Title: Osceola County ATMS Master Plan


1
Osceola County ATMSMaster Plan
  • Stakeholder Meeting
  • July 13, 2006

2
Agenda
Agenda
1
1
Project Update
Project Update
2
2
Verify ATMS User Needs
Roles and Responsibilities
3
3
Verify Market Packages
User Needs
4
4
Conclusion
Verify Roles and Responsibilities
User Services
5
5
Next Steps
Market Packages
6
Next Steps
3
Agenda
Agenda
1
1
Project Update
Project Update
2
2
Verify ATMS User Needs
Roles and Responsibilities
3
3
Verify Market Packages
User Needs
4
4
Conclusion
Verify Roles and Responsibilities
User Services
5
5
Next Steps
Market Packages
6
Next Steps
4
Project Update
  • Identified Stakeholders.
  • Conducted Stakeholder workshops.
  • Identified and defined issues, needs, and goals.
  • Developed user services.
  • Evaluated current transportation system.
  • Inventory of legacy systems.
  • Identified planned projects.
  • Collected all existing agreements.

5
Agenda
Agenda
1
1
Project Update
Project Update
2
2
Verify ATMS User Needs
Roles and Responsibilities
3
3
Verify Market Packages
User Needs
4
4
Conclusion
Verify Roles and Responsibilities
User Services
5
5
Next Steps
Market Packages
6
Next Steps
6
Roles and Responsibilities
  • Osceola County TMC
  • Operate and maintain the Countys arterial
    network.
  • Work with emergency management agencies to
    provide real-time response to incidents on the
    roadway network.
  • Provide real-time traveler information to the
    public and transportation and emergency agencies.

7
Roles and Responsibilities
  • City of Kissimmee, City of St. Cloud, Osceola
    Parkway
  • Operate and maintain own network.
  • Coordinate with Osceola County.
  • Work with emergency management to provide
    real-time response to incidents on arterials.

8
Roles and Responsibilities
  • Osceola County Emergency Operations Agencies
  • Provide real-time response to incidents.
  • Coordinate with Road Rangers.
  • Work with other emergency operations and
    transportation agencies to
  • Create an integrated communications system,
  • Create standard operating procedures, and
  • Provide staff training that will lead to
    coordinated emergency response.

9
Roles and Responsibilities
  • FDOT District 5 Regional TMC
  • Operate and maintain the Regions freeway
    network.
  • Provide Road Rangers.
  • Operate and maintain the Condition Reporting
    System.
  • Work with emergency management agencies to
    provide real-time response to incidents on the
    roadway network.
  • Provide real-time traveler information to the
    public and to transportation and emergency
    management agencies.

10
Roles and Responsibilities
  • Floridas Turnpike Enterprise
  • Operate and maintain Floridas Turnpike roads.
  • Share fiber with Osceola County.
  • Work with emergency management agencies to
    provide real-time response to incidents on the
    roadway network.
  • Provide real-time traveler information to the
    public and to transportation and emergency
    management agencies.

11
Roles and Responsibilities
  • Orange County TMC
  • Operate and maintain Orange County arterial
    network.
  • Coordinate with the CRS and FDOT District 5 RTMC.
  • Work with emergency management agencies to
    provide real-time response to incidents on the
    roadway network.
  • Provide real-time traveler information to the
    public and to transportation and emergency
    management agencies.

12
Roles and Responsibilities
  • City of Orlando TMC
  • Operate and maintain City of Orlandos arterial
    network.
  • Coordinate with the CRS and FDOT District 5 RTMC.
  • Coordinate with the Orange County TMC.
  • Work with emergency management agencies to
    provide real-time response to incidents on the
    roadway network.
  • Provide real-time traveler information to the
    public and to transportation and emergency
    management agencies.

13
Roles and Responsibilities
  • LYNX
  • Operate and maintain the transit system.
  • Work with traffic management to share traffic and
    transit information.
  • Work with public safety agencies to assist in
    evacuations.

14
Agenda
Agenda
1
1
Project Update
Project Update
2
2
Verify ATMS User Needs
Roles and Responsibilities
3
3
Verify Market Packages
User Needs
4
4
Conclusion
Verify Roles and Responsibilities
User Services
5
5
Next Steps
Market Packages
6
Next Steps
15
User Needs
STAKEHOLDER MEETINGS
INITIAL NEEDS, OBJECTIVES, PROBLEMS AND ISSUES
USER NEEDS
USER SERVICES
MARKET PACKAGES
ATMS FRAMEWORK
IMPLEMENTATION PLANNING
ATMS MASTER PLAN
16
User Needs
  • The User Needs establishes the foundation of a
    successful ATMS framework by providing initial
    goals and objectives for the planning, design,
    deployment, and operation of a successful ATMS.

17
User Needs
  • Congestion Reduction
  • Primary issue regarding traffic in Osceola
    County.
  • Signal Timing and Coordination Improvements
  • Can yield the largest user benefits of ATMS.
  • Significantly improve arterial flow.
  • Maximize the efficiency of the existing roadway
    network.
  • Reduce vehicle emissions, fuel consumption, and
    vehicle degradation.

18
User Needs
  • Network Monitoring
  • Integrates ITS systems to provide real-time data.
  • Allows operations personnel to develop response
    plans, including the dispatch of incident
    response personnel.
  • Real-time traveler information available for
    public dissemination.

