Title: Project Location: Nyamilu, Kenya
1Implementation Trip for EWB-LSU
- Project Location Nyamilu, Kenya
- Chapters EWB-LSU Dartmouth-EWB
- Brief Description of Project
- Installation of 3.6 miles of water distribution
piping - Construction of ferrocement water storage tanks
- Construction of 13 water distribution points
- Project Risk Level Level 2
- Dates of this Implementation Travel July 12
August 21
2Background
- Nyamilu is a small farming community
- located in southwest Kenya.
- Constant water shortages and outbreaks of
- waterborne diseases are common in this
- region due to the limited availability of
- water.
- The situation has also been compounded by
- an ongoing drought making a reliable water
- system all the more necessary.
3Background (cont.)
- The communitys struggles pressed one of
- the villagers, Jerry Baraza, to seek help
- from EWB-USA
- In Fall of 2004, EWB chapters at
- Dartmouth College and Louisiana State
- University adopted The Nyamilu
- Community Water Project
4Travel History
- Phase I
- The Dartmouth-EWB team traveled to Kenya in the
Summer of 2005 to install a new well and complete
a site assessment. - The Dartmouth team worked with the Nyamilu
community development leader to map the locations
of homesteads and current water sources using GPS
while meeting with the local people to get an
idea of the population of the village. - Each of the current water sources were tested.
Nearly every source had bacteria present.
5Travel History (cont.)
- Phase I
- The team estimated that there were nearly 1700
people living in the village. - After the survey was completed the group
consulted with community leaders and reviewed the
data to determine the locations of the
distribution points. - Nine distribution points around the village were
decided upon that would best accommodate the
communitys needs. - The group also contracted a drilling company to
have a 98 meter well drilled and installed a
solar-powered submersible pump at 37 meters.
6Contact Information
- Project Leads
- James Dupree (President) jdupre9_at_lsu.edu
(985) 855-2570 - Leah Lemoine
llemoi7_at_lsu.edu (337) 278-2520 - Hannah Murnen hmurnen_at_dartmouth.edu
(603) 646-7673 - Professional Mentors
- John Dupree JJDupree_at_bellsouth.net
(337) 523-1401 - Al Pawlowski
avp2_at_lsu.edu (225) 578-6834 - Faculty Advisor
- Dr. William Moe
moemwil_at_lsu.edu (225) 578-9174 - Health Point Person
- Blake Lemoine
jlemo22_at_lsu.edu - NGO/Community Contact
- Jerry Ochieng ochiengjerry_at_yahoo.com
254 722 792 414
7Project Team
- Andrew Bankston
- Chris Bergeron
- James Dupree
- Blake Lemoine
- Leah Lemoine
- William Moe
- Al Pawlowski
- Rachel Stich
- Elaine Tate
8Travel Team
- Chapter Traveling EWB-LSU
- List of Travel Team Names
- James Dupree
- Chris Bergeron
- On-the-ground Contact
- Jerry Ochieng
- 254 724 664 254, 254 720 821 809, 254
722 792414 - Charles Onyango Otieno
- PO Box 54 Suna Migori, Kenya
- 254 735 509 747
9Travel Team (cont.)
- Nearest US Consulate Contact info
- Consular Section U.S. Embassy
- United Nations Avenue
- Village Market
- Nairobi, Kenya
- Nearest Hospital Contact Info
- Ojele Memorial Hospital,
- (59)-20346, www.omh2.org
- Suna-Migori, lt6 miles from village
- admin_at_omh2.org, info_at_omh2.org
254 375 3704 254 375 3700 (automated) kenya_acs
_at_state.gov Consularnairob_at_state.gov
10Travel / Transportation
- New Orleans (MSY) ? Nairobi (NBO)
- air transportation
- Nairobi ? Nyamilu
- Some of the supplies will be purchased in Nairobi
before traveling to the village. Truck
transportation will be arranged through Jerry
prior to traveling. - Additional transportation will be provided by
Jerry throughout the teams stay in Nyamilu. - July 14 - Morning
- arrive in Nairobi
- meet with Jerry
- begin collecting supplies and making arrangements
to transport them to the village - team will stay in Nairobi for the night
- July 15 Morning
- Depart for Nyamilu
- July 15 - Evening
- Arrive in Nyamilu
11Travel / Transportation (cont.)
