DESIGN OF DEEP FOUNDATIONS - PowerPoint PPT Presentation

1 / 54
About This Presentation
Title:

DESIGN OF DEEP FOUNDATIONS

Description:

DESIGN OF DEEP FOUNDATIONS George Goble Consulting Engineer – PowerPoint PPT presentation

Number of Views:427
Avg rating:3.0/5.0
Slides: 55
Provided by: frank499
Category:

less

Transcript and Presenter's Notes

Title: DESIGN OF DEEP FOUNDATIONS


1
DESIGN OF DEEP FOUNDATIONS
  • George Goble
  • Consulting Engineer

2
In this Lecture I Will Discuss the Deep
Foundations Design ProcessBoth Driven Piles and
Cast-in-Place Systems Both Geotechnical and Some
of the Structural Aspects
3
MY BACKGROUNDStructural Engineer Minor in
Soil MechanicsExperience in Construction and
Several Years as a Structural DesignerDesigned
Several Large Pile FoundationsThirty Years as a
College Professor Teaching Structures and
Mechanics, Emphasizing DesignResearch on Optimum
Structural Designand onthe Dynamics of Pile
DrivingManaged the Research that Developed
Dynamic Methods for Pile Capacity
PredictionFounded PDI and GRLNow Have a Bridge
Testing and Rating Business
4
WHY DO THIS?
  • Driven Pile Design is Often Not Well Done
  • Not dangerous but excessively conservative
  • Design process not clearly understood
  • Large cost savings possible
  • Capabilities of modern hammers not recognized
  • Many job specs are poorly written

5
FUNDAMENTAL ADVANTAGES OF THE DRIVEN PILE
  • We know the material that we put in the ground
    before we drive
  • Because it is driven each pile penetrates to the
    depth required to get the capacity
  • Capacity can be determined accurately by driving
    observations

6
FOUNDATION DESIGN PROCESS
  • Process is Quite Complex (Unique)
  • Not Complete Until the Driving Criterion is
    Established in the Field
  • Structural Considerations can be Critical
  • But Structural Properties Known in Advance of
    Pile Installation
  • Factor of Safety (Resistance Factor) Dependent on
    Methods of Capacity Determination and
    Installation Quality Control

7
I Will Discuss the Basis for the Design.Since
early in the 19th Century a Design Approach
Called Allowable Stress Design (ASD) Has Been
Used. Will Discuss the Fundamental Basis for ASD
8
GENERAL STRUCTURAL DESIGNPROCESS
9
ASD HISTORICAL BACKGROUND
  • Rational Analyses Appeared Early 1800s
  • Analysis Linear Elastic Based - Steel
  • Well Developed by Late 1800
  • Basic Concept Do not Exceed Yield Stress
  • Produced an Orderly Basis for Design

10
ASD BASIS
STRESS
?y
?a
STRAIN
Define an ALLOWABLE STRESS ?a C ?y For Steel
Beams C 0.4 to 0.66
11
ALLOWABLE STRESS DESIGN
  • Safe Stress or Load Permitted in Design
  • Allowable Stress Determined by Dividing the Yield
    Strength of the Material by a Factor of Safety
    that is More than One
  • The Factor Provides Safety Margin
  • Factor Selected by Experience

12
STRENGTH DESIGN
  • Not All Structures Have Linear Load-Stress (or
    Load-Strength) Relationship
  • Example Columns
  • Behavior Understood by Late 1800s
  • Strength Non-Linear and Dependent on Slenderness
    Ratio and Can Be Calculated
  • Factor of Safety Introduced
  • Universally Used in Geotechnical Design
  • Still Called ASD

13
WHY LRFD?
  • First Adopted by ACI Building Code 1956 in an
    Appendix
  • Adopted 1963 as Equal to ASD
  • Strength Design Necessary for Particularly for
    Concrete Columns
  • Desirable to Split Safety Margin on Both Loads
    and Strength
  • Adopted Different Factors on Different Load Types
  • Adopted in Practice in about Two Years
  • All Factors Determined Heuristically

14
  • ASD
  • ?Qi Rn/F.S.
  • LRFD
  • ??ij Qij ?k Rnk
  • Gravity Loads
  • ASD - D L
  • LRFD - ACI 1.2D 1.6L
  • LRFD - AASHTO 1.25D 1.75L

