Title: Radiant Cooling
1Radiant Cooling In an Intensive Care Unit
Penn State
Senior Thesis 03
Keith Beidel Mechanical Option
2Presentation Outline
- Project Overview
- Mechanical
- Existing Conditions
- Redesign
- Controls
- Energy Recovery
- Radiant Panels
- Energy Analysis
- Cost Analysis
- Electrical
- Redesign
- Cost Analysis
- Acoustical
- Analysis
Conclusions
3Project Overview
Centre Community Hospital - East Wing Addition
- Located in State College, PA
- 50,000 Square Feet
- 3 Stories
New Addition will Include
- 12 Intensive Care Units
- Same Day Surgery Suites
- Medical Treatment Unit
- Cardiovascular Rehabilitation
- Executive Board Room
- 200 Seat Auditorium
- Medical Records
- Executive Offices (CEO, CFO, etc.)
4Project Team
Construction Manager Hickes Construction Archit
ect Burt Hill Kosar Rittelmann Associates MEP
Engineers GJAI Consulting Engineers
Structural Engineers Barber and Hoffman, Inc
5Presentation Outline
- Project Overview
- Mechanical
- Existing Conditions
- Redesign
- Controls
- Energy Recovery
- Radiant Panels
- Energy Analysis
- Cost Analysis
- Electrical
- Redesign
- Cost Analysis
- Acoustical
- Analysis
Conclusions
6Existing Mechanical Conditions
Cooling
- Nine AHUs serving 6 zones (3 for redundancy)
- Constant Volume DX with Air Cooled Condensers
- Constant SA Temperature of 55ºF
Heating
- Terminal Hot Water Reheat Coils
- 225 HP Boiler
ICU Unit Thesis Redesign Focus
- 100 Outdoor Air, All Air is Exhausted
- One Positive and One Negative Isolation Room
7Presentation Outline
- Project Overview
- Mechanical
- Existing Conditions
- Redesign
- Controls
- Energy Recovery
- Radiant Panels
- Energy Analysis
- Cost Analysis
- Electrical
- Redesign
- Cost Analysis
- Acoustical
- Analysis
Conclusions
8Mechanical Redesign
- First Floor
- Intensive Care Rooms
- 8,200 SF
- Most Critical Area of Addition
9- ICU Design Requirements and Criteria
- N 1 Redundancy
- 100 OA Flow
- Airflow Quantities to meet AIA Guidelines for
Design and
Construction of Hospitals and Health Care
Facilities, 2001 - Operation of 24 hours a day, 365 days of the year
- HEPA Filtration
- Meet Heating and Cooling Loads
10- Mechanical Redesign Concept
- Separate the Space Sensible and Latent Loads
- Use a 100 OA AHU to Satisfy Space Latent Loads
- Use Radiant Panels to Satisfy Space Sensible
Loads - Use an Energy Recover Wheel to Reduce Outdoor Air
Loads - Leave Existing Heating System (Terminal Coil
Reheat)
11Major Mechanical Components
Existing
New
- 70 Ton 12,285 cfm AHU (2)
- 70 Ton ACCU (2)
- Run Around Heat Recovery
- 20 HP Pump for HR
- 10,500 cfm Exhaust Fan (2)
- 25 Ton 6,895 cfm AHU (2)
- 25 Ton ACCU (2)
- Enthalpy Wheel (2)
- 6,400 cfm Exhaust Fan (2)
- Added Equipment
- 15 Ton Packaged AC Chiller (2)
- 10 HP CW Circulating Pump (2)
12- Mechanical Redesign Schematic
- 25 Ton 6,895 cfm AHU (2)
- 25 Ton ACCU (2)
- Enthalpy Wheel (2)
- 6,400 cfm Exhaust Fan (2)
- 15 Ton Packaged AC Chiller (2)
- 10 HP CW Circulating Pump (2)
13Presentation Outline
- Project Overview
- Mechanical
- Existing Conditions
- Redesign
- Controls
- Energy Recovery
- Radiant Panels
- Energy Analysis
- Cost Analysis
- Electrical
- Redesign
- Cost Analysis
- Acoustical
- Analysis
Conclusions
14System Controls
- Existing System has Pneumatic and Electric
Controls - The Radiant System Will Require More Precise and
Accurate Controls - Will be Controlled With A Direct Digital Control
System - Allows HVAC Components and Space Conditions Will
Be Easily Monitored and Adjusted at One Central
Control Station
15System Controls
Automated Logic M-Line Digital Controller
Inputs
Outputs
16System Controls
- TYP. ICU Room Control
- Constant Chiller Water Supply Temperature
- Variable Flow
- Thermostat Modulates Flow Control Valves
- Shutoff Valves for Maintenance
17Presentation Outline
- Project Overview
- Mechanical
- Existing Conditions
- Redesign
- Controls
- Energy Recovery
- Radiant Panels
- Energy Analysis
- Cost Analysis
- Electrical
- Redesign
- Cost Analysis
- Acoustical
- Analysis
Conclusions
18Energy Recovery
- Existing Energy Recovery is a Glycol Runaround
Loop - Provides Only Sensible Heat Recovery
- Does Not Perform Well in the Summer
- Requires a 20 HP Pump
- New Energy Recovery is a Semco Enthalpy Wheel
- Provides Sensible and Latent Heat Recovery
- Performs Well in the Summer and Winter
- Requires a Small Motor to Rotate the Wheel
19Energy Recovery
What About Cross Contamination?