19
User Needs
  • Field Hardware Enhancements
  • Enhance interoperability between agencies.
  • Allow for significant ease in expandability and
    future enhancements and maintenance of the
    system.
  • System Communications
  • Provide pipeline for real-time data transmission
    needs.
  • Provide a platform for future expansion.

20
User Needs
  • Traffic Management Center (TMC)
  • House operations personnel and central system
    components.
  • Provide a central location to promote synergy
    among agencies.
  • Interagency Coordination and Operations
    Integration
  • Provide a single efficient regional operations
    system.

21
User Needs
  • Traffic and Traveler Information Dissemination
    System
  • Provide traffic information to drivers.
  • Incident information
  • Alternative travel routes
  • Greatly enhance information distribution to the
    traveling public.

22
User Needs
  • Incident Response and Management System
  • Allow emergency vehicles to respond to incidents
    in less time.
  • Allow for quicker incident response, recovery,
    and return to normal traffic flows.
  • Emergency Operations
  • Coordinate response and sharing of information
    between traffic management agencies and emergency
    management agencies (TIM).
  • Establish standard operating procedures.

23
User Needs
  • Emergency Preemption System
  • Provide improved arterial traffic flow for
    emergency response vehicles.
  • Improve overall call-response times and improve
    traffic safety along each of the preemption
    routes.
  • Security
  • Includes data security, transportation
    infrastructure security, security for personnel,
    and security for the region as a whole.

24
User Needs
  • Transit Signal Priority (TSP) System
  • Improve arterial travel times for transit
    vehicles in Osceola County.
  • Centralized Data Collection, Archiving, and
    Mining Systems
  • Important to real-time traffic analysis and
    information dissemination.
  • Essential in developing updated traffic
    management plans.

25
User Needs
  • Increased Staffing and Training
  • Increased staffing of qualified personnel to
    operate the Osceola County ATMS.

26
Agenda
Agenda
1
1
Project Update
Project Update
2
2
Verify ATMS User Needs
Roles and Responsibilities
3
3
Verify Market Packages
User Needs
4
4
Conclusion
Verify Roles and Responsibilities
User Services
5
5
Next Steps
Market Packages
6
Next Steps
27
User Services
  • Establishes the high-level services that will be
    provided to address identified problems and user
    needs.

28
User Services
  • Pre-trip Travel Information
  • Route Guidance
  • Traveler Services Information
  • Traffic Control
  • Incident Management
  • Public Transportation Management
  • Public Travel Security
  • Electronic Payment Services
  • Emergency Notification and Personal Security
  • Emergency Vehicle Management
  • Disaster Response and Evacuation
  • Archived Data Function
  • Maintenance and Construction Operations

29
Agenda
Agenda
1
1
Project Update
Project Update
2
2
Verify ATMS User Needs
Roles and Responsibilities
3
3
Verify Market Packages
User Needs
4
4
Conclusion
Verify Roles and Responsibilities
User Services
5
5
Next Steps
Market Packages
6
Next Steps
30
Market Packages
STAKEHOLDER MEETINGS
INITIAL NEEDS, OBJECTIVES, PROBLEMS AND ISSUES
USER NEEDS
USER SERVICES
MARKET PACKAGES
ATMS FRAMEWORK
IMPLEMENTATION PLANNING
ATMS MASTER PLAN
31
Market Packages
  • Market packages are the basic building blocks for
    an ITS. They represent groupings of defined
    elements that directly correspond to
    transportation services.

32
Market Packages
  • Archived Data Management
  • ITS Data Mart
  • ITS Data Warehouse
  • Advanced Public Transportation
  • Transit Fixed Route Operations
  • Multi-Modal Coordination
  • Advanced Traveler Information
  • Broadcast Traveler Information

33
Market Packages
  • Advanced Traffic Management
  • Network Surveillance
  • Probe Surveillance
  • Surface Street Control
  • Traffic Information Dissemination
  • Regional Traffic Control
  • Traffic Incident Management System
  • Traffic Forecast and Demand Management
  • Electronic Toll Collection
  • Standard Railroad Grade Crossing
  • Railroad Operations Coordination

34
Market Packages
  • Commercial Vehicle Operations
  • HAZMAT Management
  • Maintenance Construction Operations
  • Road Weather Data Collection
  • Weather Information Processing and Distribution
  • Roadway Maintenance and Construction
  • Work Zone Management
  • Work Zone Safety Monitoring
  • Maintenance and Construction Activity Coordination

35
Market Packages
  • Emergency Management Operations
  • Emergency Routing
  • Roadway Service Patrols
  • Wide-Area Alert
  • Early Warning System
  • Disaster Response and Recovery
  • Evacuation and Reentry Management
  • Disaster Traveler Information

36
Agenda
Agenda
1
1
Project Update
Project Update
2
2
Verify ATMS User Needs
Roles and Responsibilities
3
3
Verify Market Packages
User Needs
4
4
Conclusion
Verify Roles and Responsibilities
User Services
5
5
Next Steps
Market Packages
6
Next Steps
37
Next Steps
  • Finalize Inventory of Legacy Systems document.
  • Finalize Requirements Tech Memo I.
  • Develop ATMS Framework.
  • Develop TMC Concept Design.
  • Develop Implementation Plan.

38
Questions?
39
Thank You
Andy Lucyshyn, P.E., PTOE Project
Manager PBSJ andylucyshyn_at_pbsj.com 407.647.7275
Craig Zetwo, P.E. Project Manager Osceola
County czet_at_osceola.org 407.343.2600