- Nyamilu ? Supplies ? Nyamilu
- truck / driver provided by the village to collect
materials required for the project - travel times / supplies decided on site with
regard to - project itinerary
- predetermined materials list
- Nyamilu ? Nairobi
- Jerrys vehicle (Oldsmobile) / driver provided
- August 21 - Morning
- Depart for Nairobi
- Flight will depart in late evening
- Return to New Orleans, LA
12Accommodations
- Jerry Ochieng has agreed to board the team in his
guest house for the duration of the project. - Any hotel stays will be in Nairobi with expenses
covered by team funds. - Jerry has agreed to see to it that meals and
bottled water will be provided to the team for
the duration of the project. - Meals outside the village will be covered by
personal funds. - The team plans to visit the nearby city of
Migori, and the Kipingi village during the trip.
13Safety Emergency Plan
- Safety Plan
- Team will register with the U.S. Embassy in
Nairobi so that the Department of State can help
us if we require information, advice, or
emergency assistance. - Team members will always travel in groups of 2
or more. - All members shall know where everyone is at any
time. - A meeting place within the village will be
designated in case group members are separated in
Nyamilu. - A meeting place in Migori will be determined
for similar circumstances. - Anyone leaving the village will be escorted by
a villager. - Vehicle transportation will be provided with a
driver when required - All team members will receive recommended
vaccinations for Typhoid, Hepatitis, Malaria, and
Yellow Fever. - Emergency Plan Exit Strategy
- In the case of an emergency, the U.S. Embassy
will be contacted from Migori for further
instruction and assistance. There is a vehicle
available to us if we need to leave the village.
14Safety Emergency Plan (cont.)
A first aid kit will be kept with the group along
with other important medications
- Insect Repellant
- Water purification tablets /
- portable water filters
- Hypodermic syringes to be used at
- a hospital
- Antidiarrheal medication (e.g.,
- bismuth subsalicylate, loperamide)
- Antibiotic for self-treatment of
- moderate to severe diarrhea
- Antihistamine
- Decongestant, alone or in
- combination with antihistamine
- Antimotion sickness medication
- Acetaminophen, aspirin, ibuprofen, or other
- medication for pain or fever
- Mild laxative
- Cough suppressant/expectorant
- Throat lozenges
- Antacid
- Antifungal and antibacterial ointments or
- creams
- 1 hydrocortisone cream
- Epinephrine auto-injector (e.g., EpiPen), for
- severe allergic reactions
- All traveling team members will have proper
- International Travel Insurance covering
accidents, - sickness, and emergency evacuation.
15General Safety
- The United States Department of State recommends
that private American citizens in Kenya evaluate
their personal security situation in light of
continuing terrorist threats and the limited
ability of the Kenyan authorities to detect and
deter such acts. - They recommend that Americans who travel to Kenya
despite this Travel Warning should register
through the State Departments travel
registration website, https//travelregistration.s
tate.gov. - By registering, American citizens make it easier
for the Embassy to contact them in case of
emergency.
16General Safety (cont.)
- There is currently a drought affecting the Horn
of Africa. - Correspondence with Jerry has informed the group
that there is an increasing need for water in the
village due to the drought. - To date the northern regions of Kenya are facing
the most severe effects. - The team will monitor the effects of the drought
before the trip in order to avoid as many
problems as possible while in Kenya.
17Objectives of Implementation Trip
- The goals
- Provide a sustainable source of
- and clean and accessible drinking
- water to the entire village
- Provide sufficient water storage to
- serve in times of high demand
-
- Teach villagers the skills necessary to
- build, maintain and expand a reliable
- water system
18Equipment
- The team will bring certain equipment with them
in order to save time buying supplies in Kenya.
Important system components will also be brought
over in order to ensure these are good quality.
(customs) - Water testing equipment???
- Measuring / surveying equipment
- Electrical equipment Voltmeter, wire
cutters/strippers - Various valves for distribution points and mains
- PVC bushings, valves
- All listed equipment complies with FAA and Kenya
Customs regulations and can be checked on to
airlines.
19Technical Description of Project
- System Capacity
- After the new well was drilled a 24 hour pump
down test was performed to determine the recharge
rate. - The well was rated to be able to provide a
constant 1.2m3/h or about 5.3gpm based on the
drilling companys tests. - With the solar pump running for a full six hour
workday the well can provide just over 1900
gallons to the community. - At this capacity the community will be able to
draw a maximum average of 1.12 gallons (4.24L)
per person each day.