- Wheel Utilizes a Purge Section
- Works on Pressure Differences
- Purged Air Cleans Wheels Face
- SA Always Sees Clean Wheel
- Final HEPA Filtration as Fail Safe
Cross Contamination Will Not Occur !
20Energy Recovery
The Enthalpy Wheel Reduces Total Load from 42.5
Tons to 24.1 Tons (43 Reduction) Outdoor Air
Load From 26 Tons to 7.6 Tons (71 Reduction)
21Presentation Outline
- Project Overview
- Mechanical
- Existing Conditions
- Redesign
- Controls
- Energy Recovery
- Radiant Panels
- Energy Analysis
- Cost Analysis
- Electrical
- Redesign
- Cost Analysis
- Acoustical
- Analysis
Conclusions
22Radiant Cooling Panels
- Redec Magic 6
- 2x2 Lay in Panels
- 28.6 BTU/SF Cooling Capacity
- Lightweight
- Easy Installation
- Good Architectural Aesthetics
23Radiant Cooling Advantages and Benefits
- Thermal Comfort
- The Body Loses Heat in Three Ways
- Convection Air Passing Over Body
- Evaporation Breathing and Perspiration
- Radiation Transmit Heat Through Skin
Heat Loss Through Radiation is the Most Pleasant
for a Human
Human Energy Balance
Chilled Ceiling 50 30 20
Non Chilled Ceiling 35 40 25
Radiation Convection Evaporation
Thermal Comfort is Hard to Quantify and Compare
but it is a Major Benefit
24Radiant Cooling Advantages and Benefits
- Reduced Air Drafts
- Can Be Critical in an ICUs Especially for Burn
Victims
- Reduced Plenum Depth
- Ductwork Depth is Reduced by 10
25Presentation Outline
- Project Overview
- Mechanical
- Existing Conditions
- Redesign
- Controls
- Energy Recovery
- Radiant Panels
- Energy Analysis
- Cost Analysis
- Electrical
- Redesign
- Cost Analysis
- Acoustical
- Analysis
Conclusions
26Energy Analysis
Using Carriers Hourly Analysis Program
48 Less Natural Gas Consumption
32 Less Electricity Consumption
27Energy Analysis
- Reasons for Reduced Energy Consumption
- Enthalpy Wheel Greatly Reduces OA Load
- Smaller Less Power Consuming HVAC Equipment
- Less Terminal Reheat Energy due to Reduced SA
- Energy Transportation Medium
- Water Has 4 Times More Heat Absorbing Capacity
Than Air - 3,480 cfm of Air 1 cf of Water in Energy
Removal - Requires Less Medium Transportation Energy
28Presentation Outline
- Project Overview
- Mechanical
- Existing Conditions
- Redesign
- Controls
- Energy Recovery
- Radiant Panels
- Energy Analysis
- Cost Analysis
- Electrical
- Redesign
- Cost Analysis
- Acoustical
- Analysis
Conclusions
29Mechanical Cost Analysis
First Cost Existing Equipment 240,612
New Equipment 311,688 New Equipment 71,076
More
30Mechanical Cost Analysis
Yearly Energy Cost Electric Rate 0.0416
0-40,000 KWH 0.0372 gt40,000 KWH Natural Gas Rate
4.15 mcf Existing System 44,901/yr Radiant
System 28,552/yr
Yearly Savings of 16,349
31Presentation Outline
- Project Overview
- Mechanical
- Existing Conditions
- Redesign
- Controls
- Energy Recovery
- Radiant Panels
- Energy Analysis
- Cost Analysis
- Electrical
- Redesign
- Cost Analysis
- Acoustical
- Analysis
Conclusions
32Electrical Analysis
- Radiant System Has Less Power Consuming Equipment