15
PROBABILITY RAISESITS UGLY HEAD
  • Concept First Proposed in 1969 by Cornell in ACI
    Journal Article
  • Extensive Research Developed Rational Load and
    Resistance Factors for Structural Elements
  • AISC Code Adopted LRFD mid-1980s
  • Ontario Bridge Code Adopted 1977
  • AASHTO Bridge Code Adopted LFD 1977
  • AASHTO Bridge Code Adopted LRFD after Extensive
    Research Project, 1994

16
STRENGTH AND LOAD DISTRIBUTION
17
STRENGTH MINUS LOAD DISTRIBUTION
18
UNDERSTAND THE LIMITATIONS
  • Load and Resistance Factors not Unique
  • Several Factors Selected Based on One Condition
  • Design Process Must Be Well-Understood by Code
    Developers
  • Strength Data May Be Dependent on Undefined
    Variables

19
FROM THE HANDLINGOF THE LOADS ALONE ITIS A BIG
IMPROVEMENTOVER ASD
20
LOAD FACTORS FOR SELECTED CODES
Code Dead Load Live Load
AASHTO Bridge Code 1.25 1.75
ACI 318-02 1.20 1.60
AISC ANSI 577 1.20 1.60
Ontario Bridge Code 1.20 1.40
Canadian Code 1.20 1.60
Euro Code 1.35 1.50
Danish Code 1.00 1.30
Australian Code 1.25 1.50
API Code 1.30 1.50
21
ButThere Are Many LoadsAnd Load
CombinationsFor Instance,Two Important OnesIn
AASHTOStr I 1.25D 1.75 L Str IV 1.50 D
22
COMPARE F.S. WITH ? FOR DIFFERENT L/D RATIOS
  • ?D QD ?L QL ? Rn ( QD QL)F.S. Rn
  • ?D ?LQL/QD ? (1 QL/QD)F.S.
  • (?D ?LQL/QD)/ (1 QL/QD) ? (F.S.)

23
Resistance Factors as Function of L/D at
F.S.2.0 for Several Different Codes
24
AASHTO Equivalent Resistance Factors for
Given F.S., Function of L/D Dead L.F. 1.25 Live
L.F. 1.75
25
F.S.1.40
F.S.1.60
F.S.2.00
F.S.2.50
F.S.3.00
F.S.3.75
F.S.5.00
Str IV
Str I
Str I 1.25 D 1.75 L Str IV 1.50 D
26
(No Transcript)
27
(No Transcript)
28
SUMMARY
  • LRFD Is an Improvement Based on the Split Safety
    Margins Alone
  • Both between Load Types and Strength
  • Load and Resistance Factors non-Unique
  • Clearly Written, Unique Codes Necessary

29
SUMMARY (Cont.)
  • Probabilistic Load and Resistance Factor
    Determination Attractive
  • Probabilistic Factors Must Be Based on a Clear
    Understanding of the Design Process
  • Must Have Good Data!!!!!!
  • Designer Neednt Know How to Obtain Resistance
    Factors from Probability

30
FOUNDATION DESIGN PROCESS
  • Combined effort of geotechnical, structural and
    construction engineer
  • Local contractor may provide input
  • Large design capacity increases are often
    possible for driven piles
  • Both design and construction practice need
    improvement

31
FOUNDATION DESIGN PROCESS
Establish requirements for structuralconditions
and site characterization
Obtain general site geology
Collect foundation experience from the area
Plan and execute subsurface investigation
32
FOUNDATION DESIGN PROCESS
  • Preliminary loads defined by structural engineer
  • Loads will probably be reduced as design advances
  • Improved (final) loads must be used in final
    design

33
FOUNDATION DESIGN PROCESS
Plan and execute subsurface investigation
Evaluate information and select foundation system
Deep Foundation
Shallow Foundation
34
Foundation Design Process
Deep Foundation
Drilled Shaft
Driven Pile
Select Drilled Shaft
35
Foundation Design Process
Drilled Shaft
Select Shaft Type and Factor of Safety or
Resistance Factor
By Static Analysis, Estimate Unit Shaft Friction
and End Bearing
Select Cross Section and Length for Required
Capacity (Structural Engineer?)
36
Foundation Design Process
Prepare Plans and Specifications
Select Contractor
Verify Shaft Constructability and Capacity
Install and Inspect Production Shafts
37
QUESTION
  • Where does the Geotechnical Strength Variability
    come from?