20Technical Description of Project
- During Dartmouths trip a solar pump was
installed with a maximum head rating of 30
meters. - Since there was no figure for the output of the
well when a pump was bought this resulted in the
selected pump not being able to utilize the full
capacity of the well. - In order to make having a large distribution
system worthwhile a new pump will need to be
installed. - Lorentz PS600 HR-20 (Max flow 3.6m3/h)
21Technical Description of Project
- Dartmouth recommended buying a new pump in Kenya
since they are readily available. - A replacement pump will need to be able to
support a maximum head of 180 feet while
providing a daily average output of 7.2m3.
22Technical Description of Project
- Water Storage
- The EWB team plans to provide the community with
a 5 day storage capacity (40,000L) in order to
make the system more reliable and convenient. - Different storage methods were examined and a
ferrocement tank was determined to be the best
choice. - With many members of the community willing to
provide assistance with construction a low cost
yet highly reliable water storage tank could be
built. - This self-help effort will allow funds to be
spent on expanding the system rather than on
labor and expensive materials. - 0.03/Liter
23Technical Description of Project
- The design and construction of ferrocement water
storage has been carefully studied to better
ensure a good quality tank can be built. A local
resident with experience building water
distribution and storage systems will also be
available while working in Nyamilu. - In order to gain experience in building a tank,
the team will design and build a practice tank
prior to implementation. Experience will also be
gained in mixing and using concrete along with
installing PVC piping. - Smaller Thai Jar type ( lt 3m3) tank
construction will also be studied in order to
possibly provide the volunteers a water storage
option that can be easily learned and repeated. - During construction, observations will be made in
order to develop better time management. This
will be utilized during implementation when time
will be limited.
24Technical Description of Project
Water Storage, Art Ludwig
25Technical Description of Project
- Distribution Points
- There are 13 proposed locations throughout the
village where water will be available. - Each point will be constructed with galvanized
iron pipe and a concrete slab to protect the
underground piping. - All locations will have a separate shut off in
the case that the point needs to be repaired
allowing the rest of the network to remain
unaffected.
26Technical Description of Project
27Technical Description of Project
- The distribution system consists of over 3.6
miles of PVC piping. - In order to accurately calculate the behavior of
the system under working conditions WaterCAD
software was used. - The system has been designed to provide no less
than 5 gpm when all distribution points are in
use. - The following map presents the topographical
layout of the village along with the proposed
pipe layout.
28(No Transcript)
29Technical Description of Project
Static Pressures
Dynamic Pressures
30A detailed view of the systems performance.
(all points at 5gpm)
31Community Participation, Education Ownership
- The NGO, Jerry, has assured us that a group of
ten volunteers will be available to help with the
project. -
- Excavation of trenches for the pipes and
collection of certain materials will be completed
prior to the teams arrival. - The volunteers will work with members of EWB-LSU
for the duration of the implementation to assist
in completing the project and to gain knowledge
on maintaining and building a water system. - The importance of maintaining a clean water
source along with other safety precautions will
be stressed.
32Community Participation, Education Ownership
- The EWB team will meet each daily to divide the
days tasks between volunteers and students so
that the project may be completed in an efficient
manner. - During Dartmouths visit a team of leaders,
namely, The Nyamilu Community Development
Committee and experts from the community agreed
to be responsible for the administration,
operation and maintenance of the system. The
procedures necessary to operate the water system
will be covered throughout implementation.
33Implementation Metrics
- Technical
- EWB-LSU and D-EWB will remain in contact with
the community after implementation to see that
the system remains in good working condition and
to provide consultation regarding any problems
that may arise.
34Implementation Metrics (cont.)
- Health
- The water sources other than the current new well
have proven to be of severe health risk
containing such water-borne diseases as E. coli,
Dysentery, Cholera, and Typhoid. - If the new system is expanded to provide easy
access to all parts of the village it will help
to reduce many of these cases . - Water samples from the new well will be collected
and tested in order to assess the need for a
filtration system in the future. - Economics
- A reduction of water quality related health
issues will allow people to spend less time and
money treating those with such illnesses. Those
with other health issues will have a better
chance of getting the help they require. - Time spent by women walking to collect water each
day will be decreased significantly thus
providing them with opportunities to partake in
profitable opportunities such as farming.
35Community Involvement
- EWB-LSU has been in regular contact with the
community through correspondence with Jerry since
the start of the design process. - Periodic consultations with Jerry have helped us
to develop a system that will best accommodate
the needs of the community. - The communication between EWB-LSU and EWB-Kenya
has been very good. Both the team and Jerry feel
that this project will be a success. - The finished project will be able to provide
water to over 1700 people living in the village.