- Therefore Conductors, Conduit, Circuit Breakers
Can Be Downsized
Motor Full Load Current NEC 430-150 NEC
430-22 Conductor Must be Sized for 125 of
FLC Conductors NEC 310-16 Conduit NEC Table
C1 NEC Table 1 Ch. 9 Only 40 of Conduit to be
Filled Circuit Breakers NEC 440-22
33Electrical Analysis
34Panel Board
- All Equipment Will Be on Emergency Equipment
Panel NE1AA - Panel NE1AA Will Be Able to be Downsized
- Existing Continuous Amperage 517 A
- New Total Continuous Amperage 264 A
- Panel can be Downsized From 600A to 400A
- Conductor can be Downsized from 2 sets of 350
kcmil to one set of 600 kcmil - Conduit can be Downsized from Two 2-1/2 to One
3-1/2
35Presentation Outline
- Project Overview
- Mechanical
- Existing Conditions
- Redesign
- Controls
- Energy Recovery
- Radiant Panels
- Energy Analysis
- Cost Analysis
- Electrical
- Redesign
- Cost Analysis
- Acoustical
- Analysis
Conclusions
36Electrical Cost Analysis
Reduction in Panel NE1AA Results in a 3,432
First Cost Savings
37Presentation Outline
- Project Overview
- Mechanical
- Existing Conditions
- Redesign
- Controls
- Energy Recovery
- Radiant Panels
- Energy Analysis
- Cost Analysis
- Electrical
- Redesign
- Cost Analysis
- Acoustical
- Analysis
Conclusions
38Acoustical Analysis
- Ceilings Will No Longer Be Acoustical Ceiling
Tiles - Radiant Ceiling Panels Have Lower Absorption
Coefficients Than Acoustical Ceiling Tiles
Will These Lower Coefficients Effect the Room
Acoustics?
39Acoustical Analysis
Reverberation Times are Essentially Identical For
All Three Cases
40Acoustical Analysis
Room Acoustics Are Not Noticeably Affected or
Altered By the Use of Radiant Cooling Panels
Sound Power Levels Are Identical For All Three
Cases
41Presentation Outline
- Project Overview
- Mechanical
- Existing Conditions
- Redesign
- Controls
- Energy Recovery
- Radiant Panels
- Energy Analysis
- Cost Analysis
- Electrical
- Redesign
- Cost Analysis
- Acoustical
- Analysis
Conclusions
42Conclusions
The Redesigned Radiant Cooling Mechanical System
WILL
- Reduce Operational Cost by 16,349/yr
- Reduce Energy Consumption 48 Less Gas 32
Less Electricity - Cost 71,067 More Than the Existing Mechanical
System - Cost 3,432 Less Than the Existing Electrical
System - Reduce the Size and Capacities of Mechanical and
Electrical Equipment - Provide N1 Redundancy
The Redesigned Radiant Cooling Mechanical System
WILL NOT
- Alter or Affect the Rooms Acoustics
- Alter the Rooms Architectural Appearance
43Conclusions
INDIANA HOSPITALINDIANA, PA.WASHINGTON
HOSPITALWASHINGTON, PA.V.A. MEDICAL
CENTERPITTSBURGH, PA.ST. FRANCIS
HOSPITALPITTSBURGH, PA.GOOD SAMARITAN MEDICAL
CENTERJOHNSTOWN, PA.
44Recommendation
Simple Payback of 4.1 Years
Install the Radiant Cooling System
45Thanks and Appreciation
Dr. Mumma Thesis Advisor GJAI Consulting
Engineers Mr. Mike Jacobs Mr. Sean
Williams Mr. Harry Gephardt Mr. Tom
Skibinski Mr. Mark Linde TWA Panels Mr. Bob
Pruett Sun-EL Corporation AE Faculty Friends
46Questions ?