38
Foundation Design Process
Deep Foundation
Drilled Shaft
Driven Pile
Select Driven Pile
39
FOUNDATION DESIGN PROCESS
Define Subsurface Conditions Select Capacity
Determination Method Select Quality Control
Procedures Determine Safety Factor or Resistance
Factor
Determine Working Loads and Loads Times Factor of
Safety Gives Required Ultimate or Nominal
Resistance for ASD For LRFD Determine Loads Times
Load Factors Get Factored Load - Divide by ?
Factor to Get Required Nominal Resistance
Penetration Not Well Defined
Penetration Well Defined
40
DRIVEN PILE DESIGN PROCESS
Penetration Well Defined
  • Pile Depth is Defined by a Dense Layer or Rock
  • The Length is Easily Selected Based on the Depth
    to the Layer

41
FOUNDATION DESIGN PROCESS
Select Pile Type and Size Determine Unit Shaft
Friction and End Bearing With Depth Estimate
Required Pile Length Do a Preliminary Drivability
Check
42
1DRIVEN PILE DESIGN PROCESSGENERAL
  • Capacity Verification Method
  • More Accurate Methods Justify a Smaller Safety
    Factor (Larger Resistance Factor)
  • Choices
  • Static load test
  • Dynamic test
  • Wave equation
  • Dynamic formula

43
DRIVEN PILE DESIGN PROCESSGENERAL
  • Q. C. Method
  • As Q.C. is Improved, Factor of Safety can
    decrease (Resistance Factor can Increase)
  • e.g., Better Capacity Determination Method
  • Increased Percentage of Piles Statically or
    Dynamically Tested
  • Critical piles tested

44
DRIVEN PILE DESIGN PROCESSGENERAL
  • Make Pile Static Capacity Prediction
  • Predict Unit Shaft Friction and End Bearing with
    Depth
  • Prediction Should Be Best Possible
  • Do Not Adjust with Resistance Factor
  • Note Any Minimum Depth Requirements
  • Pile Size Determined With Knowledge of Loads

45
DRIVEN PILE DESIGN PROCESSGENERAL
  • Pile Size Selection Should Consider Loads
  • Structural Limit State Must Also Be Considered
    Lateral Loads
  • Close Structural and Geotechnical Coordination
    Necessary
  • Maybe Pile Size Selection by Structural Engineer
    Foundation Engineer
  • Length Will Be Obvious if Piles to Rock

46
DRIVEN PILE DESIGN PROCESS
  • At this stage a proposed foundation design is
    complete
  • All other strength limit states must be checked
  • Drivability must be checked
  • All serviceability limit states also checked

47
DRIVEN PILE DESIGN PROCESS
Evaluate Drivability
Design Satisfactory?
NO
YES
Prepare plans and specifications
Select Contractor
48
DRIVEN PILE DESIGN PROCESS
  • Drivability usually evaluated by wave equation
  • Must satisfy driving stress requirement
  • Blow count must be reasonable
  • Hammer and driving system assumed
  • If dynamic formula used it will determine
    required blow count
  • Dynamic formula will not detect excessive driving
    stresses

49
DRIVEN PILE DESIGN PROCESS
Change Driving System
Select Contractor
Contractor Advises Proposed Hammer and Driving
System
Perform Drivability Analysis
Hammer Satisfactory?
NO
50
DRIVEN PILE DESIGN PROCESS
  • This is the same as above except the driving
    system is now known (given by Contractor)

51
DRIVEN PILE DESIGN PROCESS
Hammer Satisfactory?
YES
Set driving criteria
Drive test pile to criteria
Verify test pile capacity
NO
Capacity/stress satisfactory?
52
DRIVEN PILE DESIGN PROCESS
Capacity/stress satisfactory?
NO
YES
Drive production piles
Undertake construction control and monitor
installation
Resolve pile installation problems and
construction procedures
53
QUESTION
  • Where does the Geotechnical Strength Variability
    come from?

54
THE END
Write a Comment
User Comments (0)
About PowerShow.com