36Assessment for Future Project Phases
- Project assessments will be completed following
the completion of the current project for - Nyamilu
- The Kipingi Community
- A neighboring village
- Requirements and metrics of a project assessment
- Ability to communicate before and during design
phase - Magnitude of Impact
- Health metrics
- Economic impacts
- Land surveys
- Population surveys
- Population density
- Community participation
37Assessment for Future Project Phases (cont.)
- Information necessary to determine overall
project impact will be obtained by meeting with
and interviewing members of the communities. -
- The possibility of another project in this region
will depend greatly on the results of the current
project. - EWB-LSU feels that it is beneficial to
concentrate on a particular region in order to
plan future projects more efficiently.
38Assessment for Future Project Phases (cont.)
- Specific details regarding future project phases
in Nyamilu will examine the impact of - Water filtration
- It is unclear as to the exact quality of the
water being pumped from the well, a sand filter
or other means of purifying water may be
necessary as future phases. The water quality
will be tested on site. Preserved water samples
from the well will also be collected in order to
perform further quality tests following the
teams return.
39Assessment for Future Project Phases (cont.)
- Drip Irrigation
- Nyamilu relies mainly on the sale of crops for
income, an irrigation system could help to
further stimulate the economy in the village - The benefits of an improved irrigation system
will be determined through observations and
discussions with community members during
implementation.
40Assessment for Future Project Phases (cont.)
- Specific details regarding Kipingi Community
Assessment - Requirements Design and Implement a Permanent
Water Supply with a borehole, Submersible Pump,
Wind/Solar Power, Water Tank and limited
distribution with five water collection points
within the village for domestic use. - Water is currently collected from a nearby
communitys well but the residents are hostile
toward the Kipingi People because they belong to
a different county-administrative unit. - The community wishes to sink a borehole. Hydro
geological surveys have been carried out and a
suitable aquifer identified and beaconed. The
proposed borehole is 100 meters deep. The water
supply shall serve approximately 50 homesteads. - Communication with the village will be similar to
the current project through Jerry.
41Assessment for Future Project Phases (cont.)
- Specific details regarding Kipingi Community
Assessment - If possible the LSU team will evaluate the
communitys need for a water system by visiting
with the village and surveying members of the
community. - Land surveys will be completed to collect any
necessary information for designing a new system.
GPS and flexible tube water levels will be used
to collect the data.
42Budget Hours
- Budget breakdown
- Leah has been in charge of budgeting throughout
the project - Hours on the project
- Planning for this portion of the project began in
Fall of 2004 and has steadily progressed since. - The group worked an average of 2-3 hours each for
each week of planning. - The estimated total amount of time dedicated to
this project is 180 hours.
43Donors Funding
- Sources of funds and in-kind contributions
- Corporate Sponsors
- ??
- ??
- ??
- LSU Engineering Department
- LSU Organization Relief Fund
- EWB-LSU fundraisers
- Eat Out for Hunger
- Did your team meet its funding goals?
- The team has met nearly 60 of its goal.
Fundraising is still ongoing so that the complete
system can be built during implementation.
44Response to TAC Comments
- Suggestions from the TAC will be used to
improve our system and bring forth any aspects of
the project that may have been overlooked. The
information will be taken into consideration when
the final design is made.
45Project Lead Sign-Off
- I Dr. William Moe as the faculty advisor of this
project, have reviewed the technical and
logistical contents of this project, and approve
of the proposed design. I will also comply with
TAC recommended changes and make suggested
changes before traveling on the implementation
trip. -
- Signed ______________________
46Final Checklists before Travel
- The goal of the review process is to make sure
that your team has a successful implementation
trip - 1) Submit this presentation to the project
management staff and TAC liaison at
projects_at_ewb-usa.org. Turn in WITH the
following - Volunteer Waiver Form (605) for each person
traveling. Please submit all at one time. - 2) Prior to the TAC meeting The Project
Management Staff and the liaison will review this
presentation with the project lead, mentor and
other relevant team members via a conference call
prior to its presentation at the TAC meeting. - 3) Before final travel, your team should have the
following checklists signed off by the persons
listed below, and get a final OK from the EWB-USA
Project Staff - Travel Readiness Checklist (601) to project
staff - Personal Health Checklist (603) to teams
health point person (to be taken on the trip) - Detailed Field Equipment Checklist to mentor or
project lead - Proved this presentation emergency contact
information to each and every member of the team - Have each person review the Travel Tips
Presentation (602) - 4) The Project team will be responsible for
following up on TAC Comments and submitting
changes/revisions to the project staff - 5) The Project team MUST notify the project staff
of any changes to travel dates or travel teams.
Additional team members MUST send in Waivers
(605) prior to travel.