment projected for
- the year 2002-03Rs 730 Crore.
- From the above it is clear that the burden of
interest is growing year after year on APTRANSCO.
27Investments and Growing interest Burden
- We feel this burden is due to the investments
made by the APTRANSCO which are not prudent. - For Ex For the year 2002-03 APTRANSCO has
proposed the following investments - On BPL Transmission Scheme..Rs 50 crore.
- On Krishnapatnam Transmission scheme ..Rs 40
crore. - On SGP-I Rs 50 crore
- On SGP-IIRs 20 crore.
28Investments and Growing interest Burden
- Among the above projects,
- PPA with BPL has not been consented to by the
Commission. - PPAs with Krishnapatnam and other SGP projects
have not been approved by the Commission yet. - In light of the revised load forecasts, the need
for above schemes is to be examined. - Also, in its strategy paper on Power, Govt. of AP
claimed that Rs 890 Crore is requiered to reduce
1 technical loss.
29Investments and Growing interest Burden
- The reduction in power purchase
- cost due to the above is ..Rs.80 crore.
- However, the interest burden on the investments
- is(_at_16 rate of interest...Rs 134 crore.
- If investments are made in the name of system
improvements, future capacity requirements
etc,...without regard to returns from these
investmentsthe entire system may collapse unable
to recover the costs.
30Investments and Growing interest Burden
- Even in Orissa huge investments are made on
Transmission and Distribution network, but failed
to recover the costs leading to collapse of the
entire system. - In view of the above, we request the Commission
to review the entire investment of APTRANSCO and
Discoms.
31Gas allocation-avoidable burden
- The discrimination shown in allocation of gas had
adversely affected the finances of the Licensee
and resulted in additional burden on the
consumers. - Non-existing projects like GVK (extension),
Konaseema, Vemagiri and Goutami have been
recommended by the Govt. AP for allocation of gas
and have subsequently been awarded firm
allocation by the GOI. - On the other hand, existing plants like APGPCL,
Lanco Kondapally do not have firm allocation to
their full capacity, forcing them to depend on
alternate fuel like Naphtha, resulting in higher
variable cost. - The additional burden due to non-availability of
gas to Lanco project is Rs 234 Crore from Lanco
project alone.
32Gas allocation-avoidable burden
- Hence huge savings can be achieved if gas is
allocated to the existing projects. - In light of the above, we request the Commission
to direct the Govt of AP to recommend GOI to
re-allocate gas to existing plants from
non-existing plants which have already obtained
gas allocation on firm basis. - In the event of firm allocation of gas to these
existing projects based on Govt. recommendations,
the PPAs may be revised to see that no incentives
are paid for extra PLFs that are achieved with
the availability of additional gas.
33PPA with APGENCO
- At present APGENCO is not allowed to get ROE,
incentives and recover depreciation from the sale
of energy to APTRANSCO. - It is stated that the above practice may be
continued for the next year, except that the
depreciation may be allowed to the extent of debt
redemption obligations. - This is not in the interest of the APGENCO which
is the best performing utility in the country. - For IPPs whose cost of supply of energy is much
higher than the APGENCO are allowed to get all
the above benefits.
34PPA with APGENCO
- Lanco project got an incentive for producing
energy at Rs 5.93 / unit making mockery of the
very word incentive. - On the other hand , APGENCO units which are
achieving national awards for their performance
are facing the threat of Closure/ backing down. - Hence, we request the Commission to put an end to
this discriminatory treatment and allow the
APGENCO to function on commercial lines. - A portion of variable cost from APGENCO units may
be treated as Incentive to be included in the
Fixed cost to protect the highly efficient
APGENCO units from the threat of closure/ backing
down.
35Allow Returns to APTRANSCO and DISCOMS
- APTransco and DISCOMS have not claimed any
returns for their operations for the current
and ensuing years. - APTransco/DISCOMS have claimed that they would
forego returns with the intention to keep any
tariff increases required to bridge the gap to
minimum and unavoidable levels only. - It is not necessary for APTransco to play the
role of the Govt. and forego legitimate claims on
revenue requirements. - If govt. decides not to place any additional
burden on the Consumers, it should compensate for
the gap in the form of additional subsidy.
36Allow Returns to APTRANSCO and DISCOMS
- The purpose of Reforms is to run the Licensees on
commercial lines. - This is also against the ESA, 1948 , which
provides for the min. ROR of 3 on net fixed
assets. - Even the performance of APTRANSCO and DISCOMS on
revenue front is exceptional, taking the total
revenue collections from about Rs 4800 crore to
Rs 6226 crore in two years. - However the financial crises faced by the
Licensees is due to the factors which are beyond
its control and lie with the Reform program
initiated by the Govt. of AP. - Hence, Licensees should be allowed to get Returns.
37Some important Issues
- Government subsidy
- The Commission in its Tariff Order for 2001-02
directed the Govt of AP, to provide subsidy to
the DISCOMS directly in view of the proposed
Privatisation of distribution to avoid cash flow
problems to the future private companies. - However, in view of the experience of Orissa,
where the private Distribution companies
defaulting payment to the Gridco, it is interest
of the Consumers to route the Govt subsidy
through the APTRANSCO.
38Some important Issues
- 2. Variable cost of RTS of APGENCO and NPTCs
Ramagundam station - It is not clear how the variable cost of NTPCs
Ramagundam station is Rs 1.49/ unit where as the
variable cost of RTS of APGENCO is only Rs 1.02/
unit, since both the stations are located in the
same region. - Moreover, NTPCs station is large in capacity
which should have resulted in lowering of
variable cost.
39Some important Issues
- 3. The Commission has imposed ban on third party
sales to protect the interests of the consumers. - The purpose of the above ban is to prevent the
subsidizing sections from leaving the APTRANSCOs
fold. - It is strange that APTRANSCO has projected cost
of supply from LVS power at Rs 9.74/ Unit for the
current year, and it proposes to pay an amount of
Rs 35 Crore towards fixed charges without
purchasing a single unit from the MPP. - Thus the purpose of imposing the ban got
defeated, and is only helping the private
parties. - We request the Commission to see that the
decision to ban third party sales will not harm
the interests of the Licensee and the consumers.
40Some important Issues
- MOAs with Financial Institutions
- The contents of the MOAs signed by the Govt of AP
and APTRANSCO with the financial institutions in
favour of Gas based projects are not made public. - It is not clear whether the APTRANSCO has taken
approval from the Commission to sign the above
MOAs. - It was admitted by the CMD/APTRANSCO in one of
the public hearings conducted by the Commission
that the MOAs allowed for the third party sales
outside state, and he also stated that the above
matter is not within the jurisdiction of the
APERC as the sales are outside the state.
41Some important Issues
- Now, APTRANSCO proposes to sell the surplus power
outside the state, and obviously the above third
party sales allowed in the MOAs will affect the
marketing plans of APTRANSCO to other States. - Thus, any matter which affect the finances of
APTRANSCO and the Discoms should come under the
purview of the Commission. - Hence, we request the Commission to review the
MOAs signed by the Govt. of AP and APTRANSCO with
the Financial Institutions. - We also request the Commission to direct the
Licensee to make the above MOAs available to the
Petitioner.
42Reform Program
CGS
C O N S U M E R S
IPPs
(APSEB single buyer)
captive
others
43Reform Program
CGS
DISCOM1
W H O L E S A L E C O M P E T I T I O N
C O N S U M E R S
IPPs
DISCOM2
DISCOM 3
AP GENCO
DISCOM 4
others
APTRANSCO RESTRICTED TO WHEELING ONLY
44Orissa Experience with the Model
- The proposed World Bank Model failed to achieve
its goals and miserably failed in Orissa. - Discoms have defaulted in payments to Gridco.
- No fresh investments have come.
- Failed to check Commercial losses leave alone
technical losses. - Consumer service deteriorated.
- Rural consumers are the worst sufferers of the
privatisation program.
45Orissa Experience with the Model
- Competition remained a myth.
- Distribution companies tried to hide their
profits and actual reduction of losses. - Benefits of efficiency improvements have not
percolated to the consumers. - Private Discoms inflated their costs. For ex
- cost of Earth rod which was about Rs 400/- prior
to reforms was inflated to Rs 40000/- after
reforms.(MPSEB Engineers Association Report).
46Orissa Experience with the Model
- In the absence of real competition and effective
check from civil society institutions and
consumers, private companies exploited the
consumers.
47Whither Andhra Pradesh Power Sector?
- GoAP in its strategy paper on Power, has stated
that it will privatise atleast one distribution
company during 2002-03. - If the Govt. goes ahead with the privatisation
policy, the power sector of AP will get into much
bigger crises. - In view of the above, we request the Commission
to recommend to the Govt. of AP to review the
entire reform process, and make amends wherever
necessary.
48Prayer to the Commission
- We request the Commission to
- To review the Merit Order Operations.
- To consider all the factors which will increase
the revenue gap, and direct the Govt. to
compensate APTRANSCO/DISCOMS with suitable
subsidy. - To review all the existing PPAs with the IPPs.
- To review the investments that are being made as
part of the Reform Program. - To review the MOAs signed by the Govt. of AP and
APTRANSCO with the Financial Institutions. - Not to discriminate APGENCO and allow returns to
APTRANSCO and DISCOMS. - To recommend to the Govt. of AP to review the
entire reform program and make suitable amends
wherever necessary.
49Thank you
APSEB Engineers Association